BLD-Final | 2/7/2013 | 2/8/2013 | 2/8/2013 | A | PASS |
Mike Jordan
|
|
|
darin Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 2/7/2013 | 2/7/2013 | 2/7/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Conference | 2/5/2013 | 2/6/2013 | 2/6/2013 | A | CANC |
Troy Cobbley
|
|
|
Wrong permit number called in.
|
FIRE-Final Inspection | 2/5/2013 | 2/6/2013 | 2/6/2013 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given with Scott Arellano's permission until the new fire sprinkler permit has been addressed.
|
BLD-Final | 2/5/2013 | 2/6/2013 | 2/6/2013 | P | PART |
Mike Jordan
|
|
|
Darren Phone #: ###-####. Ok for temp occ. Will be ok for perm occ. once fire/life/safety singns perm.
|
FIRE-Conference | 2/5/2013 | 2/5/2013 | 2/5/2013 | P | DONE |
Troy Cobbley
|
|
|
Darren and I went over life safety requirements. All life safety items are ok except for what appears to be blocked upright sprinkler heads at new mechanical penatrations. This work was outside of the sprinkler contractors scope of work.
|
BLD-Conference | 2/1/2013 | 2/4/2013 | 2/4/2013 | A | DONE |
Mike Jordan
|
|
|
darren Phone #: ###-####
|
BLD-Conference | 1/14/2013 | 1/15/2013 | 1/15/2013 | A | DONE |
Mike Jordan
|
|
|
darren - call 30 mins prior to meet Phone #: ###-####
|
BLD-Framing/Rough-in | 11/30/2012 | 11/30/2012 | 11/30/2012 | P | PASS |
Mike Jordan
|
|
|
Steel stud - Steve Phone #: ###-####. Interior stell stud walls for new washbay and compressor room ok.
|