Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberBLD12-03142
StatusFinaled
Name KENLEY INC
Site Address 2562 E STARCREST DR
Project Name 
Customer Number 
ePlanReviewNo
Description
"PLAN MODIFICATION FOR REDESIGNED BALCONY RAILING" THIS STRUCTURE WILL BE FIRE SPRINKLERED AS AN ALTERNATE TO PROVIDING ADEQUATE FIRE DEPARTMENT VEHICHLE ACCESS. Permit for the construction of a new 3977 sq. ft., two story (Garage at grade level 1363 sq. ft., second story 2612 sq. ft.) single family dwelling with 2 bedrooms, 2 bathrooms, approximately 252 sq. ft. of covered patio/porch and a 1363 sq. ft. attached garage per the approved plans, plan review report and any notations. R-1C zoning and setbacks per planning. DEFERRED SUBMITTALS ARE BEING ALLOWED FOR THE SECOND STORY GLASS GUARDRAIL. THE ENGINEERED DESIGN IS REQUIRED TO BE SUBMITTED TO AND APPROVED BY THE BUILDING DEPARTMENT PRIOR TO THE INSTALLATION OF THE GUARDRAIL. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/7/201311/7/201311/8/2013PPASS
DetailsDave Hannah
mike Phone #: ###-####
DOC - Permit Finaled11/8/201311/8/201311/8/2013APASS
DetailsDave Hannah
BLD-Final11/1/201311/1/201311/4/2013PNR
DetailsDave Hannah
DEB Phone #: ###-####
BLD-Final10/31/201311/1/201311/1/2013ANR
DetailsDave Hannah
DEB Phone #: ###-#### needs hill side final first
BLD-Other9/9/20139/9/20139/10/2013PPASS
DetailsDave Hannah
Deb -this is to check for fire treated wood - Steve will be on site to help Phone #: ###-####
BLD-Other9/6/20139/9/20139/9/2013ANR
DetailsDave Hannah
DEB- TREATED WOOD IN DRIVEWAY Phone #: ###-####
BLD-Framing/Rough-in8/13/20138/14/20138/14/2013APART
DetailsJim Sly
fire rated soffits - deb Phone #: ###-####
Looked at 1x6 tongue and groove cedar and found stamps on the back of them. The stamps were smeared and un-readable. Should be fire rated treated. I talked to Deb about this and maybe we can get an invoice of what was ordered. Also told her if her soffit vents have not yet been approved by the City........that needs to be done. Don't know where treated cedar will be installed or even if it's been approved by Fire Dept. Deb to talk to Dave about this
BLD-Framing/Rough-in6/20/20136/20/20136/20/2013APASS
DetailsDave Hannah
Deb Jones Phone #: ###-####
BLD-Framing/Rough-in6/19/20136/19/20136/20/2013PPASS
DetailsDave Hannah
Deb Jones Phone #: ###-####
BLD-Wall Bracing6/14/20136/14/20136/14/2013PPASS
DetailsDave Hannah
deb Phone #: ###-####
BLD-Footing5/2/20135/3/20135/3/2013APASS
DetailsDave Hannah
dave Phone #: ###-####
BLD-Framing/Rough-in4/4/20134/5/20134/5/2013ANR
DetailsDave Hannah
Jerimiah Phone #: ###-####
BLD-Footing3/13/20133/14/20133/14/2013APART
DetailsTony Young
brent Phone #: ###-####,, interior slab ftgs
BLD-Foundation2/22/20132/25/20132/25/2013APART
DetailsTony Young
Brent Phone #: ###-####,,6" 4ft, 6" 6' and tall retaining walls ok per plan
BLD-Footing2/20/20132/21/20132/21/2013APASS
DetailsDave Hannah
Jeff Phone #: ###-####
BLD-Foundation2/14/20132/15/20132/15/2013APART
DetailsDave Hannah
jess Phone #: ###-#### lower wall ok to place concrete
BLD-Footing2/12/20132/12/20132/13/2013PPASS
DetailsDave Hannah
Jeff Phone #: ###-####
BLD-Foundation1/30/20131/30/20131/30/2013PPASS
DetailsDave Hannah
Brent Phone #: ###-####
BLD-Foundation1/24/20131/24/20131/24/2013PPART
DetailsTony Young
Brent Phone #: ###-####,, work in progress on retaining wall,, will cover and maybe pour Friday at 11am? then cover up for cure
BLD-Footing1/17/20131/18/20131/18/2013APART
DetailsDave Hannah
Brent Phone #: ###-#### first phase upper ftgs crew has ftgs covered and running heaters ok to place concrete
BLD-Footing1/16/20131/16/20131/16/2013PFAIL
DetailsDave Hannah
Brent- Phone #: ###-#### ground was frozen and needed to add verts