Information based on query as of Thursday, June 27, 2024.
Permit Information
Permit NumberBLD12-03273
StatusFinaled
Name EKC INC
Site Address 475 W PARKCENTER BLVD
Project NameHOLIDAY INN EXPRESS
Customer Number 
ePlanReviewNo
Description
(HOLIDAY INN EXPRESS) Interior and exterior remodel to an existing 81,264 square foot, six story, hotel building for a new hotel tenant. Work to include: Demolition work on the 1st story per plans; remove existing exterior sidewalk canopy and extend detached steel canopy with barrel framed extension; renovate lobby/reception areas and guest room finishes per plans; update the level of accessibility to (6) standard accessible rooms and (2) roll-in shower rooms; install new floor and wall finishes in compliance with chapter 8 of the 2009 IBC; replace existing lighting fixtures with new; plumbing and electrical work; and all other work per the approved drawings, the plan review report, and all applicable codes. A new Certificate of Occupancy with the new occupant load total is to be issued when completed and approved. NOTE: This building is fully fire sprinklered for area increase. Any alterations or modifications to the buildings Fire Sprinkler WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 as regulated by the Boise Fire Department. **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/29/20137/30/20137/30/2013APASS
DetailsJim Storey
joe Phone #: ###-####
BLD-Final7/26/20137/29/20137/29/2013ADEFR
DetailsJim Storey
joe Phone #: ###-####
FIRE-Final Inspection7/25/20137/26/20137/29/2013PPASS
DetailsForrest France
Fire life safety inspection passed after corrections made while on site.
FIRE-Final Inspection7/22/20137/23/20137/26/2013PNR
DetailsForrest France
Pending project related fire alarm
BLD-Final7/26/20137/26/20137/26/2013PDEFR
DetailsJim Storey
late afternoon - last possible -joe Phone #: ###-####
FIRE-Final Inspection7/15/20137/16/20137/16/2013ANR
DetailsForrest France
Project is not in condition for fire life safety final at this time. Finishes underway, project related fire alarm work incomplete.
FIRE-Final Inspection7/12/20137/15/20137/15/2013PCANC
DetailsTroy Cobbley
Cancel per Joe Phone #: ###-#### To be rescheduled for tomorrow morning.
FIRE-Conference6/20/20136/20/20136/20/2013ADONE
DetailsForrest France
Regarding cabinet and bracket heights for new and existing fire extinguishers.
FIRE-Final Inspection5/23/20135/24/20135/29/2013PDONE
DetailsForrest France
Intended for an on site conference
FIRE-Final Inspection5/24/20135/28/20135/28/2013PPART
DetailsForrest France
On site conference with the electrical contractor and general contractor regarding exit sign and EM lighting per IFC requirements. Discussed locations of areas to be included at the first through sixth floors, stair towers, and exit discharge.
BLD-Other5/24/20135/24/20135/24/2013PPASS
DetailsJim Storey
james Phone #: ###-#### fire stopping ok on sharts ada rm's at pt repair
BLD-Other5/20/20135/21/20135/21/2013APART
DetailsJim Storey
fire chase insp//James Phone #: ###-#### corewall ok and firestopping in progress/ soffit need 5/8 on coridor side at entrys/ plm clean out brass cap and fire stop anular space.
BLD-Concrete5/15/20135/15/20135/15/2013PPASS
DetailsJim Storey
Joe Phone #: ###-#### pt pour back of slab ok to proceed
FIRE-Sprinkler Rough-in5/13/20135/13/20135/13/2013APART
DetailsForrest France
Fire sprinkler work at the first floor lobby sheetrock soffits and grid ceiling areas okayed for cover.
BLD-Conference5/3/20135/6/20135/6/2013AFAIL
DetailsJim Storey
joe Phone #: ###-#### c/.n 32 clear with ada doors in ada rm's
FIRE-Conference4/25/20134/29/20134/29/2013ADONE
DetailsForrest France
On site conference with contractor regarding fire sprinkler work, existing coverage issues, and new manual pull station locations.
BLD-Footing4/22/20134/22/20134/22/2013PPART
DetailsMike Jordan
joe Phone #: ###-####. Column pad footings for new porte cochere Per RFI from stapley engineering. Will have have special inspection.
BLD-Conference4/11/20134/11/20134/11/2013PPASS
DetailsJim Storey
james Phone #: ###-#### pt coulpers w/ cable protection in place. ok to cover.
BLD-Other3/29/20134/1/20134/1/2013APART
DetailsJim Storey
post tension cable insp//James Phone #: ###-#### work ok to proceed e mail with engineer ok as well as elonggations discused w/si on site.
BLD-Conference3/18/20133/18/20133/18/2013PPASS
DetailsJim Storey
Joe Phone #: ###-####
BLD-Other2/19/20132/19/20132/19/2013PPASS
DetailsJim Storey
Fire proofing inspection please-Joseph Phone #: ###-####
FIRE-Conference2/1/20132/4/20132/4/2013ADONE
DetailsForrest France
Regarding fire alarm and sprinkler trade permits.
FIRE-Conference1/30/20131/30/20131/30/2013PDONE
DetailsForrest France
BLD-Conference1/30/20131/30/20131/30/2013PPART
DetailsJim Storey
call Joe Phone #: ###-#### walked job site/ arch to respond to shaft conditions found.
BLD-Conference1/29/20131/30/20131/30/2013ADEFR
DetailsJim Storey
call Joe Phone #: ###-####