BLD-Final | 7/29/2013 | 7/30/2013 | 7/30/2013 | A | PASS |
Jim Storey
|
|
|
joe Phone #: ###-####
|
BLD-Final | 7/26/2013 | 7/29/2013 | 7/29/2013 | A | DEFR |
Jim Storey
|
|
|
joe Phone #: ###-####
|
FIRE-Final Inspection | 7/25/2013 | 7/26/2013 | 7/29/2013 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection passed after corrections made while on site.
|
FIRE-Final Inspection | 7/22/2013 | 7/23/2013 | 7/26/2013 | P | NR |
Forrest France
|
|
|
Pending project related fire alarm
|
BLD-Final | 7/26/2013 | 7/26/2013 | 7/26/2013 | P | DEFR |
Jim Storey
|
|
|
late afternoon - last possible -joe Phone #: ###-####
|
FIRE-Final Inspection | 7/15/2013 | 7/16/2013 | 7/16/2013 | A | NR |
Forrest France
|
|
|
Project is not in condition for fire life safety final at this time. Finishes underway, project related fire alarm work incomplete.
|
FIRE-Final Inspection | 7/12/2013 | 7/15/2013 | 7/15/2013 | P | CANC |
Troy Cobbley
|
|
|
Cancel per Joe Phone #: ###-#### To be rescheduled for tomorrow morning.
|
FIRE-Conference | 6/20/2013 | 6/20/2013 | 6/20/2013 | A | DONE |
Forrest France
|
|
|
Regarding cabinet and bracket heights for new and existing fire extinguishers.
|
FIRE-Final Inspection | 5/23/2013 | 5/24/2013 | 5/29/2013 | P | DONE |
Forrest France
|
|
|
Intended for an on site conference
|
FIRE-Final Inspection | 5/24/2013 | 5/28/2013 | 5/28/2013 | P | PART |
Forrest France
|
|
|
On site conference with the electrical contractor and general contractor regarding exit sign and EM lighting per IFC requirements. Discussed locations of areas to be included at the first through sixth floors, stair towers, and exit discharge.
|
BLD-Other | 5/24/2013 | 5/24/2013 | 5/24/2013 | P | PASS |
Jim Storey
|
|
|
james Phone #: ###-#### fire stopping ok on sharts ada rm's at pt repair
|
BLD-Other | 5/20/2013 | 5/21/2013 | 5/21/2013 | A | PART |
Jim Storey
|
|
|
fire chase insp//James Phone #: ###-#### corewall ok and firestopping in progress/ soffit need 5/8 on coridor side at entrys/ plm clean out brass cap and fire stop anular space.
|
BLD-Concrete | 5/15/2013 | 5/15/2013 | 5/15/2013 | P | PASS |
Jim Storey
|
|
|
Joe Phone #: ###-#### pt pour back of slab ok to proceed
|
FIRE-Sprinkler Rough-in | 5/13/2013 | 5/13/2013 | 5/13/2013 | A | PART |
Forrest France
|
|
|
Fire sprinkler work at the first floor lobby sheetrock soffits and grid ceiling areas okayed for cover.
|
BLD-Conference | 5/3/2013 | 5/6/2013 | 5/6/2013 | A | FAIL |
Jim Storey
|
|
|
joe Phone #: ###-#### c/.n 32 clear with ada doors in ada rm's
|
FIRE-Conference | 4/25/2013 | 4/29/2013 | 4/29/2013 | A | DONE |
Forrest France
|
|
|
On site conference with contractor regarding fire sprinkler work, existing coverage issues, and new manual pull station locations.
|
BLD-Footing | 4/22/2013 | 4/22/2013 | 4/22/2013 | P | PART |
Mike Jordan
|
|
|
joe Phone #: ###-####. Column pad footings for new porte cochere Per RFI from stapley engineering. Will have have special inspection.
|
BLD-Conference | 4/11/2013 | 4/11/2013 | 4/11/2013 | P | PASS |
Jim Storey
|
|
|
james Phone #: ###-#### pt coulpers w/ cable protection in place. ok to cover.
|
BLD-Other | 3/29/2013 | 4/1/2013 | 4/1/2013 | A | PART |
Jim Storey
|
|
|
post tension cable insp//James Phone #: ###-#### work ok to proceed e mail with engineer ok as well as elonggations discused w/si on site.
|
BLD-Conference | 3/18/2013 | 3/18/2013 | 3/18/2013 | P | PASS |
Jim Storey
|
|
|
Joe Phone #: ###-####
|
BLD-Other | 2/19/2013 | 2/19/2013 | 2/19/2013 | P | PASS |
Jim Storey
|
|
|
Fire proofing inspection please-Joseph Phone #: ###-####
|
FIRE-Conference | 2/1/2013 | 2/4/2013 | 2/4/2013 | A | DONE |
Forrest France
|
|
|
Regarding fire alarm and sprinkler trade permits.
|
FIRE-Conference | 1/30/2013 | 1/30/2013 | 1/30/2013 | P | DONE |
Forrest France
|
|
|
|
BLD-Conference | 1/30/2013 | 1/30/2013 | 1/30/2013 | P | PART |
Jim Storey
|
|
|
call Joe Phone #: ###-#### walked job site/ arch to respond to shaft conditions found.
|
BLD-Conference | 1/29/2013 | 1/30/2013 | 1/30/2013 | A | DEFR |
Jim Storey
|
|
|
call Joe Phone #: ###-####
|