Permit Information
Permit NumberBLD13-00004
StatusFinaled
Name MCALVAIN CONSTRUCTION INC
Site Address 401 W FRONT ST
Project NameMicrosoft Boise Sales Office
Customer Number 
ePlanReviewYes
Description
(MICROSOFT BOISE SALES OFFICE - 6TH STORY) (4-3-13 PLAN MODIFICATION TO CHANGE “STORAGE ROOM 6177” TO A TOILET AND SHOWER ROOM. WORK IS TO INCLUDE A TOILET, LAVATORY, BENCH, AND TRANSFER-TYPE SHOWER ACCESSIBLE TO THE DISABLED. NEW FLOOR AND WALL FINISHES WILL BE PROVIDED. A GYPSUM BOARD CEILING WILL BE CONSTRUCTED. A MINIMUM 70 CFM EXHAUST FAN DUCTED TO THE OUTSIDE IS REQUIRED. LOCKERS ARE NOT ALLOWED WITHIN THE ROOM.) (3-7-13 PLAN MODIFICATION TO CREATE A 224 SQUARE FOOT CONFERENCE ROOM, A 83 SQUARE FOOT STORAGE ROOM, AND A 56 SQUARE FOOT STORAGE ROOM IN SAME LOCATION AS A PREVIOUSLY APPROVED 344 SQUARE FOOT CONFERENCE ROOM. A DOUBLE LEAF DOOR SERVING A TRAINING ROOM WILL ALSO BE RECESSED.) Fire sprinklers used for story and height increase. To remodel about 4,426 square feet of an existing 13,089 square foot whole floor tenant space located on the 14,191 square foot 6th story of an existing building. A higher security 7,643 square foot controlled access office area of this tenant space will egress through the lower security controlled access meeting room portion of this tenant space. The controlled access devices are not allowed to obstruct egress. Work is to include interior nonbearing walls, interior doors, an interior window, suspended acoustical ceilings, suspended gypsum board ceilings, and finishes. Several floor outlets will be provided and are required to be properly fire stopped for at least 1-hr. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/6/20135/7/20135/7/2013PPASS
DetailsDave Hannah
Tom Phone #: ###-####
FIRE-Final Inspection5/6/20135/7/20135/7/2013PPASS
DetailsForrest France
Fire life safety inspection passed.
FIRE-Conference4/23/20134/24/20134/24/2013ADONE
DetailsForrest France
On site discussion with contractor regarding life safety issues including exit signs, EM lights, PFE's.
BLD-Ceiling Grid Inspection4/12/20134/15/20134/17/2013ANR
DetailsDave Hannah
tom Phone #: ###-####
BLD-Other4/2/20134/3/20134/3/2013APASS
DetailsDave Hannah
fireblocking - tom Phone #: ###-#### patching fireproofing
FIRE-Conference3/21/20133/21/20133/22/2013PDONE
DetailsForrest France
Regarding fire sprinkler coverage
BLD-Framing/Rough-in3/15/20133/15/20133/19/2013PPASS
DetailsDave Hannah
tom Phone #: ###-####
BLD-Framing/Rough-in3/12/20133/13/20133/14/2013APART
DetailsDave Hannah
tom Phone #: ###-#### ok to cover top of walls in conf rooms so they can build soffits
BLD-Conference3/1/20133/1/20133/4/2013PDONE
DetailsDave Hannah
tom Phone #: ###-#### needs to resubmit new floor plans