Permit NumberBLD13-00021
StatusFinaled
Name ALTA CONSTRUCTION
Site Address 12601 W BRIDGER ST
Project NameBoise Center West IPC
Customer Number 
ePlanReviewNo
Description
(Idaho Power - Phase 5) FPP PROJECT INSPECTION # BLD 794-9494 FIR 794-9483 ELE 794-1379 PLM 794-9476 MEC 794-9461 Remove walls and ceillings to create new office, bathrooms,breakrooms,trainingrooms A3 meetting rooms with mechanical and ele.spaces.mezzanine under bld13-00028 . Open office partition in rm 533. Ada per the aproved plan. All fire spk. and alarm permits must be obtained thru the fire planreview dept. Mezzanine bld13-00028 is a stand alone permit to be inspected with the FPP insp. team. A plan for occupance phasing is on A1.00 The wheelchair lift is not a code required access for the mezzanine less than 3000 sqft. UL Panic Hardware for controled egress from time that building was constructed is code compliant. Existing access controlled egress hardware to remain and is compliant under the original code; all new door hardware must meet current code. This building is fully fire sprinklered with an approved fire alarm system. Any modifications to the building fire protection systems will require separate permits; as regulated by the Fire Department.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/30/20178/30/20178/31/2017PPASS
DetailsJim Sly
DOC - Permit Finaled8/31/20178/31/20178/31/2017PPASS
DetailsJim Sly
BLD-Aging Inspection8/30/20178/30/20178/30/2017 CANC
DetailsJim Sly
FIRE-Final Inspection4/17/20174/18/20174/18/2017APASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection8/29/20138/30/20138/30/2013AFAIL
DetailsTroy Cobbley
Life safety can be passed when the project related fire alarm permit has been finaled.
BLD-Final8/29/20138/29/20138/29/2013PNR
DetailsJim Storey
BLD-Conference7/26/20137/26/20137/26/2013APART
DetailsJim Storey
wing walls and ramp to resolve transition of lower floor to wheelchair lift access.
BLD-Concrete7/22/20137/23/20137/23/2013APASS
DetailsJim Storey
grout ok to back pour floor/ raised floor ok to cover.
BLD-Ceiling Grid Inspection7/17/20137/18/20137/18/2013APASS
DetailsJim Storey
BLD-Framing/Rough-in7/10/20137/10/20137/10/2013PFAIL
DetailsJim Storey
need beam stifners and top chord braces per engineering/ si insp for new windows upon p&z aproval reinsp. required.
BLD-Framing/Rough-in5/29/20135/30/20135/30/2013APASS
DetailsJim Storey
floor framing water closet west end ok .
FIRE-Final Inspection5/16/20135/16/20135/17/2013PPART
DetailsTroy Cobbley
Life safety is passed for the area clouded in red pen in the area dated "5/15" in the orange high-lited area. Egress approved by Romeo for this area.
BLD-Conference5/15/20135/16/20135/16/2013PPASS
DetailsJim Storey
jason ###-#### offices north as well as documented exit path ok to occupy
BLD-Final5/14/20135/15/20135/15/2013PDEFR
DetailsJim Storey
walk 1-b for occ of area.5/16
FIRE-Final Inspection5/14/20135/15/20135/15/2013ACANC
DetailsTroy Cobbley
Jeremy wants to reschedule for tomorrow - Phone #: ###-####
BLD-Final5/2/20135/2/20135/2/2013PPASS
DetailsJim Storey
temp occ of phase 1b call center area. pdf file saved for area exiting plan aproved by fire dept and planreviw for call center temp occ.
FIRE-Final Inspection5/2/20135/2/20135/2/2013PPART
DetailsTroy Cobbley
The exiting from the phase of construction dated "5/3" and highlighted in purple is approved. The life safety in this area is passed as well. This area is to the immediate west of the call center.
FIRE-Final Inspection4/30/20135/1/20135/1/2013AFAIL
DetailsTroy Cobbley
Waiting for fire dept approval of the exiting from the phase of construction dated "5/3" and highlighted in purple. This area is to the immediate west of the call center.
BLD-Conference4/29/20134/29/20134/29/2013PPASS
DetailsJim Storey
ceilling ok west rm for temp exit phase 1 b ok
BLD-Final4/23/20134/23/20134/23/2013PPASS
DetailsJim Storey
Phase 1 A ok for occupancy
FIRE-Final Inspection4/22/20134/23/20134/23/2013APART
DetailsTroy Cobbley
Life safety is passed in Area "1A" is ok to occupy as far as Fire is concerned. Emergency lighting is actually every light in the building and not scattered as per plan.
BLD-Other4/16/20134/17/20134/17/2013APART
DetailsJim Storey
need mech insp above ceilling/ remove papper on com lines in ceilling/ ok to drop tile will spot check// phase one temp exit signage above west door and clear exit path out of bldg..
BLD-Conference4/3/20134/5/20134/5/2013APASS
DetailsJim Storey
9:00 am meeting w/ idaho power had idaho power rep./ alta const rep and mec/plm/ele to review phased occ to area 1 fire will be getting aprovals from ronero sub mital should be in route by eary next week // occ to be set for 4/24/2013.
BLD-Conference4/3/20134/4/20134/4/2013APASS
DetailsJim Storey
complaint still working even though SWO is posted. bld13-000790 isued
BLD-Concrete3/27/20133/27/20133/27/2013PPASS
DetailsJim Storey
grout under mes col. ok for cover on bld13-00028 unable to add activty on that permit.
BLD-Conference3/19/20133/20/20133/20/2013APASS
DetailsJim Storey
reviewed job progress/ drop off plm and ele resubmitals.
BLD-Footing3/6/20133/6/20133/6/2013APART
DetailsJim Storey
ft holes and soil ok for mez