Permit Information
Permit NumberBLD13-00042
StatusFinaled
Name PATRICK AND JAMIE TIERNEY
Site Address 106 N CASTELLO PL
Project NameTierney Residence
Customer Number 
ePlanReviewNo
Description
WUI ZONE A, FIRE SPRINKLER SYSTEM REQUIRED, 7/22/15 ENGINEERED REVISONS TO DECK, **AJS**PLAN MODIFICATION FOR REVISED GRADING AND ENGINEERED RETAINING WALLS **AJS** 4/14/15Permit for the construction of a new 5,886 sq. ft. single family dwelling (first story 4,003 sq. ft., and 1,883 sq. ft. finished basement) with 6 bedrooms, 5.5 bathrooms, approximately 1,495 sq. ft. of covered patio/porch and a 1,178 sq. ft. attached garage per the approved plans, perscriptive energy, attached initial structural engineering, attached revised engineering, attached suplimental engineering, plan review report and any notations. A-1 zoning and setbacks per planning. AJS
Per a 01-19-1999 meeting of the Boise City Council and a follow up commentary letter dated 01-22-1999, item 7, the home is required to have a modified NFPA 13D fire sprinkler systems. In addition, to the NFPA 13D requirmenets all closets, bathrooms and attached garages are to be sprinklered. - TRF - A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 384-3946.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/3/201512/3/201512/3/2015PDONE
DetailsBob Archibald
All corrective provisions completed. Swimming pool will be finaled under its own permit #BLD13-03079.
BLD-Framing/Rough-in7/31/20158/3/20158/4/2015PPASS
DetailsDave Hannah
Deck framing/repair. Lee @###-####
BLD-Conference7/16/20157/16/20157/16/2015APEND
DetailsBob Archibald
Informed Nate and Patrick that 17 Fire Marshal approved soffit vents would be required
BLD-Conference7/8/20157/8/20157/9/2015APEND
DetailsBob Archibald
Dave Hannah and I met with Legacy, roofing contractors, structural engineer and current contractor in regard to requirements for structural engineering on patio deck,10 ft retaining wall and attic space ventilation requirements. Structural engineer will provide design calcs for both deck and retaining wall and roofing contractor to provide attic ridge vent dimensions for calculation of additional soffit or roof venting.
BLD-Other4/25/20144/25/20144/25/2014PPEND
DetailsBob Archibald
Correction Notice emailed to contractor.
BLD-Conference4/23/20144/23/20144/23/2014PDONE
DetailsBob Archibald
Site visit and review with all trades.
BLD-Final3/19/20143/20/20143/21/2014PFAIL
DetailsDave Hannah
david Phone #: ###-#### tempered glass front door hill side signoff
BLD-Energy code compliance10/17/201310/17/201310/18/2013PPASS
DetailsDave Hannah
David Phone #: ###-####
BLD-Framing/Rough-in10/15/201310/15/201310/15/2013PPASS
DetailsDave Hannah
david Phone #: ###-####
BLD-Foundation10/14/201310/15/201310/15/2013APASS
DetailsDave Hannah
retaining wall // Josh Phone #: ###-####
BLD-Wall Bracing10/15/201310/15/201310/15/2013APASS
DetailsDave Hannah
david Phone #: ###-####
BLD-Framing/Rough-in10/11/201310/14/201310/15/2013PPART
DetailsDave Hannah
david Phone #: ###-#### shear ok to cover ext but still needs a mec rough in inspection
BLD-Footing10/11/201310/14/201310/14/2013APASS
DetailsDave Hannah
after 10 // call before// footing for retaining wall // Josh Phone #: ###-####
BLD-Framing/Rough-in10/9/201310/10/201310/11/2013PNR
DetailsDave Hannah
david Phone #: ###-#### needs mec rough in and plumbing rough in
BLD-Framing/Rough-in10/8/201310/9/201310/9/2013PCANC
DetailsDave Hannah
dAVID hiCKS Phone #: ###-#### // cancelled per David, will call back to reschedule
BLD-Foundation10/7/201310/8/201310/8/2013APART
DetailsJim Sly
Josh Phone #: ###-####
OK to pour retaining wall located furthest East. Engineer Brian Sielaff OK'd # 5 horiz. in lieu of # 6 as shown on plan. Stamped letter verified. Called Mike J. He gave me a verbal that rebar in footing was OK'd by him.........He was waiting for approval of subgrade from Geotech.
BLD-Footing9/27/20139/27/20139/27/2013ANR
DetailsMike Jordan
josh Phone #: ###-####. East retaining wall per engineering and RFI. No concrete is allowed at this time. No approval on geotech report.
BLD-Footing9/24/20139/24/20139/24/2013PCANC
DetailsJim Sly
josh Phone #: ###-####
Canc by Contr.
BLD-Foundation6/27/20136/28/20136/28/2013APASS
DetailsDave Hannah
found wall//Josh Phone #: ###-####
BLD-Other6/14/20136/17/20136/18/2013APART
DetailsDave Hannah
early am please//rebar//Josh Phone #: ###-#### first wall poor ok
BLD-Footing6/11/20136/11/20136/12/2013PPASS
DetailsDave Hannah
Josh Phone #: ###-####
BLD-Footing6/10/20136/11/20136/11/2013ANR
DetailsDave Hannah
Josh Phone #: ###-####
BLD-Footing6/5/20136/6/20136/6/2013APART
DetailsDave Hannah
Josh Phone #: ###-#### basement ftgs and garage ftgs ok