BLD-Final | 3/20/2013 | 3/21/2013 | 3/21/2013 | A | PASS |
Dave Hannah
|
|
|
Rich-Please call prior to inspection Phone #: ###-####
|
DOC - Permit Finaled | 3/21/2013 | 3/21/2013 | 3/21/2013 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 3/21/2013 | 3/21/2013 | 3/21/2013 | A | PASS |
Forrest France
|
|
|
Fire alarm work completed under FIR13-00123. Fire life safety passed.
|
FIRE-Conference | 3/15/2013 | 3/15/2013 | 3/15/2013 | A | DONE |
Forrest France
|
|
|
On site meeting with Rich from Govt. buildings, T. Gainor and J. Blais regarding conditions per IFC for delayed egress. Verified new exit signs and EM lighting have been installed per previous inspection. Determined tie in to the FA system is also required unless verification of an alternate approval is provided.
|
FIRE-Final Inspection | 3/14/2013 | 3/14/2013 | 3/14/2013 | P | FAIL |
Forrest France
|
|
|
Missing exit signs per plan red-lines, provide EM lighting at the new door, must meet IFC conditions for delayed egress.
|
BLD-Framing/Rough-in | 1/18/2013 | 1/22/2013 | 1/22/2013 | A | PART |
Bob Archibald
|
|
|
rich Phone #: ###-#### please call 30 min before going out Framing adjacent to reception desk approved for cover
|