BLD-Final | 1/13/2016 | 1/13/2016 | 1/13/2016 | P | PASS |
Jim Storey
|
|
|
OK if you do this one at the end of the day per /// John Phone #: ###-####
|
BLD-Final | 1/11/2016 | 1/12/2016 | 1/12/2016 | P | NR |
Jim Storey
|
|
|
John Phone #: ###-####
|
FIRE-Final Inspection | 1/11/2016 | 1/12/2016 | 1/12/2016 | A | PASS |
Jim Page
|
|
|
Previously noted items addressed/repaired. Fire sprinkler inspections complete, fire alarm inspections complete. Life fire safety passed/complete.
|
BLD-Final | 12/29/2015 | 12/29/2015 | 12/29/2015 | P | PART |
Jim Storey
|
|
|
John Phone #: ###-#### fd/ pipe protection/at lundry rm/ mech rm/firelite glazing at 2 hr/exteriot complet expation joint and misc. penatrations. fire door and controled exits
|
FIRE-Final Inspection | 12/28/2015 | 12/29/2015 | 12/29/2015 | A | PART |
Jim Page
|
|
|
Contractor requesting TCO, fire sprinklers are complete, fire alarms have been tested and verified. Alarm contractor needs to install weather proof boxes on the Audio/Visual devices in the restrooms with showers (boxes are on order and will be installed when received). Site fire alarm system is monitored. Life fire safety inspection performed, fire extinguishers are in place, verified path of travel for emergency egress, verified egress lighting including exit discharge landings, door hardware to be installed on doors that are missing the hardware (magnet release hardware/windows). Life fire safety can be finaled after weather proof boxes are installed on A/V devices/FIR permit for alarms is finaled as well as the installation of missing door hardware. TCO authorized for moving in of furniture and employee training, no overnight occupancy for H wing allowed under this TCO, per conversation with Scott Arellano,
|
BLD-Ceiling Grid Inspection | 10/28/2015 | 10/28/2015 | 10/28/2015 | P | PASS |
Jim Storey
|
|
|
John Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 10/15/2015 | 10/16/2015 | 10/16/2015 | P | PASS |
Jim Storey
|
|
|
John Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 9/21/2015 | 9/22/2015 | 9/22/2015 | A | PASS |
Jim Storey
|
|
|
John Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 9/11/2015 | 9/14/2015 | 9/14/2015 | A | FAIL |
Jim Storey
|
|
|
John Phone #: ###-#### clips missing/ holes thru ceilling need fire rated/ remove wood
|
BLD-Ceiling Grid Inspection | 9/4/2015 | 9/8/2015 | 9/8/2015 | P | PASS |
Phil Shearer
|
|
|
Paul Phone #: ###-#### H L-Wing
|
BLD-Ceiling Grid Inspection | 9/4/2015 | 9/4/2015 | 9/4/2015 | P | FAIL |
Phil Shearer
|
|
|
H L-Wing; Paul Phone #: ###-####. penetrations thruogh fire walls.
|
BLD-Framing/Rough-in | 8/17/2015 | 8/18/2015 | 8/18/2015 | A | PASS |
Jim Storey
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 8/17/2015 | 8/17/2015 | 8/17/2015 | P | NR |
Jim Storey
|
|
|
John Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 8/7/2015 | 8/10/2015 | 8/10/2015 | A | PASS |
Jim Storey
|
|
|
1st floor; John Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 8/6/2015 | 8/7/2015 | 8/7/2015 | A | DEFR |
Jim Storey
|
|
|
1st floor; John Phone #: ###-#### monday am
|
BLD-Framing/Rough-in | 8/4/2015 | 8/4/2015 | 8/4/2015 | P | PART |
Jim Storey
|
|
|
John// ceiling framing in corridor- H building-2nd floor Phone #: ###-#### need fire stop listing for ele at 2 hr
|
BLD-Framing/Rough-in | 7/23/2015 | 7/24/2015 | 7/24/2015 | A | PASS |
Jim Storey
|
|
|
john Phone #: ###-####
|
BLD-Framing/Rough-in | 7/23/2015 | 7/23/2015 | 7/23/2015 | P | NR |
Jim Storey
|
|
|
john Phone #: ###-####
|
BLD-Framing/Rough-in | 7/21/2015 | 7/22/2015 | 7/22/2015 | A | PASS |
Jim Storey
|
|
|
to cover for second floor // John Phone #: ###-#### west side ok
|
BLD-Wall cover | 7/20/2015 | 7/21/2015 | 7/21/2015 | A | FAIL |
Jim Storey
|
|
|
3rd floor; John Phone #: ###-#### rebuild 2 hr wall to meet listting
|
BLD-Framing/Rough-in | 7/20/2015 | 7/20/2015 | 7/20/2015 | P | PART |
Jim Storey
|
|
|
3rd floor; John Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/16/2015 | 7/17/2015 | 7/17/2015 | A | PASS |
Jim Storey
|
|
|
John Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/16/2015 | 7/16/2015 | 7/16/2015 | P | NR |
Jim Storey
|
|
|
John Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/13/2015 | 7/14/2015 | 7/14/2015 | P | PASS |
Jim Storey
|
|
|
2nd floor; John Phone #: ###-#### rooms only ok
|
BLD-Energy code compliance | 7/6/2015 | 7/7/2015 | 7/7/2015 | A | PASS |
Jim Storey
|
|
|
3rd floor; John Phone #: ###-####
|
BLD-Framing/Rough-in | 7/6/2015 | 7/7/2015 | 7/7/2015 | A | PASS |
Jim Storey
|
|
|
3rd floor; John Phone #: ###-####
|
BLD-Framing/Rough-in | 6/30/2015 | 6/30/2015 | 6/30/2015 | P | PASS |
Jim Storey
|
|
|
John--- 2nd floor, H wing Phone #: ###-#### reviewed 90 min door/jamb walls
|
BLD-Framing/Rough-in | 6/23/2015 | 6/23/2015 | 6/24/2015 | P | PASS |
Jim Storey
|
|
|
2nd floor; John Phone #: ###-#### drops above doors
|
BLD-Energy code compliance | 6/19/2015 | 6/22/2015 | 6/22/2015 | P | PASS |
Jim Storey
|
|
|
2nd floor; John Phone #: ###-####
|
BLD-Framing/Rough-in | 6/18/2015 | 6/19/2015 | 6/19/2015 | P | PASS |
Jim Storey
|
|
|
2nd floor; John Phone #: ###-#### rm walls ok
|
BLD-Ceiling Grid Inspection | 6/18/2015 | 6/18/2015 | 6/18/2015 | P | PASS |
Jim Storey
|
|
|
1st floor; John Phone #: ###-####
|
BLD-Framing/Rough-in | 6/12/2015 | 6/12/2015 | 6/12/2015 | P | PART |
Tony Young
|
|
|
Wall first half of second floor // John Phone #: ###-####,, see prior notes
|
BLD-Framing/Rough-in | 6/11/2015 | 6/12/2015 | 6/12/2015 | A | PART |
Tony Young
|
|
|
Wall first half of second floor // John Phone #: ###-####,, ok to one side,, need to add layer on back side of double wall and fire caulk penetrations
|
BLD-Final | 6/11/2015 | 6/12/2015 | 6/12/2015 | P | CANC |
Jim Storey
|
|
|
JC// D commons Phone #: ###-####
|
BLD-Framing/Rough-in | 6/11/2015 | 6/11/2015 | 6/11/2015 | P | PART |
Tony Young
|
|
|
John-1st floor-south side Phone #: ###-####,, ceiling ok now
|
BLD-Ceiling Grid Inspection | 6/9/2015 | 6/10/2015 | 6/10/2015 | P | PART |
Jim Storey
|
|
|
John// 1st floor Phone #: ###-#### all but ref line set ceilling fire stop ok to cover.
|
BLD-Framing/Rough-in | 6/9/2015 | 6/10/2015 | 6/10/2015 | P | PART |
Jim Storey
|
|
|
John// 2nd floor Phone #: ###-#### firestoppimg top plate ceilling penatrations
|
BLD-Ceiling Grid Inspection | 6/9/2015 | 6/9/2015 | 6/9/2015 | P | FAIL |
Jim Storey
|
|
|
To cover 1st floor // John Phone #: ###-####
|
BLD-Framing/Rough-in | 5/28/2015 | 5/28/2015 | 5/28/2015 | P | PASS |
Jim Storey
|
|
|
basement and first floor of H wing // John Phone #: ###-#### plm 2nd floor floor fire stopping ok also,
|
BLD-Ceiling Grid Inspection | 5/27/2015 | 5/27/2015 | 5/27/2015 | P | PART |
Jim Storey
|
|
|
Garth// H basement Phone #: ###-####
|
BLD-Framing/Rough-in | 5/20/2015 | 5/21/2015 | 5/21/2015 | A | PART |
Jim Storey
|
|
|
Second floor fire walls H wing - John Phone #: ###-####
|
BLD-Energy code compliance | 4/28/2015 | 4/29/2015 | 4/29/2015 | A | PASS |
Jim Storey
|
|
|
Insulation // John Phone #: ###-#### rm only east side 1st floor ok
|
BLD-Framing/Rough-in | 4/23/2015 | 4/24/2015 | 4/24/2015 | P | PASS |
Jim Storey
|
|
|
John-1 st floor exterior walls Phone #: ###-####
|
BLD-Framing/Rough-in | 4/3/2015 | 4/6/2015 | 4/6/2015 | A | PART |
Jim Storey
|
|
|
John// basement- interior wall Phone #: ###-#### c/n 2hr joint and opening protection c/n isued ok to begin gyp.
|
BLD-Conference | 3/11/2015 | 3/11/2015 | 3/11/2015 | P | PART |
Jim Storey
|
|
|
John Phone #: ###-#### need gyp top of walls
|
BLD-Framing/Rough-in | 3/5/2015 | 3/5/2015 | 3/5/2015 | P | PASS |
Jim Storey
|
|
|
Gary-H wing 2 & 3 floor-consult Phone #: ###-#### ok to cover
|
BLD-Framing/Rough-in | 1/8/2015 | 1/9/2015 | 1/9/2015 | A | PASS |
Jim Storey
|
|
|
John-Roofing Phone #: ###-#### roof faming steel trusses ok for cover
|
BLD-Framing/Rough-in | 1/5/2015 | 1/6/2015 | 1/6/2015 | P | PART |
Jim Storey
|
|
|
JC-kitchen Phone #: ###-#### need bracing/ truss repairs ok
|
BLD-Wall Bracing | 11/6/2014 | 11/7/2014 | 11/7/2014 | A | PASS |
Jim Storey
|
|
|
JC Phone #: ###-#### exterior of commons bldg. ok to cover
|
BLD-Footing | 6/10/2014 | 6/10/2014 | 6/10/2014 | P | PASS |
Jim Storey
|
|
|
john Phone #: ###-####
|
BLD-Footing | 5/29/2014 | 5/30/2014 | 5/30/2014 | A | PART |
Jim Storey
|
|
|
John Phone #: ###-####wip si on site
|
BLD-Foundation | 5/23/2014 | 5/23/2014 | 5/23/2014 | P | PASS |
Jim Storey
|
|
|
JC Phone #: ###-####
|
BLD-Footing | 5/16/2014 | 5/16/2014 | 5/16/2014 | P | PEND |
Dave Hannah
|
|
|
John Lowe-Elevator slab Phone #: ###-#### pend spec inspection sign off
|