BLD-Final | 11/12/2013 | 11/13/2013 | 11/13/2013 | A | PASS |
Jim Storey
|
|
|
Dante Phone #: ###-####
|
BLD-Final | 11/7/2013 | 11/8/2013 | 11/8/2013 | P | PART |
Jim Storey
|
|
|
dante Phone #: ###-#### signage above entry door temp final ok.
|
FIRE-Final Inspection | 11/7/2013 | 11/8/2013 | 11/8/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 11/5/2013 | 11/5/2013 | 11/5/2013 | P | NR |
Jim Storey
|
|
|
Dante Phone #: ###-####
|
BLD-Final | 11/4/2013 | 11/5/2013 | 11/5/2013 | A | DEFR |
Jim Storey
|
|
|
Dante Phone #: ###-####
|
FIRE-Final Inspection | 11/4/2013 | 11/4/2013 | 11/4/2013 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy is given with Scott Arellano's permission for a max of 10 days. Items needing correct are the fire doors do not have activation per NFPA 80 (links on both sides), access controled egress doors do not have sensors or connection to the fire alarm system per IFC 1008.1.4.4, exit discharge lights need to be installed, add exit sign/emergency light in corridor, install tile in office, contact fire dept for gate at west side of building that is only 14'-6" wide.
|
BLD-Final | 10/31/2013 | 11/1/2013 | 11/1/2013 | P | NR |
Jim Storey
|
|
|
Dante-Late afternoon please Phone #: ###-####
|
FIRE-Final Inspection | 10/31/2013 | 11/1/2013 | 11/1/2013 | P | FAIL |
Craig D. Hanson
|
|
|
FA system not ready. Doors not installed. No mag holders.
|
BLD-Other | 10/9/2013 | 10/10/2013 | 10/10/2013 | A | PART |
Jim Storey
|
|
|
2hr wall //Dante Phone #: ###-#### core board ok
|
BLD-Energy code compliance | 10/8/2013 | 10/8/2013 | 10/8/2013 | P | PASS |
Jim Storey
|
|
|
Dante Phone #: 2###-####
|
BLD-Foundation | 7/5/2013 | 7/8/2013 | 7/8/2013 | A | PASS |
Jim Storey
|
|
|
Dante Phone #: ###-#### ft in slab ok
|
BLD-Conference | 6/18/2013 | 6/19/2013 | 6/19/2013 | A | PASS |
Jim Storey
|
|
|
stem wall//Dante Phone #: ###-####
|
BLD-Footing | 6/14/2013 | 6/17/2013 | 6/17/2013 | A | PASS |
Jim Storey
|
|
|
pouring around noon - dante Phone #: ###-####
|
BLD-Foundation | 6/10/2013 | 6/11/2013 | 6/11/2013 | P | PASS |
Jim Storey
|
|
|
Dante Phone #: ###-#### walls and piers rebar ok si pending report.
|
BLD-Footing | 6/3/2013 | 6/4/2013 | 6/4/2013 | A | PASS |
Jim Storey
|
|
|
Dante Phone #: ###-#### ft rebar ok / si pending.
|