BLD-Final | 5/8/2014 | 5/9/2014 | 5/9/2014 | A | PASS |
Mike Jordan
|
|
|
Jason Phone #: ###-####. Ok for perm occ.
|
BLD-Final | 12/20/2013 | 12/20/2013 | 12/20/2013 | P | PART |
Mike Jordan
|
|
|
jason Phone #: ###-####. Needs public works sign off, then ok for temp occ. Front counter not installed, Need final lettter from special inspection agency.
|
FIRE-Final Inspection | 12/19/2013 | 12/19/2013 | 12/19/2013 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Ceiling Grid Inspection | 12/4/2013 | 12/5/2013 | 12/5/2013 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### >> Inspection requested via web by Greg Baisch
|
BLD-Conference | 11/22/2013 | 11/25/2013 | 11/25/2013 | A | DONE |
Mike Jordan
|
|
|
Requesting Building Conference to discuss final sign-off. Phone #: ###-#### >> Inspection requested via web by Greg Baisch
|
BLD-Energy code compliance | 11/1/2013 | 11/4/2013 | 11/4/2013 | P | PASS |
Mike Jordan
|
|
|
Requesting Energy Code Inspection for exterior insulation systems on the South Half of the building. Phone #: ###-#### >> Inspection requested via web by Greg Baisch
|
BLD-Conference | 10/27/2013 | 10/28/2013 | 10/28/2013 | A | PASS |
Mike Jordan
|
|
|
Scheduling a building inspection conference at the request of Mike Jordan to review interior walls prior to closing. Phone #: ###-#### >> Inspection requested via web by Greg Baisch
|
BLD-Energy code compliance | 10/28/2013 | 10/28/2013 | 10/28/2013 | A | PASS |
Mike Jordan
|
|
|
Scheduling a building inspection conference at the request of Mike Jordan to review interior walls prior to closing. Phone #: ###-#### >> Inspection requested via web by Greg Baisch. North half ok to cover.
|
BLD-Energy code compliance | 10/17/2013 | 10/18/2013 | 10/18/2013 | A | PART |
Mike Jordan
|
|
|
Requesting Air Seal Inspection for the South half of the building and the final framing and shear nailing inspection on interior walls. Phone #: ###-#### >> Inspection requested via web by Greg Baisch. ok to insulate south half og building. Pending electrical and mechanical rough in inspections.
|
BLD-Framing/Rough-in | 10/11/2013 | 10/14/2013 | 10/14/2013 | A | PART |
Mike Jordan
|
|
|
Requesting exterior wall air-seal inspection and framing inspection. Phone #: ###-#### >> Inspection requested via web by Greg Baisch. Ok to insulate north half gridlines 1 to 6. Neesd to complete nailing on interior shearwalls, complete gussett repairs on trusses T9 and foam all top plate penetrations o n interior walls.
|
FIRE-Conference | 10/10/2013 | 10/11/2013 | 10/11/2013 | A | DONE |
Troy Cobbley
|
|
|
Greg Baisch and I discussed the placement of the exit signs that may be blocked by ducting and the need for the fire hydrant to be rotated so that the 5" barrel does not face a parking space.
|
BLD-Framing/Rough-in | 9/26/2013 | 9/27/2013 | 9/27/2013 | P | PASS |
Jim Storey
|
|
|
Requesting Roof Nailing Inspection. Phone #: ###-#### >> Inspection requested via web by Greg Baisch drag nailling ok straps ok all deck sheathing ok to cover.
|
BLD-Framing/Rough-in | 9/23/2013 | 9/23/2013 | 9/23/2013 | P | PASS |
Mike Jordan
|
|
|
Requesting a shear nailing inspection for the exterior walls Phone #: ###-#### >> Inspection requested via web by Greg Baisch. Exterior shearnailing ok. Ok to cover.
|
BLD-Framing/Rough-in | 9/19/2013 | 9/20/2013 | 9/20/2013 | A | PART |
Mike Jordan
|
|
|
Requesting a shear nailing inspection for exterior walls. Phone #: ###-#### >> Inspection requested via web by Greg Baisch. Exterior shear nailing, south east corner of biulding only ok to cover. Needs to hit missed areas and provide the double nailing in the sole plate as per approved plans or provide RFI from engineer of record. Area approved for cover has the double nailing into sole plates and top lates S required.
|
BLD-Concrete | 8/6/2013 | 8/8/2013 | 8/8/2013 | P | PASS |
Mike Jordan
|
|
|
Request inspection of wire mesh for slab-on-grade. Phone #: ###-#### >> Inspection requested via web by Greg Baisch. Slab on grade and interior footings, north half.
|
BLD-Concrete | 8/6/2013 | 8/7/2013 | 8/7/2013 | A | PART |
Mike Jordan
|
|
|
Requesting inspection of reinforcing steel for under-slab footings. Phone #: ###-#### >> Inspection requested via web by Greg Baisch. Interior footings. Work in progress, pend. special inspection.
|
BLD-Footing | 8/2/2013 | 8/5/2013 | 8/5/2013 | A | NR |
Mike Jordan
|
|
|
Rebar inspection for thickened slab areas. Requesting Noon inspection. Phone #: ###-#### >> Inspection requested via web by Greg Baisch
|
BLD-Other | 7/16/2013 | 7/16/2013 | 7/16/2013 | P | PART |
Jim Sly
|
|
|
reinforcing steel for walls-Greg Phone #: ###-#### Approved plans on site.....Foundation walls appear to be OK. Pending MTI special inspection, tests and approvals.
|
BLD-Footing | 7/10/2013 | 7/11/2013 | 7/11/2013 | A | PART |
Mike Jordan
|
|
|
mid morning rebar - greg Phone #: ###-####. Work in progress onplacing vertical reinforcement at perimeter footings and column pad footings to the S.E. Will have special inspection.
|