Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberBLD13-00645
StatusFinaled
Name HC COMPANY INC
Site Address 9976 W EMERALD ST
Project NameEmergency Responders Health Ce
Customer Number 
ePlanReviewYes
Description
Emergency Responders Health Center - To construct a new 4,785 square foot, one story, wood framed medical office building and related site improvements. This building is not fire sprinkled. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/8/20145/9/20145/9/2014APASS
DetailsMike Jordan
Jason Phone #: ###-####. Ok for perm occ.
BLD-Final12/20/201312/20/201312/20/2013PPART
DetailsMike Jordan
jason Phone #: ###-####. Needs public works sign off, then ok for temp occ. Front counter not installed, Need final lettter from special inspection agency.
FIRE-Final Inspection12/19/201312/19/201312/19/2013PPASS
DetailsTroy Cobbley
life safety passed
BLD-Ceiling Grid Inspection12/4/201312/5/201312/5/2013APASS
DetailsJim Sly
Phone #: ###-#### >> Inspection requested via web by Greg Baisch
BLD-Conference11/22/201311/25/201311/25/2013ADONE
DetailsMike Jordan
Requesting Building Conference to discuss final sign-off. Phone #: ###-#### >> Inspection requested via web by Greg Baisch
BLD-Energy code compliance11/1/201311/4/201311/4/2013PPASS
DetailsMike Jordan
Requesting Energy Code Inspection for exterior insulation systems on the South Half of the building. Phone #: ###-#### >> Inspection requested via web by Greg Baisch
BLD-Conference10/27/201310/28/201310/28/2013APASS
DetailsMike Jordan
Scheduling a building inspection conference at the request of Mike Jordan to review interior walls prior to closing. Phone #: ###-#### >> Inspection requested via web by Greg Baisch
BLD-Energy code compliance10/28/201310/28/201310/28/2013APASS
DetailsMike Jordan
Scheduling a building inspection conference at the request of Mike Jordan to review interior walls prior to closing. Phone #: ###-#### >> Inspection requested via web by Greg Baisch. North half ok to cover.
BLD-Energy code compliance10/17/201310/18/201310/18/2013APART
DetailsMike Jordan
Requesting Air Seal Inspection for the South half of the building and the final framing and shear nailing inspection on interior walls. Phone #: ###-#### >> Inspection requested via web by Greg Baisch. ok to insulate south half og building. Pending electrical and mechanical rough in inspections.
BLD-Framing/Rough-in10/11/201310/14/201310/14/2013APART
DetailsMike Jordan
Requesting exterior wall air-seal inspection and framing inspection. Phone #: ###-#### >> Inspection requested via web by Greg Baisch. Ok to insulate north half gridlines 1 to 6. Neesd to complete nailing on interior shearwalls, complete gussett repairs on trusses T9 and foam all top plate penetrations o n interior walls.
FIRE-Conference10/10/201310/11/201310/11/2013ADONE
DetailsTroy Cobbley
Greg Baisch and I discussed the placement of the exit signs that may be blocked by ducting and the need for the fire hydrant to be rotated so that the 5" barrel does not face a parking space.
BLD-Framing/Rough-in9/26/20139/27/20139/27/2013PPASS
DetailsJim Storey
Requesting Roof Nailing Inspection. Phone #: ###-#### >> Inspection requested via web by Greg Baisch drag nailling ok straps ok all deck sheathing ok to cover.
BLD-Framing/Rough-in9/23/20139/23/20139/23/2013PPASS
DetailsMike Jordan
Requesting a shear nailing inspection for the exterior walls Phone #: ###-#### >> Inspection requested via web by Greg Baisch. Exterior shearnailing ok. Ok to cover.
BLD-Framing/Rough-in9/19/20139/20/20139/20/2013APART
DetailsMike Jordan
Requesting a shear nailing inspection for exterior walls. Phone #: ###-#### >> Inspection requested via web by Greg Baisch. Exterior shear nailing, south east corner of biulding only ok to cover. Needs to hit missed areas and provide the double nailing in the sole plate as per approved plans or provide RFI from engineer of record. Area approved for cover has the double nailing into sole plates and top lates S required.
BLD-Concrete8/6/20138/8/20138/8/2013PPASS
DetailsMike Jordan
Request inspection of wire mesh for slab-on-grade. Phone #: ###-#### >> Inspection requested via web by Greg Baisch. Slab on grade and interior footings, north half.
BLD-Concrete8/6/20138/7/20138/7/2013APART
DetailsMike Jordan
Requesting inspection of reinforcing steel for under-slab footings. Phone #: ###-#### >> Inspection requested via web by Greg Baisch. Interior footings. Work in progress, pend. special inspection.
BLD-Footing8/2/20138/5/20138/5/2013ANR
DetailsMike Jordan
Rebar inspection for thickened slab areas. Requesting Noon inspection. Phone #: ###-#### >> Inspection requested via web by Greg Baisch
BLD-Other7/16/20137/16/20137/16/2013PPART
DetailsJim Sly
reinforcing steel for walls-Greg Phone #: ###-####
Approved plans on site.....Foundation walls appear to be OK. Pending MTI special inspection, tests and approvals.
BLD-Footing7/10/20137/11/20137/11/2013APART
DetailsMike Jordan
mid morning rebar - greg Phone #: ###-####. Work in progress onplacing vertical reinforcement at perimeter footings and column pad footings to the S.E. Will have special inspection.