DOC - Permit Finaled | | | 10/25/2013 | | DONE |
|
|
|
|
BLD-Final | 10/23/2013 | 10/24/2013 | 10/24/2013 | A | DONE |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
BLD-Final | 10/24/2013 | 10/24/2013 | 10/24/2013 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
FIRE-Final Inspection | 10/24/2013 | 10/24/2013 | 10/24/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 10/21/2013 | 10/22/2013 | 10/23/2013 | P | CANC |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
FIRE-Final Inspection | 10/21/2013 | 10/22/2013 | 10/23/2013 | P | PART |
Forrest France
|
|
|
Final pending project related fire sprinkler permit items and finishes.
|
BLD-Final | 10/9/2013 | 10/10/2013 | 10/14/2013 | P | NR |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer needs fire finals
|
FIRE-Final Inspection | 10/9/2013 | 10/10/2013 | 10/10/2013 | A | NR |
Forrest France
|
|
|
Building shell permit fire life safety approval pending completion and final acceptance testing of trade related and project attatched fire sprinkler and fire alarm permit work in accordance with applicable standards (NFPA13, NFPA72, IFC). Refer to BLD13-00729 fire code plan review notes for specific details.
|
BLD-Conference | 10/8/2013 | 10/8/2013 | 10/9/2013 | P | PASS |
Dave Hannah
|
|
|
Meet onsite for a pre-turnover/final inspection meeting. Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
BLD-Framing/Rough-in | 9/6/2013 | 9/6/2013 | 9/9/2013 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer insulation of ext walls ok
|
BLD-Framing/Rough-in | 8/26/2013 | 8/26/2013 | 8/28/2013 | P | PASS |
Dave Hannah
|
|
|
Homer Phone #: ###-#### ext steel stud walls ok
|
BLD-Framing/Rough-in | 8/21/2013 | 8/21/2013 | 8/21/2013 | P | PART |
Mike Jordan
|
|
|
chris Phone #: ###-####. Work in progress on exterior steel stud walls for storefronts. All Cross bracing not yet installed, parapets ok.
|
BLD-Foundation | 8/7/2013 | 8/7/2013 | 8/7/2013 | P | CANC |
Dave Hannah
|
|
|
Footing and foundation waterproofing inspection. Phone #: ###-#### >> Inspection requested via web by Chris Palmer Inspection cancelled from web by: Chris Palmer
|
BLD-Footing | 7/8/2013 | 7/8/2013 | 7/8/2013 | A | PASS |
Dave Hannah
|
|
|
Footing at NW corner of property. Approx 5 yds. Pour at 1130 am. Please call with any questions. Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
BLD-Foundation | 6/28/2013 | 6/28/2013 | 7/2/2013 | P | PASS |
Dave Hannah
|
|
|
Stem walls at Retail 1. Pour is scheduled for 1pm today. Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
BLD-Energy code compliance | 7/1/2013 | 7/1/2013 | 7/1/2013 | A | FAIL |
Dave Hannah
|
|
|
Foundation insulation inspection late morning. Please call with any questions. Phone #: ###-#### >> Inspection requested via web by Chris Palmer insulation stopped at bottom of slab
|
BLD-Footing | 6/19/2013 | 6/20/2013 | 6/20/2013 | A | PASS |
Dave Hannah
|
|
|
Footing inspection for Retail 1. Pour scheduled for 11am, inspection requested for 930am. Construction access is located on 6th. Please call with any questions. Thank You. Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|