BLD-Final | 10/10/2013 | 10/11/2013 | 10/14/2013 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
DOC - Permit Finaled | | | 10/14/2013 | | DONE |
Christina Prado
|
|
|
Per Dave Hannah
|
FIRE-Final Inspection | 10/10/2013 | 10/11/2013 | 10/11/2013 | A | PASS |
Craig D. Hanson
|
|
|
all devices tested and passed
|
BLD-Energy code compliance | 9/23/2013 | 9/24/2013 | 9/25/2013 | P | PASS |
Dave Hannah
|
|
|
Early afternoon if possible. Thank You. Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
BLD-Framing/Rough-in | 9/17/2013 | 9/17/2013 | 9/17/2013 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
BLD-Energy code compliance | 7/9/2013 | 7/9/2013 | 7/9/2013 | P | PASS |
Dave Hannah
|
|
|
Foundation Insulation Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
BLD-Foundation | 7/3/2013 | 7/3/2013 | 7/3/2013 | A | PART |
Dave Hannah
|
|
|
Stem walls. Pour scheduled for noon today. Phone #: ###-#### >> Inspection requested via web by Chris Palmer mti on site for spec. inspection
|
BLD-Footing | 6/27/2013 | 6/27/2013 | 6/27/2013 | P | PART |
Dave Hannah
|
|
|
Footing pour scheduled for 1pm. Phone #: ###-#### >> Inspection requested via web by Chris Palmer mti will be doing spec inspection on this project
|
BLD-Footing | 6/26/2013 | 6/26/2013 | 6/27/2013 | P | PART |
Dave Hannah
|
|
|
Footing rebar inspection. Pour scheduled for 3pm today. Call with any questions. Thanks, Phone #: ###-#### >> Inspection requested via web by Chris Palmer mti will be doing spec inspection on this project
|