BLD-Final | 9/22/2014 | 9/23/2014 | 9/23/2014 | P | PASS |
Dave Hannah
|
|
|
Duel Phone #: ###-####
|
FIRE-Final Inspection | 9/23/2014 | 9/23/2014 | 9/23/2014 | P | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
BLD-Aging Inspection | 9/8/2014 | 9/8/2014 | 9/8/2014 | | PEND |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 7/8/2014 | 7/10/2014 | 7/11/2014 | A | PART |
Forrest France
|
|
|
2nd floor core area passed fire life safety inspection.
|
BLD-Final | 7/3/2014 | 7/3/2014 | 7/7/2014 | P | PART |
Dave Hannah
|
|
|
Jim Phone #: ###-####
|
FIRE-Final Inspection | 7/3/2014 | 7/3/2014 | 7/3/2014 | P | PART |
Forrest France
|
|
|
Completed re-inspection for previous correction items dated 6/30 related to apartments on the 2nd, 3rd and 4th floors. Provisions and adjustments finished with the exception of door closure at 212, exit discharge light at the main street side, outside waterflow bell not yet installed. Shell fire protection 1st floor pending necessary revisions per agreement on record. Temporary occupancy approved per R. Gervais.
|
FIRE-Final Inspection | 6/26/2014 | 6/30/2014 | 7/1/2014 | P | FAIL |
Forrest France
|
|
|
Fire life safety inspection items for the 2nd, 3rd and 4th floor apartments completed 6/30 include; provide exit sign per plan review red line at the 1st floor landing east side stairway, install exit discharge lighting for both east and west stairways, test EM light 1st floor east stairway, remove scafolding in the west stairway, remove tape covering smoke alarms at 4th floor apartment units, install door seals at doors serving elevator lobbies to apt unit corridors, adjust closer at units 204, 206, 212. Remove tape and provide escutcheon at sprinkler head unit 206, provide intermediate temp pendent head at unit 312 adjacent to HVAC diffuser, install outside waterflow bell 11th street side, relocate two smoke alarms at unit 301, replace malfunctional flow switches at the 3rd and 4th floor sprinkler control manifolds. 1st floor fire sprinkler protection at the vacant shell does not meet NFPA 13 standards.
|
BLD-Final | 6/26/2014 | 6/30/2014 | 6/30/2014 | P | NR |
Dave Hannah
|
|
|
apartments only - Jim Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 6/26/2014 | 6/26/2014 | 6/26/2014 | P | PASS |
Dave Hannah
|
|
|
2nd fl corridor bridal - Jim Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 6/25/2014 | 6/25/2014 | 6/25/2014 | P | PASS |
Dave Hannah
|
|
|
2nd fl ballroom - Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 6/24/2014 | 6/24/2014 | 6/24/2014 | P | PASS |
Dave Hannah
|
|
|
West side apart fire escape - Jim Phone #: ###-####
|
BLD-Conference | 6/23/2014 | 6/24/2014 | 6/24/2014 | A | PASS |
Dave Hannah
|
|
|
Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 6/18/2014 | 6/18/2014 | 6/18/2014 | P | PART |
Jim Sly
|
|
|
Ceiling grid inspection in the basement please-Jim Phone #: ###-#### Bsmnt elevator lobby and Board room.....OK.
|
BLD-Conference | 6/16/2014 | 6/17/2014 | 6/17/2014 | A | PASS |
Jim Storey
|
|
|
Jim Phone #: ###-#### entry vestabule ceilling ok to cover
|
BLD-Conference | 6/11/2014 | 6/11/2014 | 6/12/2014 | P | PASS |
Dave Hannah
|
|
|
Bill Phone #: ###-####
|
BLD-Framing/Rough-in | 6/10/2014 | 6/10/2014 | 6/11/2014 | P | DEFR |
Dave Hannah
|
|
|
shaft wall inspection please-Jim Phone #: ###-#### called in wrong permit number
|
BLD-Other | 5/30/2014 | 6/6/2014 | 6/6/2014 | A | CANC |
Dave Hannah
|
|
|
Foam barrier - Nabi Phone #: ###-####
|
BLD-Conference | 6/5/2014 | 6/5/2014 | 6/6/2014 | P | DONE |
Dave Hannah
|
|
|
Jim Phone #: ###-#### rise and run of stairs and handrails
|
BLD-Conference | 5/30/2014 | 6/2/2014 | 6/2/2014 | A | PASS |
Dave Hannah
|
|
|
hand rail for core stairwell - Jim Phone #: ###-#### I have walked stair tower #2 and because of egress widths I have approved the handrails as they are currently built.
|
BLD-Conference | 5/22/2014 | 5/23/2014 | 5/27/2014 | A | PASS |
Dave Hannah
|
|
|
*Requests around 10 - Jim Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 5/14/2014 | 5/15/2014 | 5/15/2014 | A | NR |
Jim Storey
|
|
|
Jim-2nd floor core Phone #: ###-####
|
BLD-Framing/Rough-in | 5/9/2014 | 5/12/2014 | 5/12/2014 | A | PASS |
Dave Hannah
|
|
|
Juron Phone #: ###-####
|
BLD-Other | 5/6/2014 | 5/6/2014 | 5/6/2014 | P | PASS |
Dave Hannah
|
|
|
1st fl cover/walk/ceiling - Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 5/2/2014 | 5/2/2014 | 5/6/2014 | P | PASS |
Dave Hannah
|
|
|
Jim-cover inspections for 1st and 2nd floors Phone #: ###-####
|
BLD-Conference | 4/30/2014 | 5/1/2014 | 5/1/2014 | A | CANC |
Mike Jordan
|
|
|
jim - 11am please Phone #: ###-####. Cancelled, rescheduled for friday in the am.
|
BLD-Other | 4/24/2014 | 4/25/2014 | 4/29/2014 | A | PART |
Dave Hannah
|
|
|
jim - ceiling assembly on 1st floor Phone #: ###-#### hardlid first floor . rest rooms on the second/mezz deck ok to cover also ok to one side int walls on second /mezz deck ceiling grid in halls on 4 and 3 ok to cover
|
BLD-Framing/Rough-in | 4/21/2014 | 4/22/2014 | 4/23/2014 | A | PASS |
Dave Hannah
|
|
|
2nd fl restrooms & basement data room - Jim Phone #: ###-####
|
BLD-Other | 4/18/2014 | 4/18/2014 | 4/21/2014 | P | PART |
Dave Hannah
|
|
|
jim - shaft inspection Phone #: ###-####
|
BLD-Other | 4/10/2014 | 4/10/2014 | 4/11/2014 | P | NR |
Dave Hannah
|
|
|
fire stop - 2nd floor core Phone #: ###-####
|
BLD-Other | 4/9/2014 | 4/9/2014 | 4/9/2014 | P | PART |
Dave Hannah
|
|
|
Fire stop - Jim Phone #: ###-#### first floor mailbox area ok to cover
|
BLD-Other | 4/3/2014 | 4/3/2014 | 4/4/2014 | P | PART |
Dave Hannah
|
|
|
Mechanical shaft inspection please-Jason Phone #: ###-#### ok to cover
|
BLD-Other | 3/25/2014 | 3/25/2014 | 3/25/2014 | P | PART |
Dave Hannah
|
|
|
Shaft inspection in the core pleaseJIm Phone #: ###-#### ok to start framing and installing ent layer of shaft wall board
|
BLD-Framing/Rough-in | 3/21/2014 | 3/21/2014 | 3/24/2014 | P | PASS |
Dave Hannah
|
|
|
Ceiling cover inspection for the apt lobby please-Jim Phone #: ###-####
|
BLD-Conference | 3/17/2014 | 3/17/2014 | 3/18/2014 | P | PASS |
Dave Hannah
|
|
|
Jim Phone #: ###-####
|
BLD-Conference | 3/18/2014 | 3/18/2014 | 3/18/2014 | P | PASS |
Dave Hannah
|
|
|
Jim - Conf at 11 Phone #: ###-####
|
BLD-Other | 3/11/2014 | 3/12/2014 | 3/12/2014 | A | FAIL |
Jim Storey
|
|
|
late AM// cover insp for apartment lobby / Jim Phone #: ###-#### oversized pvc penatration/ mail box area shaft required/ 1 ht protection of wood floor support/ west window gyp at ceilling line 1 hr protection behind metal framing.
|
BLD-Concrete | 3/3/2014 | 3/4/2014 | 3/4/2014 | A | PART |
Dave Hannah
|
|
|
jim - 6th fl shaft; 3th fl bath room; Phone #: ###-#### bath room ok need to finish framing shaft and install shaft board
|
BLD-Other | 2/25/2014 | 2/26/2014 | 2/27/2014 | A | NR |
Dave Hannah
|
|
|
ceiling, elevator and stair tower core // Jim Phone #: ###-####
|
BLD-Other | 2/24/2014 | 2/24/2014 | 2/25/2014 | P | PART |
Dave Hannah
|
|
|
core shaft - Jim Phone #: ###-#### ok to keep working on shaft they have the back wall in
|
BLD-Other | 2/18/2014 | 2/18/2014 | 2/18/2014 | P | PART |
Dave Hannah
|
|
|
JIM - SHAFT LINER 6TH FL Phone #: ###-#### ok to keep going
|
BLD-Wall cover | 2/11/2014 | 2/12/2014 | 2/12/2014 | A | PASS |
Dave Hannah
|
|
|
apt corridor 2nd floor cover insp // Jim Phone #: ###-####
|
BLD-Other | 2/6/2014 | 2/7/2014 | 2/7/2014 | A | PASS |
Tony Young
|
|
|
2nd fl soffit cover - Jim Phone #: ###-####
|
BLD-Other | 2/5/2014 | 2/5/2014 | 2/6/2014 | P | PEND |
Dave Hannah
|
|
|
reinsp soffit on 2nd floor for cover // Jim Phone #: ###-#### ok after fire oks
|
BLD-Other | 2/3/2014 | 2/3/2014 | 2/4/2014 | P | NR |
Dave Hannah
|
|
|
jim Phone #: ###-####
|
BLD-Wall cover | 1/30/2014 | 1/31/2014 | 1/31/2014 | A | PASS |
Dave Hannah
|
|
|
4th floor restrooms please-Jim Phone #: ###-####
|
BLD-Other | 1/28/2014 | 1/28/2014 | 1/28/2014 | P | NR |
Dave Hannah
|
|
|
JIM - FIRE PROOFING ON THE 4TH FLOOR Phone #: ###-####
|
BLD-Other | 1/10/2014 | 1/13/2014 | 1/14/2014 | A | CANC |
Dave Hannah
|
|
|
2nd & 5th floor caulking - Jim Phone #: ###-#### Dave told me to cancel.....Already looked at it.
|
BLD-Framing/Rough-in | 1/13/2014 | 1/13/2014 | 1/14/2014 | P | PART |
Dave Hannah
|
|
|
2nd & 5th floor caulking - Jim Phone #: ###-#### ok to cover 2nd floor aprt and 5th floor restrooms
|
BLD-Ceiling Grid Inspection | 1/7/2014 | 1/8/2014 | 1/9/2014 | A | PART |
Dave Hannah
|
|
|
JIM apt first floor Phone #: ###-#### needs to finish fire spray on rock wool floor infills
|
BLD-Other | 1/3/2014 | 1/6/2014 | 1/7/2014 | P | PASS |
Dave Hannah
|
|
|
jim - 3rd floor apts - fire stop Phone #: ###-####
|
BLD-Other | 1/7/2014 | 1/7/2014 | 1/7/2014 | A | PART |
Dave Hannah
|
|
|
jim - 3rd floor apts - fire stop Phone #: ###-#### ok to cover walls on 3rd floor
|
BLD-Other | 12/24/2013 | 12/27/2013 | 12/27/2013 | A | PASS |
Dave Hannah
|
|
|
jim - cover on 3rd floor apartments Phone #: ###-####
|
BLD-Framing/Rough-in | 12/19/2013 | 12/20/2013 | 12/21/2013 | P | NR |
Dave Hannah
|
|
|
Ok to cover 3rd fl apart - Jim Phone #: ###-####
|
FIRE-Conference | 12/11/2013 | 12/11/2013 | 12/11/2013 | P | DEFR |
Forrest France
|
|
|
tim - fire walk 2:30 if possible Phone #: ###-####
|
BLD-Framing/Rough-in | 12/5/2013 | 12/5/2013 | 12/9/2013 | P | PASS |
Dave Hannah
|
|
|
3RD FLOOR - FRAMING AND FIRE PROOFING PER DAVE HANNAH
|
BLD-Other | 12/4/2013 | 12/5/2013 | 12/9/2013 | A | NR |
Dave Hannah
|
|
|
jim - 7 to 1 floor Phone #: ###-####
|
FIRE-Final Inspection | 12/9/2013 | 12/9/2013 | 12/9/2013 | P | NR |
Forrest France
|
|
|
Jim Phone #: ###-####
|
FIRE-Final Inspection | 12/4/2013 | 12/5/2013 | 12/5/2013 | A | NR |
Forrest France
|
|
|
early as poss // use permit to occupy the 7th floor // Jim Phone #: ###-#### *Completed on site walkthrough with G. Goldsmith, T. Gainor, and general contractors. Project is not in condition for occupancy at this time due to construction underway and site work in progress.*
|
BLD-Other | 11/27/2013 | 12/2/2013 | 12/4/2013 | A | PART |
Dave Hannah
|
|
|
Mid-morning request // apt fire caulking cover, 7th floor ceiling insp // Jim Phone #: ###-#### ok to 7th floor ceiling and 4th floor walls
|
BLD-Ceiling Grid Inspection | 11/20/2013 | 11/21/2013 | 11/22/2013 | A | PART |
Dave Hannah
|
|
|
After 10 please - 2nd fl apartments - Jim Phone #: ###-#### ok to cover ceilings 2nd and 3rd fl apts and rest rooms on 6th fl
|
BLD-Framing/Rough-in | 11/18/2013 | 11/19/2013 | 11/19/2013 | A | FAIL |
Dave Hannah
|
|
|
cover for 6th flr bathrooms // Jim Phone #: ###-#### need to fire stop at ceiling and floor lines
|
BLD-Other | 11/14/2013 | 11/15/2013 | 11/18/2013 | P | PART |
Dave Hannah
|
|
|
late am // fire caulking 4th floor apts // Jim Phone #: ###-#### ok to cover walls
|
BLD-Framing/Rough-in | 11/7/2013 | 11/8/2013 | 11/12/2013 | A | PART |
Dave Hannah
|
|
|
4th floor walls in the apts, 3rd floor ceiling cover, insulation on 2nd floor all in the apartments--Jim Phone #: ###-#### ok to cover 3rd floor ceiling but needs to finish fire stopping on 4th floor.
|
BLD-Other | 11/1/2013 | 11/4/2013 | 11/5/2013 | A | PART |
Dave Hannah
|
|
|
Mock up cover - Jim Phone #: ###-#### needs to fire proof floor and ceiling opennings ok to one side
|
BLD-Framing/Rough-in | 11/4/2013 | 11/4/2013 | 11/5/2013 | P | PEND |
Dave Hannah
|
|
|
fire proofing floor in chase by elev shaft west wing
|
BLD-Ceiling Grid Inspection | 10/31/2013 | 11/1/2013 | 11/1/2013 | A | PASS |
Dave Hannah
|
|
|
3rd floor apts // Jim Phone #: ###-####
|
BLD-Other | 10/30/2013 | 10/31/2013 | 10/31/2013 | A | PASS |
Dave Hannah
|
|
|
4th fl ceiling cover/apartments - Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 10/25/2013 | 10/29/2013 | 10/29/2013 | A | PART |
Dave Hannah
|
|
|
jim Phone #: ###-#### 7th floor ok to cover walls
|
BLD-Framing/Rough-in | 10/23/2013 | 10/24/2013 | 10/24/2013 | A | PART |
Dave Hannah
|
|
|
7th fl core, 3rd & 4th apartment- Jim Phone #: ###-#### ok to cover ext walls ok to one side ent walls
|
BLD-Conference | 10/15/2013 | 10/16/2013 | 10/16/2013 | A | DONE |
Dave Hannah
|
|
|
jim - before 10 please Phone #: ###-####
|
BLD-Other | 10/11/2013 | 10/14/2013 | 10/15/2013 | A | PART |
Dave Hannah
|
|
|
fire pillow insp, 3rd flr apts // jim Phone #: ###-#### ok to cover
|
BLD-Ceiling Grid Inspection | 10/7/2013 | 10/8/2013 | 10/9/2013 | A | PART |
Dave Hannah
|
|
|
2nd floor corrider ceiling insp // Jim Phone #: ###-#### ok to insulate and rock
|
BLD-Framing/Rough-in | 10/2/2013 | 10/3/2013 | 10/4/2013 | A | NR |
Dave Hannah
|
|
|
request late AM -- conference/cover insp/framing -- Jim Phone #: ###-####
|
BLD-Conference | 9/26/2013 | 9/27/2013 | 9/27/2013 | A | DONE |
Dave Hannah
|
|
|
bradden Phone #: ###-####
|
BLD-Conference | 9/17/2013 | 9/18/2013 | 9/18/2013 | P | DONE |
Dave Hannah
|
|
|
1:00 pm meeting to walk project .
|
BLD-Concrete | 9/13/2013 | 9/16/2013 | 9/17/2013 | A | PEND |
Dave Hannah
|
|
|
JIM Phone #: ###-####
|
BLD-Conference | 9/10/2013 | 9/11/2013 | 9/12/2013 | A | DONE |
Dave Hannah
|
|
|
jim Phone #: ###-####
|