BLD-Final | 11/22/2013 | 11/22/2013 | 11/22/2013 | P | PASS |
Jim Sly
|
|
|
|
DOC - Permit Finaled | 11/22/2013 | 11/22/2013 | 11/22/2013 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 11/21/2013 | 11/22/2013 | 11/22/2013 | A | PEND |
Jim Sly
|
|
|
|
BLD-Final | 11/21/2013 | 11/21/2013 | 11/21/2013 | P | NR |
Jim Sly
|
|
|
darren Phone #: ###-####
|
FIRE-Final Inspection | 11/20/2013 | 11/21/2013 | 11/21/2013 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy for life safety is ok per Romeo Gervais until the CM Company tenant space is complete. 12-10-13 per phone call with Troy Cobbley fire has been signed off all the way.the building final was signed off early,but Troy went back out and signed it off.
|
FIRE-Final Inspection | 11/19/2013 | 11/20/2013 | 11/20/2013 | A | CANC |
Troy Cobbley
|
|
|
Not ready for life safety due to emergency lights.
|
FIRE-Final Inspection | 11/18/2013 | 11/19/2013 | 11/19/2013 | A | CANC |
Troy Cobbley
|
|
|
Not ready for inspection. Rescheduled for tomorrow
|
BLD-Energy code compliance | 10/21/2013 | 10/22/2013 | 10/22/2013 | A | PASS |
Jim Sly
|
|
|
Darren Phone #: ###-####
|
FIRE-Conference | 10/14/2013 | 10/15/2013 | 10/15/2013 | A | DONE |
Troy Cobbley
|
|
|
darren discussed sprinkler protection in the center space that may have a tenant soon
|
BLD-Framing/Rough-in | 10/14/2013 | 10/14/2013 | 10/14/2013 | P | PASS |
Jim Sly
|
|
|
darren Phone #: ###-####
|
BLD-Energy code compliance | 9/10/2013 | 9/11/2013 | 9/11/2013 | A | PART |
Jim Sly
|
|
|
Darren-Please call at least 30 mins prior to inspection Phone #: ###-#### 2 Layers 2 1/2 " roof insulation OK.
|
BLD-Footing | 8/14/2013 | 8/15/2013 | 8/15/2013 | A | PASS |
Jim Sly
|
|
|
darren Phone #: ###-#### Trash Enclosure.
|
BLD-Footing | 8/13/2013 | 8/14/2013 | 8/14/2013 | P | CANC |
Jim Sly
|
|
|
darren Phone #: ###-####
|
BLD-Footing | 8/9/2013 | 8/12/2013 | 8/12/2013 | A | PASS |
Jim Sly
|
|
|
Darren please call 30 min before going out Phone #: ###-#### Footing OK pending MTI special insp, tests and approvals
|
BLD-Footing | 8/8/2013 | 8/9/2013 | 8/9/2013 | P | NR |
Jim Storey
|
|
|
rebar - Darren Phone #: ###-####
|
BLD-Other | 8/5/2013 | 8/6/2013 | 8/6/2013 | P | PART |
Jim Sly
|
|
|
call 1/2 hr before//rebar//darren Phone #: ###-#### Remainder of tilt up panels OK pending MTI special inspections, tests and approvals.
|
BLD-Other | 7/29/2013 | 7/30/2013 | 7/30/2013 | A | PART |
Jim Sly
|
|
|
call 1/2 hr ahead//rebar // darren Phone #: ###-#### Panels 18, 19, 20, 21, 23 ,24 ,25, 26 ,27, 7 ,8 ,9, 10, 11, 12, 13, 14, 15, 16, and 17. Pending MTI special inspection, tests and approvals. Panels pending MTI inspection include.....1, 2, 3, 4, 5, 6, and trash enclosure panels. Approved plans on site.
|
FIRE-Conference | 7/11/2013 | 7/12/2013 | 7/12/2013 | A | DONE |
Troy Cobbley
|
|
|
Daren, Don and I discussed options to get the fire sprinkler supply piping down to the proper depth of cover once it leaves the United Water stub out.
|