BLD-Final | 7/16/2013 | 7/17/2013 | 7/17/2013 | P | PASS |
Tom Arcoraci
|
|
|
Brian Phone #: ###-####
|
FIRE-Final Inspection | 7/17/2013 | 7/17/2013 | 7/17/2013 | P | PASS |
Tom Arcoraci
|
|
|
all items completed
|
FIRE-Final Inspection | 7/16/2013 | 7/17/2013 | 7/17/2013 | A | FAIL |
Troy Cobbley
|
|
|
Provide panic hardware on the doors into the building lobby as per the approved plans, the door is missing from the mezzanine/stairway into the building lobby. Provide door that will maintain any rated assembly if required or get plan review approval that the door can be deleted (per later conversation with Tim it appears the door is part of a rated assembly). The fire extinguisher on the mezzanine is expired.
|
FIRE-Final Inspection | 7/10/2013 | 7/10/2013 | 7/10/2013 | P | NR |
Forrest France
|
|
|
Brian Phone #: ###-#### *Previous correction items are not completed per phone conversation with tenant*
|
FIRE-Final Inspection | 5/31/2013 | 6/3/2013 | 6/3/2013 | A | FAIL |
Forrest France
|
|
|
Modifications to the existing hood suppression system will require a permit, provide EM lighing as discussed, post accurate max. occupant load signage per current plan notes, PFE at the second level is overdue.
|