Calvary Chapel - Thrift Store Addition and Remodel - To construct a new 1,675 square foot, one story, wood framed storage and office addition on the east side of an existing 4,850 square foot, one story, concrete tilt-up retail sales building. This permit is to also construct a new 130 square foot entry vestibule on the north side of the existing building and a 730 square foot wood trellis shade structure. This permit is also to remodel the existing retail space with new finishes, new accessible restroom, janitor closet and two changing rooms, as well as, new plumbing electrical and mechanical equipment. The remodel also includes the installation of some new exterior doors and windows and some new exterior finishes. This permit also includes all related site improvements. This building is not fire sprinkled. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/8/20147/9/20147/9/2014APASS
DetailsMike Jordan
Joe Phone #: ###-####. ok for perm occ.
BLD-Footing5/29/20145/30/20145/30/2014APART
DetailsMike Jordan
Joe Phone #: ###-####. Footing inspected by strata. Ok per special inspection report. Verified non shrink grout under column base plates.
BLD-Final3/10/20143/11/20143/11/2014APASS
DetailsMike Jordan
joe Phone #: ###-####. Temp occ. given. Will be ok for perm occ. once zoning has signed perm occ.
BLD-Final3/5/20143/6/20143/6/2014PPEND
DetailsMike Jordan
Joe Phone #: ###-####. Still needs zoning final. Inspection was performed. Needs to add signs to storage racks to read no storage or above 8ft. Everything else ok.
FIRE-Final Inspection3/5/20143/6/20143/6/2014APASS
DetailsTroy Cobbley
life safety passed. Remove the thumbturn locks at the main exit doors and remove the exit sign as per the aproved plans prior to the building inspection.
BLD-Energy code compliance12/30/201312/31/201312/31/2013PPASS
DetailsMike Jordan
Joe Phone #: ###-####
BLD-Framing/Rough-in12/20/201312/23/201312/23/2013PPASS
DetailsMike Jordan
Joe Genovese Phone #: ###-####
BLD-Framing/Rough-in11/22/201311/25/201311/25/2013APASS
DetailsMike Jordan
Joe Phone #: ###-####. Exterior wood framed wall over existing concrete double T panels at west wall per RFI from engineer. Ok to cover.
BLD-Other11/19/201311/20/201311/20/2013APART
DetailsMike Jordan
roof sheathing - Joseph Phone #: ###-####. Roof sheathing attacment ok. Also noted that a resubmittal is required for the change in exterior wall finishes and framing, no details have been provided.
BLD-Footing11/12/201311/13/201311/13/2013APASS
DetailsMike Jordan
joe Phone #: ###-####. footing for new vestibule.
BLD-Foundation7/24/20137/25/20137/25/2013PPART
DetailsMike Jordan
JOE Phone #: ###-####.
BLD-Footing7/24/20137/24/20137/24/2013PPART
DetailsMike Jordan
Work in progress. Special inspector wil be on site.
BLD-Footing7/23/20137/24/20137/24/2013ANR
DetailsMike Jordan
joe Phone #: ###-####. Moved to pm.