BLD-Final | 1/16/2014 | 1/17/2014 | 1/22/2014 | A | PASS |
Dave Hannah
|
|
|
adam Phone #: ###-####
|
FIRE-Final Inspection | 1/16/2014 | 1/17/2014 | 1/17/2014 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 1/16/2014 | 1/16/2014 | 1/16/2014 | P | NR |
Jim Sly
|
|
|
Building final with Roger. Thanks AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson Need Fire life safety final.
|
FIRE-Final Inspection | 1/16/2014 | 1/16/2014 | 1/16/2014 | P | PART |
Forrest France
|
|
|
Final pending exit signage per plan review notes and comments.
|
BLD-Final | 1/14/2014 | 1/15/2014 | 1/16/2014 | P | NR |
Dave Hannah
|
|
|
Fire Life Saftey final with Dave H. Requested by Roger W. Thanks. AKJ. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
FIRE-Final Inspection | 1/14/2014 | 1/14/2014 | 1/15/2014 | P | NR |
Forrest France
|
|
|
Request for Fire Life Saftey walk by Roger W. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
FIRE-Final Inspection | 1/14/2014 | 1/15/2014 | 1/15/2014 | A | PART |
Forrest France
|
|
|
Fire Life Saftey final with Dave H. Requested by Roger W. Thanks. AKJ. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Final | 1/14/2014 | 1/14/2014 | 1/14/2014 | P | DEFR |
Tony Young
|
|
|
Request for Fire Life Saftey walk by Roger W. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Ceiling Grid Inspection | 12/10/2013 | 12/10/2013 | 12/11/2013 | P | PART |
Dave Hannah
|
|
|
6th Floor Ceiling cover scheduled per Roger W. Thanks. AKJ 12-10-13 Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok for sw corner offices
|
BLD-Wall cover | 8/23/2013 | 8/26/2013 | 8/27/2013 | A | PASS |
Dave Hannah
|
|
|
Dave, Ready for cover inspection. 6th floor. I have permit set printing right now, will have in hand first thing Monday AM. Thanks. Adam ###-#### Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|