Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberBLD13-01287
StatusFinaled
Name TRILOGY DEVELOPMENT INC
Site Address 10115 W SMOKE RANCH DR
Project NameUnion Square Apts - Phase II
Customer Number 
ePlanReviewNo
Description
(UNION SQUARE APTS)(BLDG#13) To construct a wood frame, Three story, 20,412 sq. ft., 18 Unit Multi Family Dwellings - 2 (2B/2B Type 'B'), 4 (1B/1B Type 'B'), 4 (2B/2B), and 8 (1B/1B), per reviewed plans. All units exceed 800 sq. ft., are fully sprinklered W/ alarm. Work includes associated site work, footing & foundation, structural & non-structural framing; electrical, mechanical, plumbing, sprinkler & alarm work; fire-resistive construction between units, at stair enclosures or rated corridor breezeways; accessible Type 'A' & 'B' units; interior cabinetry, wall, floor and ceiling finishes and fixtures. All work shall comply with the approved drawings, the plan review report, and all applicable codes. This building will be fire sprinkled with a 13R sprinkler system. **SRZ** DRH13-00005 CUP12-00064
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/5/20146/6/20146/5/2014APASS
DetailsMike Jordan
BLD-Final4/7/20144/8/20144/8/2014APASS
DetailsMike Jordan
ok for temp. occ. Willbe ok for perm occ. once zoning and public works signs perm.
BLD-Final4/4/20144/7/20144/7/2014PPART
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Scheduled inspection in the am to complete remainder.
FIRE-Final Inspection4/4/20144/7/20144/7/2014APASS
DetailsForrest France
Fire life safety inspection passed. Noted three dry sidewall fire sprinkler heads which need travel caps removed. Door closure at unit 305 adjusted while on site.
BLD-Wall cover1/6/20141/6/20141/6/2014APASS
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Remaining units completed. ok to tape.
BLD-Wall cover12/31/201312/31/201312/31/2013PPASS
DetailsMike Jordan
2nd floor, south units and central units ok to tape.
BLD-Wall cover12/31/201312/31/201312/31/2013ANR
DetailsMike Jordan

Moved to pm inspection.
BLD-Wall cover12/30/201312/30/201312/31/2013PDEFR
DetailsJim Storey
Wall/Ceiling screw inspection mid/late afternoon. Phone #: ###-#### >> Inspection requested via web by Mike McHargue
BLD-Wall cover12/27/201312/30/201312/30/2013APART
DetailsJim Sly
More units ready for 2nd layer on ceiling
Some ready for taping

>> Inspection requested via web by Mike McHargue
Select units.....OK 1st layer......OK 2nd layer.
BLD-Wall cover12/20/201312/23/201312/23/2013APART
DetailsMike Jordan
Wall cover lets try it again. They are suppose to work all weekend >> Inspection requested via web by Mike McHargue. base layers on 1hr. floor ceiling assemblies ok.
BLD-Wall cover12/19/201312/20/201312/20/2013PPART
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Mike McHargue3rd floor, north units, south vside only.
BLD-Energy code compliance12/9/201312/9/201312/9/2013PPASS
DetailsMike Jordan
wall & floor insulation BLDG 13 Phone #: ###-#### >> Inspection requested via web by Mike McHargue
BLD-Energy code compliance12/3/201312/4/201312/4/2013APART
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Airseal package only.
BLD-Framing/Rough-in12/3/201312/4/201312/4/2013APART
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Mike McHargue. ok to insulate. Needs to complete fireblocking at furdowns and behind tubs. Also needs to provide straps on top plates at various locations.
BLD-Energy code compliance11/27/201312/2/201312/2/2013ANR
DetailsMike Jordan
air sill Phone #: ###-#### >> Inspection requested via web by Mike McHargue
BLD-Framing/Rough-in11/27/201312/2/201312/2/2013ANR
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Mike McHargue
BLD-Framing/Rough-in11/27/201311/29/201311/27/2013ACANC
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Mike McHargue Inspection cancelled from web by: Mike McHargue
BLD-Wall Bracing10/22/201310/22/201310/22/2013PPASS
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Mike McHargue
BLD-Wall Bracing10/15/201310/17/201310/17/2013AFAIL
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Nail off belly band at 2nd. 3rd. floor at breezeway.
BLD-Wall Bracing10/9/201310/9/201310/9/2013PFAIL
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Mike McHargue. install all holdowns, install all missing floor to floor straps and pick up nailing at missing locations, 1st, 2nd, and 3rd. floors.
BLD-Concrete8/1/20138/1/20138/1/2013PCANC
DetailsMike Jordan
BLD-Concrete8/1/20138/1/20138/1/2013PPASS
DetailsMike Jordan
interior footing on south slab of building 13
Phone #: ###-#### >> Inspection requested via web by Mike McHargue
BLD-Concrete7/31/20138/1/20138/1/2013ACANC
DetailsMike Jordan
north end building 13 interior footings Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Moved to pm.
BLD-Energy code compliance7/22/20137/22/20137/22/2013PPASS
DetailsMike Jordan
Early afternoon inspection for foundation insulation on building 13. Phone #: ###-#### >> Inspection requested via web by Mike McHargue
BLD-Foundation7/19/20137/19/20137/19/2013PPASS
DetailsTom Arcoraci
Stemwall/rebar inspection Phone #: ###-#### >> Inspection requested via web by Mike McHargue
BLD-Footing7/17/20137/17/20137/17/2013PPASS
DetailsTom Arcoraci
john Phone #: ###-####
BLD-Footing7/16/20137/16/20137/16/2013PCANC
DetailsJim Sly
Bld 13 footing/rebar inspection Phone #: ###-#### >> Inspection requested via web by Mike McHargue Inspection cancelled from web by: Mike McHargue