Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD13-01397
StatusFinaled
Name BARROW DESIGN & CONSTRUCTION
Site Address 970 E BRAEMERE RD
Project Name 
Customer Number 
ePlanReviewNo
Description
WUI ZONE A, Permit for the construction of a new 3,236 sq. ft., two story (lower level 1,013 sq. ft., main level 2,223 sq. ft.) single family dwelling with 3 bedrooms, 2.5 bathrooms, 805 sq ft deck/patio and a 960 sq. ft. attached garage per the approved plans, prescriptive energy, structural engineering, statement of special inspection, plan review report and any notations. R-1B zoning and setbacks per planning. AJS All compaction testing/ fill results and a letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 384-3946.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/6/201510/7/201510/7/2015APASS
DetailsTony Young
Bob Phone #: ###-####
DOC - Permit Finaled10/7/201510/7/201510/7/2015PPASS
DetailsTony Young
c of o issued
BLD-Conference4/2/20154/3/20154/3/2015APART
DetailsTony Young
David Phone #: ###-####,, need conf on final.. call 1st,, went over corrections
BLD-Final3/30/20154/2/20154/2/2015PFAIL
DetailsTony Young
David Phone #: ###-####,, need: plans, hill side, temp glass, guardrail engineering,, rise and run of stairs,, garage step,, open risers more than 4",, insulated door to crawl,, hand rails per code,, inside and out per code,, etc
BLD-Final3/30/20153/30/20153/30/2015PNR
DetailsTony Young
David Phone #: ###-####
BLD-Final9/9/20149/9/20149/9/2014PNR
DetailsTony Young
David Phone #: ###-####
BLD-Other5/15/20145/15/20145/15/2014PPART
DetailsTony Young
Fire soffits and exterior wall - David Phone #: ###-####
BLD-Other5/14/20145/15/20145/15/2014APART
DetailsTony Young
Fire soffits and exterior wall - David Phone #: ###-####,, wall ok
BLD-Other5/14/20145/14/20145/14/2014PPART
DetailsTony Young
Fire soffits - David Phone #: ###-####,, work in progress,, ok
BLD-Wall Bracing5/7/20145/8/20145/8/2014APASS
DetailsTony Young
david Phone #: ###-####,, interior shear
BLD-Energy code compliance5/6/20145/7/20145/8/2014PPASS
DetailsTony Young
david Phone #: ###-####
BLD-Framing/Rough-in5/6/20145/7/20145/8/2014PPASS
DetailsTony Young
david Phone #: ###-####
BLD-Framing/Rough-in4/30/20145/1/20145/1/2014PPASS
DetailsJim Sly
Roger Phone #: ###-####
BLD-Wall Bracing4/28/20144/29/20144/29/2014APART
DetailsTony Young
roger Phone #: ###-####,, exterior shear ok to cover,,, will put other straps inside and will have interior shear
BLD-Wall Bracing4/25/20144/28/20144/28/2014ADEFR
DetailsTony Young
roger Phone #: ###-####
BLD-Wall Bracing4/24/20144/25/20144/25/2014AFAIL
DetailsTony Young
roger Phone #: ###-####,, need plans,, nail panel edges
BLD-Conference4/11/20144/14/20144/14/2014APART
DetailsTony Young
Roger Phone #: ###-####,, call 30 min,, frame walk through
BLD-Conference4/11/20144/11/20144/11/2014PDEFR
DetailsTony Young
Roger Phone #: ###-####,, frame ?s,,
BLD-Footing8/27/20138/27/20138/27/2013PPART
DetailsTony Young
steve Phone #: ###-####,, 90%,, ok
BLD-Footing8/26/20138/27/20138/27/2013APART
DetailsTony Young
steve Phone #: ###-####,, work in progress.. 80%
BLD-Conference8/26/20138/26/20138/27/2013PPART
DetailsTony Young
steve Phone #: ###-####,, ?s on rebar,, pre conf.