BLD-Final | 1/23/2014 | 1/23/2014 | 1/23/2014 | P | PASS |
Tony Young
|
|
|
Request for final inspection sign off of Ruth''s Chris restaurant. Electrical will be signed off by Noon. Please contact Adam when available, ###-####. Thanks. Phone #: ###-#### >> Inspection requested via web by Adam Johnson,,, ok for perm c of o
|
FIRE-Final Inspection | 1/21/2014 | 1/22/2014 | 1/23/2014 | P | PASS |
Craig D. Hanson
|
|
|
emergency lighting and generator pass
|
BLD-Conference | 1/21/2014 | 1/22/2014 | 1/22/2014 | A | PASS |
Dave Hannah
|
|
|
Meeting on site with Dave H. requested in ESI field office, followed by site visit if necessary. Please call Adam with any questions. ###-#### Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
FIRE-Final Inspection | 1/21/2014 | 1/21/2014 | 1/22/2014 | P | FAIL |
Craig D. Hanson
|
|
|
Emergency generator failure, Emergency lighting failure.
|
BLD-Ceiling Grid Inspection | 1/7/2014 | 1/8/2014 | 1/9/2014 | A | PASS |
Dave Hannah
|
|
|
Ceiling Grid Inspection, AM Wednesday, Ruths Chris, Per Mike Beeson. Thanks AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 12/6/2013 | 12/9/2013 | 12/9/2013 | A | PASS |
Dave Hannah
|
|
|
Follow up documentation to Fridays inspection of Ruths Chris w/Mike Beeson. Thanks. akj Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok to cover the rest of the hard ceilings
|
BLD-Framing/Rough-in | 11/22/2013 | 11/25/2013 | 11/25/2013 | A | PASS |
Dave Hannah
|
|
|
Framing inspection of Ruths Chris, 1st Floor. Per Mike Beeson, thanks. akj Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 11/6/2013 | 11/6/2013 | 11/7/2013 | P | PART |
Dave Hannah
|
|
|
Framing inspection of Ruths Chris, 8th and Main 1st Floor, Mike Beeson, Thanks. ###-#### Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok to cover walls servce area
|
BLD-Conference | 10/31/2013 | 11/1/2013 | 11/1/2013 | A | PART |
Dave Hannah
|
|
|
Permit was Pulled 10-31, Plans sent to print shop, if you could do a framing inspection around 10-10:30 please. Call Adam to confirm Plans on site to coordinate. ###-#### Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok to cover walls inkitchen area.
|