BLD-Final | 2/13/2014 | 2/14/2014 | 2/14/2014 | P | PASS |
Dave Hannah
|
|
|
Reinspection of 17th Floor Holland and Hart after walk with Forrest. Coordinate with Adam for inspection. Crews will be on site to drop power and test MAG locks for Forrest. Thanks. AKJ >> Inspection requested via web by Adam Johnson
|
FIRE-Final Inspection | 2/13/2014 | 2/14/2014 | 2/14/2014 | A | PASS |
Forrest France
|
|
|
Previous C/N items verified for completion. Fire life safety passed.
|
BLD-Final | 2/10/2014 | 2/11/2014 | 2/12/2014 | P | NR |
Dave Hannah
|
|
|
Final inspection request of H&H 17th Floor. Adam will walk with you for this inspection. Thanks. AKJ. Phone #: ###-#### >> Inspection requested via web by Adam Johnson needs fire life saftey final first
|
FIRE-Final Inspection | 2/10/2014 | 2/11/2014 | 2/11/2014 | P | PART |
Forrest France
|
|
|
Final pending relay to the fire alarm panel at the main entry/exit door mags, post max occupant signage at the meeting room.
|
BLD-Framing/Rough-in | 12/30/2013 | 12/30/2013 | 12/31/2013 | P | PART |
Dave Hannah
|
|
|
Framing inspection requested by John Woods, FCS, 17th Floor Holland and Hart. Thanks, AKJ. Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok to cover hard lids each side of elevators
|
BLD-Framing/Rough-in | 12/10/2013 | 12/10/2013 | 12/11/2013 | P | PASS |
Dave Hannah
|
|
|
Faming inspection walk requested by John Woods FCS. Thanks. akj 12-10-13 Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 11/22/2013 | 11/22/2013 | 11/25/2013 | P | PART |
Dave Hannah
|
|
|
Framing Holland and Hart, 17th Floor. Thanks. Adam. Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok to one side int walls
|
BLD-Framing/Rough-in | 10/1/2013 | 10/1/2013 | 10/3/2013 | P | NR |
Dave Hannah
|
|
|
17th Floor, Holland and Hart, East and South Sections. Thanks. Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|