BLD-Final | 2/12/2014 | 2/13/2014 | 2/13/2014 | A | PASS |
Mike Jordan
|
|
|
Al Huerta Phone #: ###-####
|
DOC - Permit Finaled | 2/13/2014 | 2/13/2014 | 2/13/2014 | P | PASS |
Mike Jordan
|
|
|
Certificate of completion issued.
|
FIRE-Final Inspection | 2/12/2014 | 2/12/2014 | 2/12/2014 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Framing/Rough-in | 2/5/2014 | 2/5/2014 | 2/5/2014 | P | PART |
Mike Jordan
|
|
|
Albert Phone #: ###-####. Interior steel stud walls for new storage room.
|
BLD-Framing/Rough-in | 2/4/2014 | 2/4/2014 | 2/4/2014 | P | PASS |
Mike Jordan
|
|
|
for phase 3 // Al Phone #: ###-####. Interior steel stud framed walls ok.
|
BLD-Framing/Rough-in | 1/28/2014 | 1/28/2014 | 1/28/2014 | P | PASS |
Mike Jordan
|
|
|
richard Phone #: ###-####. Phase 2 interior steel stud framed walls at north east portion of building and front column at main door. All screws were removed and and kickers added.
|
BLD-Framing/Rough-in | 1/27/2014 | 1/28/2014 | 1/28/2014 | A | FAIL |
Mike Jordan
|
|
|
phase 2 - Richard Phone #: ###-####. Rermove screws from grid to top plate and install kickers to structure above.
|
BLD-Framing/Rough-in | 1/16/2014 | 1/16/2014 | 1/16/2014 | P | PASS |
Mike Jordan
|
|
|
partial r/i for phase 1 // Richard Phone #: ###-####. interior steel stud walls for 5 way mirror dressing rooms, phase 1.
|
BLD-Framing/Rough-in | 1/8/2014 | 1/9/2014 | 1/9/2014 | A | PART |
Mike Jordan
|
|
|
phase 1 framing - Richard Phone #: ###-####. phase 1, interior steel stud framed walls for new storefront showcases. Pending electrical rough in inspection.
|