BLD-Final | 9/24/2014 | 9/24/2014 | 9/24/2014 | P | PASS |
Mike Jordan
|
|
|
Curt Phone #: ###-####. Ok for prm. occ.
|
FIRE-Final Inspection | 8/14/2014 | 8/14/2014 | 8/14/2014 | P | PASS |
Forrest France
|
|
|
Verified plan resubmittals and previous correction items. Life safety final approved.
|
BLD-Final | 8/14/2014 | 8/14/2014 | 8/14/2014 | P | PART |
Mike Jordan
|
|
|
call before// Curt Phone #: ###-####. Ok for temp occ. Needs to install high/low drinking fountain.
|
FIRE-Final Inspection | 7/8/2014 | 7/9/2014 | 7/9/2014 | A | FAIL |
Troy Cobbley
|
|
|
Resubmit plans showing the correct door/exit path layout with the desited exit sign arrangement for approval. Also show the new wall being deleted. Install fire extinguisher as discussed.
|
BLD-Conference | 5/12/2014 | 5/13/2014 | 5/13/2014 | A | DONE |
Mike Jordan
|
|
|
Kurt-pleae call for access Phone #: ###-####
|
BLD-Energy code compliance | 2/24/2014 | 2/24/2014 | 2/24/2014 | P | PASS |
Mike Jordan
|
|
|
Curtis Phone #: ###-####
|
BLD-Framing/Rough-in | 2/14/2014 | 2/18/2014 | 2/18/2014 | P | PASS |
Mike Jordan
|
|
|
Curt Phone #: ###-####. All framing issues resolved. Ok to insulate.
|
BLD-Framing/Rough-in | 2/11/2014 | 2/11/2014 | 2/11/2014 | P | FAIL |
Mike Jordan
|
|
|
curtis Phone #: ###-####. Airseal pack to be completed prior to framing inspection. Provide additional nailing on 3 ply T03 truss as well as the required 14 SDS screws on 2x6 blocks at both bearing ends. Correction notice posted.
|
BLD-Wall Bracing | 1/8/2014 | 1/9/2014 | 1/9/2014 | A | PASS |
Mike Jordan
|
|
|
Curt Phone #: ###-####. North wall ok to cover.
|
BLD-Other | 1/6/2014 | 1/6/2014 | 1/6/2014 | P | PART |
Mike Jordan
|
|
|
curt - shear inspection Phone #: ###-####. Needs to complete the north side of building, connect holddowns, and complete sheathing.
|
BLD-Foundation | 10/25/2013 | 10/28/2013 | 10/28/2013 | A | PASS |
Mike Jordan
|
|
|
JOHN Phone #: ###-####
|
BLD-Foundation | 10/24/2013 | 10/25/2013 | 10/25/2013 | P | CANC |
Mike Jordan
|
|
|
John Phone #: ###-####
|
BLD-Footing | 10/25/2013 | 10/25/2013 | 10/25/2013 | P | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####. All issues have been resolved.
|
BLD-Footing | 10/25/2013 | 10/25/2013 | 10/25/2013 | A | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####. All issues have been resolved. 2500 psi for design, clearance issues resolved. also noted per engineers letter that as built condtion at existing building is acceptable.
|
BLD-Footing | 10/21/2013 | 10/22/2013 | 10/22/2013 | A | FAIL |
Mike Jordan
|
|
|
John MIller Phone #: ###-####. Provide additional chairs on north footing line to provide the min. required clearances. Provide RFI from engineer for change in field conditions for connection to existing footing. Provide specified conc psi to be used and concrete design psi by engineer. Correction notice posted. Also noted ESC issues. No concrete allowed at this time.
|