BLD-Final | 1/16/2014 | 1/16/2014 | 1/16/2014 | P | PASS |
Jim Sly
|
|
|
13th floor final with Roger W. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson OK for Perm Occ.
|
FIRE-Final Inspection | 1/16/2014 | 1/16/2014 | 1/16/2014 | P | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
BLD-Final | 1/14/2014 | 1/15/2014 | 1/16/2014 | P | NR |
Dave Hannah
|
|
|
Final walk request by Roger Wilson, walk with Dave H. 13th Floor PB&L. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
FIRE-Final Inspection | 1/14/2014 | 1/15/2014 | 1/15/2014 | A | PART |
Forrest France
|
|
|
Fire Final Prewalk with Forrest, requested by Roger Wilson, 13th Floor PB&L. Thanks AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Ceiling Grid Inspection | 12/11/2013 | 12/11/2013 | 12/12/2013 | P | PASS |
Dave Hannah
|
|
|
Ceiling cover inspection on 13th Floor PB&L, per Roger W. Thanks. akj Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 10/27/2013 | 10/28/2013 | 10/28/2013 | A | PASS |
Tom Arcoraci
|
|
|
Fireproof patch inspection requested per Roger Wilson, ESI, on 13th Floor. Thanks. Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 10/3/2013 | 10/4/2013 | 10/7/2013 | A | PASS |
Dave Hannah
|
|
|
Follow up from yesterday, conformation of FP at perimeter, thanks. Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 10/2/2013 | 10/3/2013 | 10/7/2013 | A | PASS |
Dave Hannah
|
|
|
Framing Inspection Thanks. Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 10/1/2013 | 10/1/2013 | 10/7/2013 | P | PASS |
Dave Hannah
|
|
|
PB&L Framing Inspection, 13th Floor. Thanks. Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|