Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD13-02305
StatusFinaled
Name ALPINE CONSTRUCTION INC
Site Address 225 N 9TH ST Unit: 200
Project NameCLEARWATER ANALYTICS
Customer Number 
ePlanReviewYes
Description
(CLEARWATER ANALYTICS-Suite 200) (Sedgewick Building)Plan Modification 1/10/14 to include conference room as shown on submitted floor plan and revised occupant load. Permit for T.I of existing tenant space on second floor. Tenant space created under BLD12-01166. Scope of work to include; demo of existing partition was per approved plans. Construction of new nonbearing partition walls for new office lay out including new break room per approved plans. Interior finish shall be per chapter 8, IBC.This building is fire sprinklered to meet high rise provisions. There is 1 conference roomr, office space, office space and break rooms space. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/13/20141/14/20141/14/2014APASS
DetailsMike Jordan
call 30 min ahead // Garrett Phone #: ###-####. Ok for perm. occ.
FIRE-Final Inspection1/13/20141/14/20141/14/2014APASS
DetailsTroy Cobbley
life safety passed
BLD-Final11/26/201311/27/201311/27/2013APASS
DetailsTom Arcoraci
GARRETT please call 30 min before going out Phone #: ###-####
FIRE-Final Inspection10/16/201310/16/201310/16/2013PPASS
DetailsForrest France
For verification of repairs and revised locations of EM lights.
BLD-Final10/15/201310/16/201310/16/2013APART
DetailsDave Hannah
Garrett Phone #: ###-#### ok for temp occ needs to install one door and side lights
FIRE-Final Inspection10/15/201310/15/201310/15/2013PPASS
DetailsForrest France
Fire life safety okay pending EM lights and one exit sign are repaired or provided per plan as discussed. MIssing door/frame and glass to be completed prior to structural final.
BLD-Other10/7/201310/8/201310/9/2013APASS
DetailsDave Hannah
Garrett Phone #: ###-#### ok to cover ceiling grid
FIRE-Sprinkler Rough-in10/3/201310/3/201310/3/2013PPART
DetailsForrest France
Overhead fire sprinkler work okayed to cover as noted.
BLD-Framing/Rough-in9/23/20139/24/20139/24/2013APASS
DetailsDave Hannah
Garrett Phone #: ###-####
BLD-Framing/Rough-in9/19/20139/20/20139/20/2013APASS
DetailsDave Hannah
garrett Phone #: ###-####