BLD-Final | 2/27/2014 | 2/27/2014 | 2/27/2014 | P | PASS |
Dave Hannah
|
|
|
Adam - call for access Phone #: ###-####
|
BLD-Final | 2/24/2014 | 2/26/2014 | 2/26/2014 | P | PART |
Dave Hannah
|
|
|
Final BLD inspection request, coordinate with Korey or Adam for walk. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok for temp occ
|
FIRE-Final Inspection | 2/24/2014 | 2/26/2014 | 2/26/2014 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Ceiling Grid Inspection | 2/19/2014 | 2/19/2014 | 2/20/2014 | P | PASS |
Dave Hannah
|
|
|
Ceiling grid inspection. 2nd half requested by Kory, second floor Zenergy t.i. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Ceiling Grid Inspection | 2/14/2014 | 2/14/2014 | 2/19/2014 | P | PART |
Dave Hannah
|
|
|
Ceiling inspection walk of Zenergy, 2nd floor. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok to cover hallways
|
BLD-Ceiling Grid Inspection | 2/6/2014 | 2/7/2014 | 2/7/2014 | A | PASS |
Dave Hannah
|
|
|
Follow up to on site ceiling grid inspection, follow up of added wires requested by Dave Hannah. Thanks. AKJ. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 1/7/2014 | 1/7/2014 | 1/9/2014 | P | PART |
Dave Hannah
|
|
|
adam Phone #: ###-#### fire proofing ok ok to cover all walls
|
BLD-Framing/Rough-in | 12/27/2013 | 1/2/2014 | 1/3/2014 | A | PASS |
Dave Hannah
|
|
|
Adam @ ###-####
|