BLD-Final | 2/20/2014 | 2/21/2014 | 2/21/2014 | A | PASS |
Dave Hannah
|
|
|
Reinspection of MMC 12th Floor, Fire Final, Coordinate with Adam or Bob for inspection. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
FIRE-Final Inspection | 2/20/2014 | 2/21/2014 | 2/21/2014 | A | PASS |
Forrest France
|
|
|
C/N items verified. Fire life safety passed. *Note- fire sprinkler coverage at the shell areas to be maintained at new demising walls as discussed on site.
|
BLD-Final | 2/19/2014 | 2/20/2014 | 2/20/2014 | P | PEND |
Dave Hannah
|
|
|
Final walk MMC TI, 12th Floor. Coordinate with Adam or Bob for walk. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok after fire finals
|
FIRE-Final Inspection | 2/19/2014 | 2/20/2014 | 2/20/2014 | A | FAIL |
Forrest France
|
|
|
C/N items include; repair one EM light at the main entry, replace missing ceiling tile, obstruction to fire sprinkler coverage at the server room, post suite address numbers, replace missing escutcheon at the conference room, check pendent sprinkler head at the east office adjacent to the server room for physical damage.
|
BLD-Ceiling Grid Inspection | 2/4/2014 | 2/4/2014 | 2/5/2014 | P | PASS |
Dave Hannah
|
|
|
Request for Partial ceiling inspection, 12th floor MMC. VAV unit stalled in shipment, but would like to flood the rest of the suite. Please check in with Adam or Bob. Thanks. AKJ. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 12/16/2013 | 12/16/2013 | 12/17/2013 | P | PASS |
Dave Hannah
|
|
|
Inspection request for MMC, 12th Floor, per Bob L. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|