Permit Information
Permit NumberBLD13-03185
StatusFinaled
Name BENITON CONSTRUCTION
Site Address 2650 S ORCHARD ST
Project NameMAVERIK
Customer Number 
ePlanReviewYes
Description
" MAVERIK " For the construction of a new 4, 790 sq. ft. Maverick convenience store with the associated 6,900 sq. ft. fuel canopy with work to include grading and associated ground work foundation and building construction.All work per the approved plans and any notations. This building is not fire sprinklered. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/13/20151/14/20151/13/2015APASS
DetailsPhil Shearer
Richard Phone #: ###-####
FIRE-Final Inspection1/13/20151/14/20151/13/2015APASS
DetailsTroy Cobbley
life safety passed
BLD-Final1/12/20151/12/20151/12/2015PCANC
DetailsPhil Shearer
Please return after all signatures are logged into system to review for final inspection and C of O Phone #: ###-#### Inspection requested via web by Richard Fontaine
FIRE-Final Inspection1/12/20151/12/20151/12/2015PFAIL
DetailsTroy Cobbley
Need to provide fire dept approval on tanks, scott has approved existing fire dept access without utilizing the east side driveway, and the two emergency stop buttons along Orchard Street do not work.
BLD-Final1/7/20151/9/20151/9/2015PCANC
DetailsPhil Shearer
Please come after 3 pm for final inspection. Phone #: ###-#### Inspection requested via web by Richard Fontaine
FIRE-Final Inspection1/7/20151/9/20151/9/2015AFAIL
DetailsTroy Cobbley
See posted correction notice that includes: Provide fire dept sign off, remove thumbturn on main exit and provide sticker, remove deadbolt from beer cooler door, provide all small documents including fire dept review comments, repair and finish installing exit discharge lighting, test duct smoke detectors, provide signage for emergency stop and at gas pumps, test emergency stop...ect.
BLD-Final1/8/20151/9/20151/9/2015ACANC
DetailsPhil Shearer
Richard Phone #: ###-####
BLD-Final1/7/20151/7/20151/7/2015PCANC
DetailsPhil Shearer
Please come around 3pm for the final walkthru Phone #: ###-#### >> Inspection requested via web by Richard Fontaine Inspection cancelled from web by: Richard Fontaine
FIRE-Conference12/12/201412/12/201412/12/2014PDONE
DetailsTroy Cobbley
Discussed address placement
BLD-Wall cover11/24/201411/24/201411/24/2014PPASS
DetailsPhil Shearer
Please inspect wall cover later in the afternoon. Phone #: ###-#### Inspection requested via web by Richard Fontaine
BLD-Energy code compliance11/20/201411/21/201411/21/2014APASS
DetailsPhil Shearer
Please come early AM to inspect interior insulation prior to Sheetrock Phone #: ###-#### Inspection requested via web by Richard Fontaine
BLD-Framing/Rough-in11/21/201411/21/201411/21/2014PPASS
DetailsPhil Shearer
Please come early AM to inspect interior insulation prior to Sheetrock Phone #: ###-#### Inspection requested via web by Richard Fontaine
BLD-Framing/Rough-in11/18/201411/19/201411/19/2014PPART
DetailsPhil Shearer
Please inspect towards the end of the day on Wednesday for approval to insulate. Phone #: ###-#### Inspection requested via web by Richard Fontaine. ok except for front high wall has not passed electrical inspection
BLD-Framing/Rough-in11/12/201411/13/201411/13/2014PPART
DetailsPhil Shearer
Partial wall inspection prior to partial insulation behind beer cooler Phone #: ###-#### Inspection requested via web by Richard Fontaine.
BLD-Wall Bracing10/31/201411/3/201411/3/2014PPASS
DetailsPhil Shearer
Shear wall inspection sometime during the afternoon please. Phone #: ###-#### Inspection requested via web by Richard Fontaine
BLD-Energy code compliance9/30/20149/30/20149/30/2014PPASS
DetailsPhil Shearer
Please inspect the foundation insulation around 3 pm Phone #: ###-#### Inspection requested via web by Richard Fontaine
BLD-Foundation9/25/20149/29/20149/29/2014APASS
DetailsPhil Shearer
We are pouring the foundation stem walls at 10 am. Please inspect prior Phone #: ###-#### Inspection requested via web by Richard Fontaine
BLD-Footing9/22/20149/24/20149/24/2014APASS
DetailsPhil Shearer
We are pouring building footings at 10 a.m. Please inspect prior to this. Phone #: ###-#### Inspection requested via web by Richard Fontaine
BLD-Footing9/17/20149/18/20149/18/2014APASS
DetailsPhil Shearer
Canopy column footings and overview of work to be performed. (Conference) Phone #: ###-#### Inspection requested via web by Richard Fontaine