BLD-Other | 2/18/2014 | 2/19/2014 | 2/19/2014 | A | PASS |
Mike Jordan
|
|
|
Mike, I have replace the existing window glass with tempered as required. Phone #: ###-#### >> Inspection requested via web by Miles Hash. Ok to occupy the remodeled offices on main sales floor. waiting on resubmittals for changes to the upstairs remodel.
|
BLD-Other | 2/12/2014 | 2/13/2014 | 2/13/2014 | A | PART |
Mike Jordan
|
|
|
pre building final conference walk. thanks Miles Phone #: ###-#### >> Inspection requested via web by Miles Hash. Partial final only. Ok to occupy down stairs remodeled offices except for two offices were tempered glazing is required. Life/safety and other trades have been signed off. Architect trying to submit plan mod for changes upstairs, so partial final only in area noted above.
|
FIRE-Final Inspection | 2/11/2014 | 2/12/2014 | 2/12/2014 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Door hardware not installed yet but I went over requirements with superintendant.
|
BLD-Ceiling Grid Inspection | 2/7/2014 | 2/7/2014 | 2/7/2014 | P | DONE |
Jim Sly
|
|
|
Offices......OK
|
BLD-Ceiling Grid Inspection | 2/6/2014 | 2/7/2014 | 2/7/2014 | A | CANC |
Mike Jordan
|
|
|
come in the north entry at the Toyota sign Phone #: ###-#### >> Inspection requested via web by Miles Hash. Moved to pm.
|
BLD-Framing/Rough-in | 1/17/2014 | 1/21/2014 | 1/21/2014 | A | PASS |
Jim Sly
|
|
|
call me to find area thanks Phone #: ###-#### >> Inspection requested via web by Miles Hash
|