BLD-Final | 9/9/2015 | 9/10/2015 | 9/10/2015 | P | PASS |
Mike Jordan
|
|
|
Please call with 15 minute lead time. Thank you, Scott Phone #: ###-#### Inspection requested via web by Scott Zierler
|
FIRE-Final Inspection | 9/9/2015 | 9/10/2015 | 9/10/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 8/31/2015 | 9/1/2015 | 9/1/2015 | P | FAIL |
Troy Cobbley
|
|
|
Need city approved plans and the one painted pendant, of the two in the furnace room, replaced.
|
BLD-Conference | 8/24/2015 | 8/25/2015 | 8/25/2015 | A | DONE |
Mike Jordan
|
|
|
Preliminary walk through for final. Thanks. Phone #: ###-#### Inspection requested via web by Scott Zierler. Needs door hardware installed, life/safety and zoning finals.
|
BLD-Conference | 8/21/2015 | 8/24/2015 | 8/24/2015 | P | CANC |
Mike Jordan
|
|
|
Preliminary meeting before going for building final. Thanks Scott Phone #: ###-#### >> Inspection requested via web by Scott Zierler Inspection cancelled from web by: Scott Zierler
|
BLD-Energy code compliance | 3/27/2015 | 3/27/2015 | 3/27/2015 | P | PASS |
Mike Jordan
|
|
|
Added rockwool insulation to all condensate line penetration into floor assembly. Thanks! Phone #: ###-#### Inspection requested via web by Scott Zierler
|
BLD-Framing/Rough-in | 3/24/2015 | 3/25/2015 | 3/25/2015 | P | PASS |
Mike Jordan
|
|
|
Three times a charm? Call me when you are heading over. I found 14 holes that needed caulk. Will have caulk gun with me. Thanks Phone #: ###-#### Inspection requested via web by Scott Zierler. All issues resolved. ok to insulate.
|
BLD-Framing/Rough-in | 3/19/2015 | 3/20/2015 | 3/19/2015 | A | CANC |
Mike Jordan
|
|
|
Pat Phone #: ###-####. cancelled per contractor.
|
BLD-Framing/Rough-in | 3/18/2015 | 3/18/2015 | 3/18/2015 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Zierler. Still noted several penetrations in the floor ceiling assembly that are unprotected. See posted correction notice for locations. Nail off TBE in unit #5.
|
BLD-Framing/Rough-in | 3/16/2015 | 3/17/2015 | 3/17/2015 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Zierler. Noted some areas not firecaulked. Needs to nail off TBE and provide the additional studs for the interior columns on 2nd floor.
|
BLD-Framing/Rough-in | 3/13/2015 | 3/16/2015 | 3/16/2015 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Scott Zierler Inspection cancelled from web by: Scott Zierler
|
BLD-Framing/Rough-in | 3/12/2015 | 3/13/2015 | 3/13/2015 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Scott Zierler Inspection cancelled from web by: Scott Zierler
|
BLD-Framing/Rough-in | 2/24/2015 | 2/25/2015 | 2/25/2015 | P | FAIL |
Mike Jordan
|
|
|
Thanks! Phone #: ###-#### Inspection requested via web by Scott Zierler. Complete firecaulking, provide adequate support for beams in closet in upstairs unit, Provide TBE on CG2 truss.
|
BLD-Wall Bracing | 12/17/2014 | 12/18/2014 | 12/18/2014 | P | PASS |
Mike Jordan
|
|
|
Reinspection Phone #: ###-#### Inspection requested via web by Scott Zierler. All exterior shear ok.
|
BLD-Wall Bracing | 12/17/2014 | 12/17/2014 | 12/17/2014 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Zierler
|
BLD-Other | 12/17/2014 | 12/17/2014 | 12/17/2014 | P | PASS |
Mike Jordan
|
|
|
Inspection for separation wall insulation. Phone #: ###-#### Inspection requested via web by Scott Zierler
|
BLD-Other | 10/29/2014 | 10/29/2014 | 10/29/2014 | P | PASS |
Mike Jordan
|
|
|
Inspection of fire wall insulation prior to cover. At new framed building 715 Mitchell Phone #: ###-#### Inspection requested via web by Scott Zierler. oK to sheetrock party walls and corridor walls.
|
BLD-Conference | 9/23/2014 | 9/24/2014 | 9/24/2014 | A | PART |
Mike Jordan
|
|
|
Floor inspection Phone #: ###-#### Inspection requested via web by Scott Zierler. 1hr. fire partition from footing to underneath side of floor.
|
BLD-Foundation | 6/18/2014 | 6/19/2014 | 6/19/2014 | P | PASS |
Mike Jordan
|
|
|
Heron Phone #: ###-####
|
BLD-Footing | 6/18/2014 | 6/18/2014 | 6/18/2014 | P | PART |
Mike Jordan
|
|
|
Heron Phone #: ###-####
|
BLD-Footing | 5/29/2014 | 5/30/2014 | 5/30/2014 | A | CANC |
Mike Jordan
|
|
|
Juron Phone #: ###-####
|