BLD-Final | 8/21/2014 | 8/22/2014 | 8/22/2014 | A | PASS |
Jim Sly
|
|
|
Ed Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 8/22/2014 | 8/22/2014 | 8/22/2014 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 8/21/2014 | 8/21/2014 | 8/21/2014 | P | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm permit addressed and the exit signs and emergency lights added as per the Review Comments.
|
BLD-Ceiling Grid Inspection | 7/31/2014 | 8/1/2014 | 8/1/2014 | A | PART |
Jim Sly
|
|
|
Ed Phone #: ###-#### B hall OK.
|
BLD-Ceiling Grid Inspection | 7/23/2014 | 7/23/2014 | 7/23/2014 | P | PART |
Jim Sly
|
|
|
Ed Cuttlers Phone #: ###-#### Select ceilings
|
FIRE-Conference | 7/22/2014 | 7/22/2014 | 7/23/2014 | P | DONE |
Troy Cobbley
|
|
|
Matt Forester Phone #: ###-####
Per discussion with Tim Frost and Romeo Gervais the "end gap" of the new ceiling assemble at the windows will be allowed without a requirement to "box-in" the ends.
Per conversation with Romeo Gervais the limited existing ceiling tile, installed above the conduit and wire mold, will be allowed to remain.
|
BLD-Framing/Rough-in | 7/21/2014 | 7/21/2014 | 7/21/2014 | P | PASS |
Mike Jordan
|
|
|
Above ceiling inspection please Phone #: ###-####. Girls east shower and boys shower, girls west ADA shower ok.
|
BLD-Conference | 7/9/2014 | 7/10/2014 | 7/10/2014 | A | DONE |
Jim Sly
|
|
|
Ed Phone #: ###-#### Walk thru done.
|