Permit Information
Permit NumberBLD13-03418
StatusIssued
Name CM COMPANY
Site Address 150 N CAPITOL BLVD
Project NameBOISE CITY HALL
Customer Number 
ePlanReviewYes
Description
(BOISE CITY HALL – Phase II Code Improvements) The main scope of work within this permit is to upgrade the existing parking garage, Annex and CH2 to make them more seismically resistant. PLAN MODIFICATION 10-8-12 – Modification submitted to reconfigure the HR Dept. area. The area will now be mostly all open office without walls dividing the space into individual office. **TLW** A tenant improvement for a portion of the HR Dept in the Annex is also included within this scope of work. Work is to include: [structural upgrades including: new concrete sheer walls, new collectors, repair concrete beams, and concrete deck repair], [construction of interior non-bearing walls to create eight private offices, a conference room, and a copy room], exterior site improvements, and interior finishes. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Other2/14/20182/15/20182/16/2018PNR
DetailsDave Hannah
Railing and Guardrail Inspection on Main Street Stairs and Patios. Prior to tearing down fence. Phone #: ###-#### Inspection requested via web by Anna Ellis
BLD-Final6/25/20156/25/20157/2/2015PPEND
DetailsDave Hannah
Dennis Phone #: ###-#### needs a final letter on all spec inspections
FIRE-Final Inspection6/24/20156/24/20156/24/2015PPASS
DetailsJim Page
Life fire safety inspection, HR, Annex passed/complete
BLD-Final3/31/20154/1/20154/2/2015APEND
DetailsDave Hannah
Bruce Phone #: ###-####ok to occ the I T area print shop
FIRE-Final Inspection3/31/20154/1/20154/1/2015APART
DetailsForrest France
Fire life safety walkthrough completed for the print office 147A, IT 151, flex office 153, HR office 154/155, IT work area and hall 170/171. Hardware at the HR office revised while on site, hardware at the print shop to storage area/restroom vestibules to be corrected as discussed.
BLD-Ceiling Grid Inspection3/17/20153/18/20153/18/2015APASS
DetailsDave Hannah
Phone #: ###-####
FIRE-Final Inspection2/18/20152/19/20152/19/2015APART
DetailsForrest France
Preliminary walkthrough of the cafeteria area and adjacent corridor regarding fire life safety items. Cafe area EM lights and exit signs tested okay. Discussed locations of exit signs at the corridor.
BLD-Framing/Rough-in2/18/20152/19/20152/19/2015APASS
DetailsDave Hannah
###-####-IT room
BLD-Ceiling Grid Inspection2/13/20152/17/20152/17/2015APASS
DetailsBob Archibald
Cafateria - 1st thing please - Bruce Phone #: ###-####
BLD-Final1/21/20151/23/20151/23/2015APEND
DetailsDave Hannah
bruce Phone #: ###-#### ok to move into hr area
FIRE-Final Inspection1/21/20151/23/20151/23/2015APART
DetailsForrest France
Completed fire life safety walkthrough of the HR dept. remodel area first floor- 6th street exit access and egress path to be maintained available as discussed.
BLD-Framing/Rough-in1/14/20151/15/20151/15/2015APART
DetailsDave Hannah
Bruce Phone #: ###-#### kitchen area by front door ok after elec oks
BLD-Conference1/14/20151/15/20151/15/2015ADONE
DetailsDave Hannah
Bruce Phone #: ###-####
BLD-Ceiling Grid Inspection1/7/20151/9/20151/9/2015APART
DetailsDave Hannah
Dennis-print shop and HR dept-call to meet for inspection Phone #: ###-#### ok to cover hr area after other trades ok
BLD-Conference12/22/201412/23/201412/23/2014APASS
DetailsDave Hannah
bruce Phone #: ###-####
BLD-Framing/Rough-in12/12/201412/15/201412/15/2014APASS
DetailsDave Hannah
Bruce-CH2 basement east side, CH@ 4th floor east side, Annex print shop Phone #: ###-####
BLD-Framing/Rough-in11/12/201411/12/201411/13/2014PPART
DetailsDave Hannah
Bruce Phone #: ###-#### ok to insulate nw section ext walls and cover int walls
BLD-Ceiling Grid Inspection10/8/201410/9/201410/10/2014APASS
DetailsDave Hannah
CH2 4th lobby - Bruce Phone #: ###-####
BLD-Framing/Rough-in9/22/20149/23/20149/24/2014PPASS
DetailsDave Hannah
CH2 - 3rd fl - Bruce Phone #: ###-####
BLD-Ceiling Grid Inspection8/28/20148/29/20148/29/2014APASS
DetailsDave Hannah
2nd fl lobby - Bruce Phone #: ###-####
BLD-Framing/Rough-in8/22/20148/25/20148/25/2014APASS
DetailsDave Hannah
ch 2, 2nd floor lobby Phone #: ###-####
FIRE-Conference8/5/20148/5/20148/5/2014PPART
DetailsForrest France
Inspection for verification of adjusted fire sprinkler coverage at the first floor office 103 completed.
BLD-Conference7/29/20147/30/20147/31/2014APART
DetailsDave Hannah
Conference for Phased finals at basement and 1st floor CH2 at west side Phone #: ###-#### phase one these areas are ok
FIRE-Final Inspection7/29/20147/30/20147/30/2014APART
DetailsForrest France
Phase one work at the basement level west side CH2 elevator lobby sheet A100 okayed. Phase one 1st floor west side CH2 sheet A110 hall, lobby, and office okay with the exception of overspaced fire sprinkler coverage at office 103 due to relocated walls.
BLD-Final7/21/20147/22/20147/22/2014ANR
DetailsJim Storey
Bruce Phone #: ###-####
FIRE-Final Inspection7/21/20147/22/20147/22/2014APART
DetailsForrest France
Regarding completion of work at the basement level.
BLD-Framing/Rough-in7/1/20147/2/20147/2/2014PDONE
DetailsDave Hannah
Bruce Phone #: ###-#### Framing approved for cover @ art annex area on main floor.
BLD-Footing6/20/20146/23/20146/23/2014APASS
DetailsDave Hannah
Bruce (10AM) Phone #: ###-####
BLD-Ceiling Grid Inspection6/19/20146/20/20146/20/2014APASS
DetailsDave Hannah
bruce Phone #: ###-####
BLD-Ceiling Grid Inspection6/18/20146/19/20146/19/2014PFAIL
DetailsDave Hannah
bruce - basement lobby CH2 Phone #: ###-####