Information based on query as of Tuesday, June 25, 2024.
Permit Information
Permit NumberBLD13-03589
StatusFinaled
Name ANDERSEN CONSTRUCTION CO
Site Address 11959 W OVERLAND RD
Project NameCantabria Development
Customer Number 
ePlanReviewNo
Description
(CANTABRIA DEVELOPMENT - BLDG 10) - To construct a new 3,668 sq. ft., two story, Four unit, apartment building. Units 'A' have one bedroom, one den, and two bathrooms. Units 'B' have two bedrooms, and two bathrooms. All 4 dwelling units have their own independent exit. All construction per the approved plans, attached plan review report, and all other reviewing agencies approvals. One hour fire-partition separations are required between dwelling units. This building is required to be fire sprinklered. The fire sprinkler system shall be per NFPA 13R as regulated by the fire department. DRH13-00337 Per Planning and Zoning. See BLD13-03579 for building plan review report. **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection2/29/20162/29/20163/1/2016 PASS
DetailsMike Jordan
DOC - Permit Finaled3/1/20163/1/20163/1/2016PPASS
DetailsMike Jordan
BLD-Aging Inspection12/30/201512/30/201512/30/2015 PASS
DetailsMike Jordan
BLD-Aging Inspection10/19/201510/19/201510/19/2015 PASS
DetailsMike Jordan
BLD-Final7/10/20157/13/20157/13/2015APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Tyler Hildebrand. Ok for temp occ. Will be ok for perm occ. once zoning and public works signs perm.
BLD-Final7/9/20157/10/20157/10/2015AFAIL
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Tyler Hildebrand. Provide the required 1hr enclosure at riser rooms and at party walls underneath stairs.
FIRE-Final Inspection7/1/20157/2/20157/2/2015APASS
DetailsTroy Cobbley
Life safety passed
BLD-Energy code compliance5/11/20155/12/20155/12/2015APASS
DetailsMike Jordan
insulation inspection Phone #: ###-#### Inspection requested via web by Mel Rawlinson
BLD-Framing/Rough-in5/8/20155/11/20155/11/2015APASS
DetailsMike Jordan
rough frame Phone #: ###-#### Inspection requested via web by Mel Rawlinson
BLD-Framing/Rough-in5/7/20155/8/20155/8/2015ANR
DetailsMike Jordan
rough frame Phone #: ###-#### Inspection requested via web by Mel Rawlinson. Needs fire sprinkler ri
BLD-Wall Bracing4/17/20154/20/20154/20/2015APASS
DetailsMike Jordan
BLD-Wall Bracing4/8/20154/9/20154/9/2015APASS
DetailsMike Jordan
2nd // Tyler Phone #: ###-####. Interior shear walls.
BLD-Wall Bracing3/26/20153/26/20153/26/2015PPASS
DetailsMike Jordan
first floor // Tyler Phone #: ###-####
BLD-Energy code compliance3/10/20153/10/20153/10/2015APASS
DetailsMike Jordan
Vicky Phone #: ###-####. rigid insulation on interior side of foundation wall under SOG.
BLD-Foundation3/3/20153/4/20153/4/2015APASS
DetailsJim Sly
wall // manuel Phone #: ###-####
BLD-Footing3/2/20153/2/20153/2/2015PPASS
DetailsPhil Shearer
Manuel Phone #: ###-####. per MTI inspection
BLD-Wall Bracing4/17/20154/17/2015 P 
DetailsMike Jordan
exterior shear Phone #: ###-#### >> Inspection requested via web by Mel Rawlinson