BLD-Final | 12/12/2014 | 12/15/2014 | 12/15/2014 | A | PASS |
Mike Jordan
|
|
|
Brad Turk Phone #: ###-#### Inspection requested via web by Brad Turk. Ok for perm occ.
|
BLD-Conference | 11/25/2014 | 11/25/2014 | 11/25/2014 | P | DONE |
Mike Jordan
|
|
|
Mike, I think we can do this conference over the phone. Please give me a call at your convenience. Thanks Phone #: ###-#### Inspection requested via web by Brad Turk
|
FIRE-Final Inspection | 11/25/2014 | 11/25/2014 | 11/25/2014 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Ceiling Grid Inspection | 11/20/2014 | 11/20/2014 | 11/20/2014 | P | PASS |
Mike Jordan
|
|
|
Brad Turk Grip inspection for Maternity room 124 Phone #: ###-#### Inspection requested via web by Brad Turk
|
BLD-Framing/Rough-in | 10/30/2014 | 10/31/2014 | 10/31/2014 | P | PASS |
Mike Jordan
|
|
|
Final phase framing inspection. Phone #: ###-#### Inspection requested via web by Chris Jackson. existing nurses station addition, window infill and removal of portion interior non load bearing wall.
|
BLD-Ceiling Grid Inspection | 10/8/2014 | 10/9/2014 | 10/9/2014 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Jackson. equipment rm. 126 and med rm 125.
|
BLD-Framing/Rough-in | 9/16/2014 | 9/17/2014 | 9/17/2014 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Peter Kilpatrick ph 2 med rm ok to cover after other trades ok rough ins
|
BLD-Final | 7/28/2014 | 7/29/2014 | 7/29/2014 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Jackson phase 1 ok for occupance. saftey glazzing to be labled in doors between or suits.
|
BLD-Final | 7/28/2014 | 7/28/2014 | 7/28/2014 | P | DEFR |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Jackson
|
FIRE-Final Inspection | 7/24/2014 | 7/25/2014 | 7/25/2014 | A | FAIL |
Troy Cobbley
|
|
|
Life safety in Maternity area will be ok to sign off when the fire alarm is passed in this area.
|
BLD-Ceiling Grid Inspection | 7/21/2014 | 7/21/2014 | 7/21/2014 | P | PASS |
Mike Jordan
|
|
|
Chris Jackson - Andersen Phone #: ###-#### Inspection requested via web by Chris Jackson. Passage 109 completed ok.
|
BLD-Ceiling Grid Inspection | 7/7/2014 | 7/8/2014 | 7/8/2014 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Jackson. rooms 110, 113, 116 ok.
|
BLD-Ceiling Grid Inspection | 6/13/2014 | 6/16/2014 | 6/16/2014 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Jackson. OR #10 ok for hardlid.
|
BLD-Framing/Rough-in | 4/17/2014 | 4/18/2014 | 4/18/2014 | A | PASS |
Tom Arcoraci
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Jackson
|
BLD-Footing | 3/17/2014 | 3/18/2014 | 3/18/2014 | A | PASS |
Tom Arcoraci
|
|
|
Please call 15 min before, new project at St. Als. 10:00 A.M. Pour. Phone #: ###-#### >> Inspection requested via web by Chris Jackson
|