BLD-Aging Inspection | 7/8/2015 | 7/8/2015 | 7/9/2015 | | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 7/9/2015 | 7/9/2015 | 7/9/2015 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 4/9/2015 | 4/9/2015 | 4/9/2015 | P | PASS |
Mike Jordan
|
|
|
Dave Phone #: ###-####
|
BLD-Aging Inspection | 3/30/2015 | 3/30/2015 | 3/30/2015 | | PASS |
Mike Jordan
|
|
|
|
BLD-Aging Inspection | 1/26/2015 | 1/26/2015 | 1/27/2015 | | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 11/6/2014 | 11/6/2014 | 11/6/2014 | P | PART |
Mike Jordan
|
|
|
Tyler Phone #: ###-####. 1hr. const. complete in riser room. ok for temp occ.
|
BLD-Final | 11/5/2014 | 11/6/2014 | 11/6/2014 | A | FAIL |
Mike Jordan
|
|
|
Tyler Phone #: ###-####. Provide the required 1hr. construction in the fire riser rm.
|
FIRE-Final Inspection | 11/4/2014 | 11/5/2014 | 11/5/2014 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Building address to be mounted prior to the final inspection
|
BLD-Energy code compliance | 9/9/2014 | 9/10/2014 | 9/10/2014 | P | PASS |
Mike Jordan
|
|
|
Richard Phone #: ###-####
|
BLD-Framing/Rough-in | 9/9/2014 | 9/9/2014 | 9/9/2014 | P | PASS |
Mike Jordan
|
|
|
Richard Phone #: ###-####
|
BLD-Wall Bracing | 8/15/2014 | 8/15/2014 | 8/15/2014 | P | PASS |
Mike Jordan
|
|
|
Richard Phone #: ###-####. floor to floor straps ok.
|
BLD-Wall Bracing | 8/14/2014 | 8/14/2014 | 8/14/2014 | P | NR |
Mike Jordan
|
|
|
Richard Phone #: ###-####
|
BLD-Wall Bracing | 8/11/2014 | 8/12/2014 | 8/12/2014 | A | PASS |
Mike Jordan
|
|
|
Richard Phone #: ###-####. Roof strapping ok.
|
BLD-Wall Bracing | 7/31/2014 | 7/31/2014 | 7/31/2014 | P | PASS |
Phil Shearer
|
|
|
Richard Phone #: ###-#### All exterior shear walls ok
|
BLD-Wall Bracing | 7/30/2014 | 7/30/2014 | 7/30/2014 | P | PASS |
Phil Shearer
|
|
|
Richard Phone #: ###-#### 2nd floor exterior shear walls ok
|
BLD-Wall Bracing | 7/21/2014 | 7/21/2014 | 7/21/2014 | P | NR |
Mike Jordan
|
|
|
Ken Phone #: ###-####
|
BLD-Wall Bracing | 7/18/2014 | 7/18/2014 | 7/18/2014 | P | PASS |
Mike Jordan
|
|
|
Ken Phone #: ###-####. 1st floor exterior shear walls and interior shear walls only ok.
|
BLD-Energy code compliance | 6/27/2014 | 7/1/2014 | 7/1/2014 | A | PASS |
Mike Jordan
|
|
|
Ashley Phone #: ###-####. rigid insulation, interior side of stemwaal under slab on grade.
|
BLD-Foundation | 6/25/2014 | 6/26/2014 | 6/26/2014 | P | PASS |
Mike Jordan
|
|
|
Manual Phone #: ###-####
|
BLD-Footing | 6/25/2014 | 6/25/2014 | 6/25/2014 | P | PASS |
Mike Jordan
|
|
|
|