BLD-Conference | 2/27/2014 | 2/27/2014 | 2/27/2014 | P | DONE |
Mike Jordan
|
|
|
john - call 30 mins prior Phone #: ###-####. Correct all life/safety items from life/safety inspection, provide lever hardware at warehouse exit, repair damaged grid ceiling. Also needs to provide evidence that apermit was pulled for the mezzanine that was constructed. Current building classification is type IIB construction. The constructed mezzanine does not meet this criteria. Also noted racking over 8ft. tall that has been installed as well.
|
FIRE-Final Inspection | 2/26/2014 | 2/27/2014 | 2/27/2014 | A | FAIL |
Troy Cobbley
|
|
|
Repair the fire alarm system/provide verification that the system is monitored, install all ceiling tile, remove dead bolt at office, remove exit sign by fire sprinkler riser, provide fire extinguisher with current tag on the mezzanine, provide/repair all exit signs/emergency lights (see approved plans), provide racking permit or contact scott arellano with removal timeline.
|
BLD-Final | 2/26/2014 | 2/27/2014 | 2/27/2014 | A | CANC |
Mike Jordan
|
|
|
John Phone #: ###-####
|