Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberBLD14-00272
StatusFinaled
Name ESI
Site Address 800 W MAIN ST Unit: 940
Project NameBabcock Design Group Suite 940
Customer Number 
ePlanReviewYes
Description
(BABCOCK DESIGN GROUP)(SUITE 940)The fire sprinkler system is used for high-rise. This project is a tenant improvement for Babcock Design Group on the 9th floor of the 8th and main building. The project will consist of open office space, conference room, library, and work room. Mechanical, electrical, and plumbing will be part of the tenant improvement to build out the suite. Scope of work includes nonbearing noncombustible partition walls, heavy duty suspended ceiling grid. There are 2 walls that are being constructed under this project in the hallway that limit access around the core of the building. These walls will need to be reevaluated when future tenant spaces are submitted. All high-rise fire and life safety systems must also be installed and operational before occupancy. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department.**ajs**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/12/20146/13/20146/13/2014PPASS
DetailsDave Hannah
Final BLD inspection for Babcock T.I. . Call Adam for any access needs ###-####. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
BLD-Ceiling Grid Inspection6/12/20146/13/20146/13/2014APASS
DetailsDave Hannah
Final Ceiling sign off request for Babcock, exit corridor. Call Adam for any access needs ###-####. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
FIRE-Final Inspection6/12/20146/13/20146/13/2014PPASS
DetailsTroy Cobbley
Life safety passed
BLD-Ceiling Grid Inspection6/6/20146/9/20146/9/2014APEND
DetailsDave Hannah
Ceiling cover inspection for access cooridor outside babcock t.i. space. Please let me know if you have any questions, or need assistance for access. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok to layin bourders
BLD-Ceiling Grid Inspection5/30/20146/2/20146/2/2014APASS
DetailsDave Hannah
Bob Ledford Phone #: ###-####
BLD-Framing/Rough-in4/1/20144/1/20144/2/2014PPASS
DetailsDave Hannah
Follow up to yesterdays walk with FCS and Dave Hannah. This request for formal sign off for framing cover on this TI. Thanks AKJ. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in3/31/20143/31/20143/31/2014PPASS
DetailsDave Hannah
Jeff Russell Phone #: ###-####