Description
(JUNIPER) Permit for renovations of and existing restaurant. Scope of work shall include new finishes, kitchen equipment & Furnishings. Existing restrooms to remain, new finishes. ADA Upgrades to include: vertical grab bars installed in all restrooms; new guardrail installed on second floor; new lever handles, where none existed before. The floor loading is 50# per square foot as noted in plan review BLD96-01799 resulting in the reduced occupant load. Reduced floor loading shall be posted. Demolition per approved plans. There is an existing 1 hour corridor exiting the back of the 2nd floor. The second floor does not qualify as a mezzanine and shall meet all 2nd floor requirements. New roof top units to be installed, new walk in cooler, new lighting, new duct work, plumbing in kitchen also to be installed. There are 5 existing window openings that will be resotred as part of this project. The exterior side has been infilled with brick. The openings will be unprotected and fall within the 10% unprotected openings appowed per current code. This building is NOT fire sprinklered. **ajs**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/19/20146/20/20146/20/2014APASS
DetailsDave Hannah
Darren Phone #: ###-#### as per city aproved plans note handrails on ext stairs are not to todays codes and not on plans to be changed.
FIRE-Final Inspection6/13/20146/16/20146/16/2014APASS
DetailsForrest France
Fire life safety inspection completed satisfactory.
FIRE-Conference6/10/20146/10/20146/10/2014PDONE
DetailsForrest France
Regarding fire life safety items and project schedule.
FIRE-Conference5/6/20145/8/20145/8/2014ADONE
DetailsForrest France
On site conference regarding hood suppression permit work and equipment layout.
BLD-Framing/Rough-in5/6/20145/7/20145/7/2014APASS
DetailsDave Hannah
darren Phone #: ###-####
FIRE-Conference5/1/20145/2/20145/2/2014ADONE
DetailsForrest France
On site conference with contractor regarding hood suppression system, EM lighting, exit signs, rated stairway, door hardware, fire life safety conditions and project schedule.
BLD-Framing/Rough-in5/1/20145/2/20145/2/2014APASS
DetailsDave Hannah
darren Phone #: ###-####
BLD-Conference4/30/20145/1/20145/1/2014ADONE
DetailsMike Jordan
darrin Phone #: ###-####. Spoke to contractor about concerns for a draft stop in ceiling. One is already present, but concealed area is less than 3000 s.f.