BLD-Final | 6/25/2015 | 6/25/2015 | 6/25/2015 | P | PASS |
Jim Storey
|
|
|
MIke Phone #: ###-####
|
BLD-Final | 6/22/2015 | 6/24/2015 | 6/24/2015 | A | FAIL |
Jim Storey
|
|
|
Mike Phone #: ###-#### need handrail
|
BLD-Final | 4/30/2015 | 5/1/2015 | 5/1/2015 | P | PART |
Jim Storey
|
|
|
Mike Phone #: ###-#### temp occ ok no storage or occ. of mez. no card on site
|
FIRE-Final Inspection | 4/30/2015 | 5/1/2015 | 5/1/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 4/29/2015 | 4/30/2015 | 4/30/2015 | A | FAIL |
Troy Cobbley
|
|
|
All life safety items are ok except the project related fire alarm and fire sprinkler permits need addressed
|
BLD-Final | 4/29/2015 | 4/30/2015 | 4/30/2015 | P | CANC |
Jim Storey
|
|
|
Cancel per Mike Phone #: ###-####
|
BLD-Final | 4/28/2015 | 4/28/2015 | 4/28/2015 | P | NR |
Jim Storey
|
|
|
Mike Phone #: ###-####
|
BLD-Final | 4/23/2015 | 4/24/2015 | 4/24/2015 | P | CANC |
Jim Storey
|
|
|
Mike Phone #: ###-####
|
FIRE-Final Inspection | 4/23/2015 | 4/24/2015 | 4/24/2015 | A | FAIL |
Troy Cobbley
|
|
|
Not ready for a final due to the project related fire alarm and fire sprinkler permits. Mike and I did discuss life safety items. I noted that the two electric gates may require Opticon opening devices. Per Idaho Power a access card will be provided in the Knox Box for access. I will need Boise Fire approval for this prior to final sign off.
|
BLD-Framing/Rough-in | 1/23/2015 | 1/26/2015 | 1/26/2015 | P | PASS |
Jim Storey
|
|
|
Mike Phone #: ###-####
|
BLD-Foundation | 1/14/2015 | 1/14/2015 | 1/14/2015 | P | PASS |
Jim Storey
|
|
|
Mike-rebar Phone #: ###-#### top out cmu ok
|
BLD-Foundation | 12/9/2014 | 12/9/2014 | 12/9/2014 | P | PASS |
Jim Storey
|
|
|
Mike-rebar Phone #: ###-####2nd lift ok
|
BLD-Foundation | 12/5/2014 | 12/8/2014 | 12/8/2014 | A | PART |
Jim Storey
|
|
|
rebar// Jermey Phone #: ###-#### wip ok
|
BLD-Foundation | 11/4/2014 | 11/5/2014 | 11/5/2014 | P | PASS |
Jim Storey
|
|
|
slab insp// Jeremy Phone #: ###-####
|
BLD-Footing | 8/20/2014 | 8/21/2014 | 8/21/2014 | P | PART |
Jim Storey
|
|
|
please call first-Jeremy Phone #: ###-#### all pads ok pending south wall line bar clearance to be inspected by si prior to placment.
|
BLD-Foundation | 8/13/2014 | 8/14/2014 | 8/14/2014 | A | PASS |
Jim Storey
|
|
|
Jeremy Phone #: ###-####
|
BLD-Footing | 8/11/2014 | 8/12/2014 | 8/12/2014 | A | PASS |
Jim Storey
|
|
|
Jeremy Phone #: ###-#### need compacktion report for fill.
|
BLD-Footing | 8/11/2014 | 8/11/2014 | 8/11/2014 | P | CANC |
Jim Storey
|
|
|
Jeremy Phone #: ###-#### - canceled
|