BLD-Other | 12/8/2014 | 12/8/2014 | 12/8/2014 | P | CANC |
Phil Shearer
|
|
|
Erosion Control Program Final inspection. Building and site work are complete. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Final | 12/5/2014 | 12/8/2014 | 12/8/2014 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
FIRE-Final Inspection | 12/4/2014 | 12/5/2014 | 12/5/2014 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory. Two non-functional exit signs to be repaired and one EM light to be added per discussion prior to structural final.
|
BLD-Final | 12/2/2014 | 12/4/2014 | 12/4/2014 | A | CANC |
Phil Shearer
|
|
|
Structural and final. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Final | 11/20/2014 | 11/20/2014 | 11/20/2014 | P | NR |
Jim Sly
|
|
|
Completion Inspection on remodeled rooms #123,126,128,114,115,116,117,118,101,119,129,133,134,135,136 ; 137 Ceiling Grid inspection in Room #120, 121, 122 Phone #: ###-#### Inspection requested via web by Markus Schlegel
Contractor wants to allow church members to use Kitchen, some class rooms and restooms completed prior to final inspection. Advised to have conference with Fire Inspector.
|
BLD-Framing/Rough-in | 10/7/2014 | 10/8/2014 | 10/8/2014 | P | PASS |
Phil Shearer
|
|
|
South Storage room addition, would prefer later in the day around 2pm. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Framing/Rough-in | 10/6/2014 | 10/6/2014 | 10/6/2014 | P | PART |
Phil Shearer
|
|
|
North addition steel stud framing and south addition wood framing. Early afternoon preferred. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Framing/Rough-in | 9/29/2014 | 9/30/2014 | 9/30/2014 | A | PASS |
Phil Shearer
|
|
|
Truss and roof framing and sheeting on north addition multi use rooms Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Other | 9/23/2014 | 9/23/2014 | 9/23/2014 | P | PART |
Phil Shearer
|
|
|
ESC Site Inspection ESC#14-00175 Last performed by Andy Long 7/15/14. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Other | 9/18/2014 | 9/19/2014 | 9/19/2014 | P | PASS |
Phil Shearer
|
|
|
CMU Rebar and grouting inspection. Grouting to take place at 2pm. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Other | 9/12/2014 | 9/15/2014 | 9/15/2014 | A | PASS |
Phil Shearer
|
|
|
Rebar and Grout inspection, north CMU walls. Grout time is 8am. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Other | 9/10/2014 | 9/12/2014 | 9/12/2014 | A | PASS |
Phil Shearer
|
|
|
CMU Rebar and Grout inspection. Grout at 8am. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Other | 9/8/2014 | 9/10/2014 | 9/10/2014 | A | **** |
Phil Shearer
|
|
|
*****pour time 10:00AM*****Masonry rebar & grout inspection second course, grouting will take on will call and TBD for AM grouting. Phone #: ###-#### >> Inspection requested via web by Markus Schlegel
|
BLD-Framing/Rough-in | 9/9/2014 | 9/9/2014 | 9/9/2014 | P | PASS |
Phil Shearer
|
|
|
ADA restrooms
|
BLD-Framing/Rough-in | 9/9/2014 | 9/9/2014 | 9/9/2014 | A | NR |
Phil Shearer
|
|
|
Framing inspection in the mechanical/pantry room can be do the same time as grout and rebar for masonry at 11am. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Other | 9/8/2014 | 9/9/2014 | 9/9/2014 | A | PASS |
Phil Shearer
|
|
|
Masonry rebar ; grout inspection second course, grouting will take place at 11am. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Conference | 9/5/2014 | 9/8/2014 | 9/8/2014 | A | PASS |
Phil Shearer
|
|
|
inspection will include 1st course of masonry and rebar on the north and south addition prior to grouting. Grouting is scheduled for 7am pending inspection. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Foundation | 8/19/2014 | 8/20/2014 | 8/20/2014 | P | PASS |
Phil Shearer
|
|
|
rebar and stem wall inspection Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Foundation | 8/19/2014 | 8/19/2014 | 8/19/2014 | P | PASS |
Phil Shearer
|
|
|
Footing and rebar inspection on north and south foundation additions. Phone #: ###-#### Inspection requested via web by Markus Schlegel Footings
|
BLD-Conference | 7/15/2014 | 7/16/2014 | 7/16/2014 | P | PASS |
Jim Storey
|
|
|
Marcus-would like a call with an approx meet time Phone #: ###-####
|