Permit Information
Permit NumberBLD14-00681
StatusFinaled
Name MCALVAIN CONSTRUCTION INC
Site Address 1570 S LUSK PL
Project NameLusk Place Apartments
Customer Number 
ePlanReviewYes
Description
VISTA WEST (formerly known as Lusk Apartments) - This permit if for the tenant finish of the approximate 85,500 sq. ft. first floor parking garage and office areas and to construct a three story apartment building above a three-hour fire-resistive concrete structural podium. The first story garage is constructed of concrete and is Type 1A construction. The apartment building is constructed of wood frame one-hour fire-resistive construction. The apartment building is being divided by a two-hour fire-resistive fire wall, area one is approximately 58,500 sq. ft. and area two is approximately 103,435 sq. ft.. The second floor has approximately 5,385 square feet of community activity areas and an approximate 2,275 sq. ft. outdoor patio area. The fire wall also functions as a horizontal exit to satisfy travel distance requirements. This building is fully fire sprinklered with an NFPA 13 sprinkler system. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/4/201512/7/201512/7/2015APASS
DetailsJim Storey
would like call ahead; Abel Phone #: ###-#### f offinal ok pending fire sign
BLD-Aging Inspection10/28/201510/28/201510/28/2015 DEFR
DetailsJim Storey
pending fire c/n///Test of the area of refuge emergency communication system. Floors 1 thru 3 tested satisfactorily, however floor # 4 did not call out. Contractor agreed to trouble shoot problem and will schedule a final inspection when corrected
FIRE-Final Inspection10/3/201512/7/201510/3/2015APASS
DetailsThomas Walsh
I went by Lusk St. Apts and we tested the one remaining area of refuge comm. system panel (4th floor) that did not work last visit , and that worked – so this system is completed for this building. Tom Walsh
FIRE-Final Inspection8/28/20158/28/20158/28/2015PFAIL
DetailsThomas Walsh
Test of the area of refuge emergency communication system. Floors 1 thru 3 tested satisfactorily, however floor # 4 did not call out. Contractor agreed to trouble shoot problem and will schedule a final inspection when corrected.
FIRE-Final Inspection8/10/20158/10/20158/10/2015PDONE
DetailsThomas Walsh
Reinspection to confirm two (2) added no parking signs for fire access road. Also completed inspection of fire sprinkler punchlist items. ROCs docs to be completed when ready.
FIRE-Final Inspection8/7/20158/7/20158/7/2015PPASS
DetailsThomas Walsh
Final FireLife-Safety inspection. Fire sprinklers and fire alarm systems signed off. Exit signage and EM lighting completed. EVAC signs posted in elevator lobbies. Fire access road completed on south side of building. Need to add two (2) addtional "No Parking" signs for cul-de-sac that leads into the fire access road. Fire extinguishers located throughout.
NOTE: Per BO email, elevator lobbies not longer required per latest ICC interp.
Signed off Bldg. Permit inspection card for full occupancy.
BLD-Final8/7/20158/7/20158/7/2015PPART
DetailsJim Storey
temp occ. ok c/n on site for perm
BLD-Final8/6/20158/6/20158/6/2015PNR
DetailsJim Storey
Jose Phone #: ###-####
FIRE-Final Inspection8/6/20158/6/20158/6/2015PPART
DetailsThomas Walsh
Fire life satey inspection to test new exit signs installed on floors 2-4 to improve egress signage. Also looked at EM lights that were repositioned to improve lighting along the pathway.
Fire lane and signage for the fire access road on the south side not completed yet.
Also had two (2) portable BBQ units removed from the clubhouse patios, as these are not permitted for R2 buildings of Type V constuction.
FIRE-Final Inspection8/5/20158/5/20158/5/2015PPART
DetailsThomas Walsh
Final fire life-safety inspection for apartment building. Tested some new exit signs added to clarify egress paths in some areas. Also retested some emerg. lights that were not working last visit. Tested last dry pipe fire sprinkler system, that failed last test. All fire sprinklers are fully tested, however some systems are still shutdown as some painted heads have to be changed out. The fire alarm system has been fully tested however, it is not being monitored off-site because of the fire sprinkler work being done.
I have approved TCO for staff only personel to work in the leasing office only. I have not approved TCO for any use of the building for public use, access for residents, or for any overnight stays.
BLD-Final8/4/20158/4/20158/4/2015PPART
DetailsJim Storey
Jose Phone #: ###-#### stair enclosers ok/ pending sign offs
BLD-Final7/30/20157/30/20157/30/2015PFAIL
DetailsJim Storey
Jose Phone #: ###-#### stair b hardware to outside smoke seal both doors leval 1//stair a 4th and 2 not latching level 1 smoke seal screwed closed and need hardware//stair c 1 level smoke seals/ 4th floor no latch// stair d smoke seal screwed shut no hardware. clean all exit sys.elvator machine rm snoke seal and fire chalk top of wall and holes.
BLD-Ceiling Grid Inspection7/28/20157/29/20157/29/2015APASS
DetailsJim Storey
Jose Phone #: ###-####
BLD-Ceiling Grid Inspection7/20/20157/21/20157/21/2015APASS
DetailsJim Storey
Jose Phone #: ###-####
BLD-Ceiling Grid Inspection7/20/20157/20/20157/20/2015PPASS
DetailsJim Storey
Jose Phone #: ###-#### level 4 1&2
BLD-Ceiling Grid Inspection7/8/20157/8/20157/8/2015PCANC
DetailsJim Storey
Jose Phone #: ###-#### lev 2/3 sec 2/3
BLD-Ceiling Grid Inspection6/22/20156/23/20156/23/2015PPASS
DetailsJim Storey
Jose Phone #: ###-#### as noted in office sign off
BLD-Other6/8/20156/8/20156/8/2015PPART
DetailsJim Storey
sofits; Jose Phone #: ###-#### ceilling ok pool house area.
BLD-Ceiling Grid Inspection6/5/20156/5/20156/5/2015APASS
DetailsJim Storey
Level 2, Section 1 - Jose Phone #: ###-#### and first floor insulation and grid ok
BLD-Ceiling Grid Inspection6/4/20156/4/20156/5/2015PDEFR
DetailsDave Hannah
Level 2, Section 1 - Jose Phone #: ###-#### out of time reschduled this for jim 6/5
BLD-Framing/Rough-in5/20/20155/21/20155/21/2015PNR
DetailsJim Storey
Soffit framing, level 4 section 3 - Jose Phone #: ###-####
BLD-Framing/Rough-in5/20/20155/21/20155/21/2015APASS
DetailsJim Storey
Soffit framing, level 4 section 2 - Jose Phone #: ###-####
BLD-Framing/Rough-in5/15/20155/15/20155/15/2015PPASS
DetailsJim Storey
Jose-level 4 section 1 Phone #: ###-#### soffits ok
BLD-Energy code compliance5/12/20155/12/20155/12/2015PPASS
DetailsJim Storey
Jose Phone #: ###-####club house ok insulation ok to cover.
BLD-Framing/Rough-in5/7/20155/8/20155/8/2015APASS
DetailsJim Storey
soffits/ 3 an4 2hr corridor wall penatrations ok Jose// level 3-section 3 Phone #: ###-####
BLD-Framing/Rough-in5/5/20155/5/20155/5/2015PPASS
DetailsJim Storey
Jose-section 3 level 2-sofit framing Phone #: ###-#### club house exterior framing ok paretpet.
BLD-Energy code compliance4/30/20155/1/20155/1/2015APASS
DetailsJim Storey
Insulation // Jose Phone #: ###-#### sec 2 /3 level 4
BLD-Energy code compliance4/27/20154/28/20154/28/2015APASS
DetailsJim Storey
Jose-level 4 area 1 Phone #: ###-####
BLD-Framing/Rough-in4/23/20154/24/20154/24/2015PPASS
DetailsJim Storey
Jose-soffits-section 2 level 3 Phone #: ###-####and shafts
BLD-Energy code compliance4/22/20154/22/20154/22/2015PPASS
DetailsJim Storey
Area 3, level 3 - Jose Phone #: ###-####
BLD-Framing/Rough-in4/16/20154/17/20154/17/2015APASS
DetailsJim Storey
John-level 2 area 2 Phone #: ###-#### drops ok to cover
BLD-Energy code compliance4/13/20154/14/20154/14/2015PPASS
DetailsJim Storey
Insulations // Jose Phone #: ###-####sec3 2 floor fire chalk ok/ 3fl insulation ok
BLD-Energy code compliance4/13/20154/13/20154/13/2015PPASS
DetailsJim Storey
Insulation // Jose Phone #: ###-#### sec 123 floor 4 exterior walls
BLD-Framing/Rough-in4/13/20154/13/20154/13/2015PPASS
DetailsJim Storey
Insulation // Jose Phone #: ###-#### sec 123 floor 4 pass
BLD-Energy code compliance4/8/20154/9/20154/9/2015APASS
DetailsJim Storey
Jose Phone #: ###-#### drops 1sec3rdfloor
BLD-Framing/Rough-in4/7/20154/7/20154/7/2015PPASS
DetailsJim Storey
- Jose Phone #: ###-#### elavator lobby/ libary rm/ stair enclosers ok to cover
BLD-Energy code compliance4/6/20154/7/20154/7/2015APASS
DetailsJim Storey
Jose Phone #: ###-#### 3 sec 2nd floor
BLD-Framing/Rough-in4/1/20154/2/20154/2/2015APASS
DetailsJim Storey
Jose Phone #: ###-####exterior walls sec3/2 &3 floors/ shaft ok to cover trash shoot.
BLD-Framing/Rough-in3/23/20153/24/20153/24/2015ANR
DetailsJim Storey
lvl 2 area 1 soffit framing- Jose Phone #: ###-####
BLD-Energy code compliance3/19/20153/20/20153/23/2015PPASS
DetailsJim Storey
Jose Phone #: ###-####sec2 fl2
BLD-Framing/Rough-in3/16/20153/16/20153/16/2015PPASS
DetailsJim Storey
Jose Phone #: ###-#### 2nd sec 1 and 2 frame ok
BLD-Framing/Rough-in3/12/20153/12/20153/13/2015PPASS
DetailsJim Storey
Jose Phone #: ###-####1st floor office area ok to cover
BLD-Energy code compliance3/4/20153/5/20153/5/2015PPASS
DetailsJim Storey
insulation // Jose Phone #: ###-####sec 1 floor 3 ok to cover
BLD-Framing/Rough-in3/2/20153/3/20153/3/2015APART
DetailsJim Storey
Jose Phone #: ###-#### clubhouse roof deck ok will check blk. on perimitor from under deck.
BLD-Framing/Rough-in2/26/20152/27/20152/27/2015APASS
DetailsJim Storey
Jose-section 1 level 3 Phone #: ###-####
BLD-Framing/Rough-in2/24/20152/25/20152/25/2015APASS
DetailsJim Storey
Jose-level 3 section 2 Phone #: ###-#### exterior airseal ok/ 1st floor b occ framing ok.
BLD-Framing/Rough-in2/23/20152/23/20152/23/2015PPASS
DetailsJim Storey
Jose Phone #: ###-#### elavator ok to cover
BLD-Energy code compliance2/23/20152/23/20152/23/2015PPASS
DetailsJim Storey
Jose Phone #: ###-####exterior air sealsec2 all/238 237 240 239
BLD-Energy code compliance2/19/20152/20/20152/20/2015PPASS
DetailsJim Storey
Section 1 Level 2 // Jose Phone #: ###-####
BLD-Framing/Rough-in2/17/20152/18/20152/18/2015APART
DetailsJim Storey
Jose-Section 1 2nd floor Phone #: ###-#### c/n posted/riser in coridor gyp ok
BLD-Framing/Rough-in2/17/20152/17/20152/17/2015PDEFR
DetailsJim Storey
Jose-Section 1 2nd floor Phone #: ###-#### out of time defr. ot am
BLD-Framing/Rough-in2/10/20152/11/20152/11/2015APASS
DetailsJim Storey
Jose Phone #: ###-#### 4th floor sec 1 exterior walls ok to insulate
BLD-Wall Bracing2/3/20152/3/20152/3/2015PPART
DetailsJim Sly
Jose-roofing & exterior walls Phone #: ###-####
Roof deck nailing and fire resistive ply at 2 hr walls......Sect 3......level 3 OK. Anchor bolts/ hold down bolts, nuts and washers at exterior walls of Sect.3..... level 2 and 3 OK........ except for 6 nuts not tightened on anchor bolts ......room 236 ext wall level 2.......OK to insulate. (Electr OKd). Steel stud framing OK level 1 (Garage)........OK to cover Ext.
BLD-Other1/21/20151/21/20151/21/2015PPASS
DetailsJim Storey
roof decking// Jose Phone #: ###-#### sec 2 ok// corridors 234 sec ok to prerock.
BLD-Wall Bracing1/9/20151/12/20151/12/2015PPASS
DetailsJim Storey
Jose-sheathing for the roof Phone #: ###-#### phase 1