BLD-Final | 1/15/2015 | 1/15/2015 | 1/15/2015 | P | PASS |
Mike Jordan
|
|
|
Chris Phone #: ###-####. Ok for perm occ.
|
BLD-Final | 1/14/2015 | 1/14/2015 | 1/14/2015 | P | NR |
Mike Jordan
|
|
|
Chris Phone #: ###-####. Will reschedule and provide approved plans.
|
BLD-Final | 8/6/2014 | 8/7/2014 | 8/7/2014 | P | PART |
Mike Jordan
|
|
|
Chris Phone #: ###-####. ok for temp occ.
|
FIRE-Final Inspection | 8/6/2014 | 8/7/2014 | 8/7/2014 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Wood above the ceiling has been changed to fire treated. Building contractor to provide panic hardware on door 111 prior to a building sign off
|
FIRE-Conference | 8/6/2014 | 8/6/2014 | 8/6/2014 | P | DONE |
Forrest France
|
|
|
On site conference with contractor regarding fire life safety conditions and inspection items necessary for final. Noted door hardware issues, one exit sign to be repaired, noted curtain partitions are not yet installed and may create obstructions to fire alarm and sprinkler coverage.
|
BLD-Framing/Rough-in | 8/4/2014 | 8/5/2014 | 8/5/2014 | A | CANC |
Mike Jordan
|
|
|
Chric Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 8/4/2014 | 8/5/2014 | 8/5/2014 | A | PASS |
Mike Jordan
|
|
|
Chric Phone #: ###-####
|
BLD-Framing/Rough-in | 6/24/2014 | 6/25/2014 | 6/25/2014 | P | PASS |
Mike Jordan
|
|
|
Michael Phone #: ###-####. iNterior steel stud framed walls only, no grid.
|