BLD-Final | 12/29/2015 | 12/30/2015 | 12/30/2015 | A | DONE |
Tony Young
|
|
|
Call for access // Josh Phone #: ###-####
|
BLD-Final | 12/28/2015 | 12/29/2015 | 12/29/2015 | A | PASS |
Tony Young
|
|
|
Call for access // Josh Phone #: ###-####
|
DOC - Permit Finaled | 12/29/2015 | 12/29/2015 | 12/29/2015 | P | PASS |
Tony Young
|
|
|
bond in place,,
|
BLD-Final | 12/23/2015 | 12/24/2015 | 12/24/2015 | A | NR |
Tony Young
|
|
|
Josh Phone #: ###-####,, walk through only,, need hill side,, steps out 2 doors
|
BLD-Framing/Rough-in | 10/6/2015 | 10/7/2015 | 10/7/2015 | A | PART |
Dave Hannah
|
|
|
Josh Phone #: ###-#### ok to cover bathroom addn area in basement nrw change
|
BLD-Conference | 8/4/2015 | 8/5/2015 | 8/5/2015 | A | PEND |
Tony Young
|
|
|
under floor venting will be required
|
BLD-Energy code compliance | 8/4/2015 | 8/4/2015 | 8/4/2015 | P | PASS |
Tony Young
|
|
|
Jason Phone #: ###-####
|
BLD-Energy code compliance | 8/3/2015 | 8/3/2015 | 8/3/2015 | P | NR |
Tony Young
|
|
|
Insulation // Josh Phone #: ###-####
|
BLD-Framing/Rough-in | 8/3/2015 | 8/3/2015 | 8/3/2015 | P | PASS |
Tony Young
|
|
|
Josh Phone #: ###-####
|
BLD-Framing/Rough-in | 7/14/2015 | 7/15/2015 | 7/15/2015 | A | NR |
Tony Young
|
|
|
Josh Phone #: ###-####,, still waiting on fixing correction notice
|
BLD-Framing/Rough-in | 7/13/2015 | 7/14/2015 | 7/14/2015 | A | NR |
Tony Young
|
|
|
Josh Phone #: ###-####
|
BLD-Framing/Rough-in | 7/13/2015 | 7/13/2015 | 7/13/2015 | P | FAIL |
Tony Young
|
|
|
Josh Phone #: ###-####,, correction notice posted
|
BLD-Conference | 7/10/2015 | 7/10/2015 | 7/11/2015 | P | CANC |
Tony Young
|
|
|
frame walk through
|
BLD-Framing/Rough-in | 7/9/2015 | 7/10/2015 | 7/10/2015 | A | NR |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 7/9/2015 | 7/9/2015 | 7/9/2015 | P | NR |
Tony Young
|
|
|
need trades,, seal package
|
BLD-Wall Bracing | 6/17/2015 | 6/17/2015 | 6/17/2015 | P | PASS |
Tony Young
|
|
|
Shear // Josh Phone #: ###-####,, exterior ok
|
BLD-Footing | 4/24/2015 | 4/27/2015 | 4/27/2015 | A | PART |
Tony Young
|
|
|
ok to pour interior pony wall footings and west piers over helicals,, work in progress
|
BLD-Footing | 4/24/2015 | 4/24/2015 | 4/24/2015 | P | NR |
Tony Young
|
|
|
Phone #: ###-####
|
BLD-Foundation | 4/14/2015 | 4/14/2015 | 4/14/2015 | P | PASS |
Phil Shearer
|
|
|
Adam Phone #: ###-####
|
BLD-Footing | 4/10/2015 | 4/10/2015 | 4/10/2015 | P | PASS |
Jim Sly
|
|
|
Going to pour between 1230 and 1 // Adam Phone #: ###-####
|
BLD-Foundation | 3/20/2015 | 3/23/2015 | 3/23/2015 | A | PART |
Tony Young
|
|
|
Adam Phone #: ###-####,, basement walls ok
|
BLD-Wall Bracing | 3/20/2015 | 3/20/2015 | 3/20/2015 | P | PART |
Tony Young
|
|
|
Adam Phone #: ###-####,, wanted a basement wall inspection,, work in progress,, ok
|
BLD-Footing | 3/10/2015 | 3/10/2015 | 3/10/2015 | P | PART |
Tony Young
|
|
|
Adam-pour time 2:30 Phone #: ###-####,, work in progress,,, helical piers in place within footing
|
BLD-Footing | 3/9/2015 | 3/9/2015 | 3/10/2015 | P | DEFR |
Tony Young
|
|
|
Adam-pour time 2:30 Phone #: ###-####
|