BLD-Final | 6/24/2015 | 6/24/2015 | 6/24/2015 | P | PASS |
Tony Young
|
|
|
Please call ###-####. Thanks Dylan Phone #: ###-#### Inspection requested via web by Dylan Schneider
|
DOC - Permit Finaled | 6/24/2015 | 6/24/2015 | 6/24/2015 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 6/11/2015 | 6/12/2015 | 6/12/2015 | A | PART |
Tony Young
|
|
|
Please call before inspection. ThankS, Dylan ###-#### Phone #: ###-#### Inspection requested via web by Dylan Schneider,, vents
|
BLD-Wall cover | 12/15/2014 | 12/18/2014 | 12/18/2014 | A | PASS |
Jim Sly
|
|
|
Please call when heading to job. Thank You! Dylan Schneider Phone #: ###-#### Inspection requested via web by Dylan Schneider
|
BLD-Wall cover | 12/12/2014 | 12/15/2014 | 12/15/2014 | P | NR |
Tony Young
|
|
|
Please call when heading to job. Thank You! Dylan Schneider Phone #: ###-#### Inspection requested via web by Dylan Schneider,, waiting on sprinkler company
|
BLD-Wall cover | 12/11/2014 | 12/12/2014 | 12/12/2014 | A | NR |
Tony Young
|
|
|
Please call when heading to job. Thank You! Dylan Schneider Phone #: ###-#### Inspection requested via web by Dylan Schneider,, still waiting on sprinkler company to complete the job and call for reinspection
|
BLD-Wall cover | 12/10/2014 | 12/11/2014 | 12/11/2014 | A | PART |
Tony Young
|
|
|
Please call when heading to job. Thank You! Dylan Schneider Phone #: ###-#### Inspection requested via web by Dylan Schneider,, ok to cover hallway area where fix has been done,, still need sprinkler full pass
|
BLD-Energy code compliance | 12/8/2014 | 12/10/2014 | 12/10/2014 | A | PEND |
Tony Young
|
|
|
Please call when heading to job. Thank You! Dylan Schneider Phone #: ###-#### Inspection requested via web by Dylan Schneider,, energy ok,,, just need sprinkler company to fix/complete and to get approval to cover all areas
|
BLD-Energy code compliance | 12/5/2014 | 12/8/2014 | 12/8/2014 | A | PART |
Tony Young
|
|
|
Please call when heading to job. Thank You! Dylan Schneider Phone #: ###-#### Inspection requested via web by Dylan Schneider/// ok only in areas allowed by sprinkler pass
|
BLD-Energy code compliance | 12/4/2014 | 12/5/2014 | 12/5/2014 | A | PART |
Tony Young
|
|
|
Please call when heading to job. Thank You! Dylan Schneider Phone #: ###-#### Inspection requested via web by Dylan Schneider,, interior walls ok to cover and exterior that have sprinkler approval
|
BLD-Framing/Rough-in | 12/4/2014 | 12/5/2014 | 12/5/2014 | A | PASS |
Tony Young
|
|
|
Please call when heading to job. Thank You! Dylan Schneider Phone #: ###-#### Inspection requested via web by Dylan Schneider
|
BLD-Framing/Rough-in | 12/4/2014 | 12/4/2014 | 12/4/2014 | P | PART |
Tony Young
|
|
|
Please call when heading to job. Thank You! Dylan Schneider Phone #: ###-#### Inspection requested via web by Dylan Schneider,, need fire sprinklers,, ok to insulate
|
BLD-Conference | 12/3/2014 | 12/4/2014 | 12/4/2014 | A | PEND |
Tony Young
|
|
|
Please call when heading to job. Thank You! Dylan Schneider Phone #: ###-#### Inspection requested via web by Dylan Schneider,, need fire pass
|
BLD-Framing/Rough-in | 12/2/2014 | 12/3/2014 | 12/3/2014 | A | PEND |
Tony Young
|
|
|
Please call when heading to job. Thank You! Dylan Schneider Phone #: ###-#### Inspection requested via web by Dylan Schneider
|
BLD-Framing/Rough-in | 12/2/2014 | 12/2/2014 | 12/3/2014 | P | PART |
Tony Young
|
|
|
Please call when heading to job. Thank You! Dylan Schneider Phone #: ###-#### Inspection requested via web by Dylan Schneider,, some areas ok,, will go back to site on 3rd,, sprinklers are vwork in progress
|
BLD-Framing/Rough-in | 12/1/2014 | 12/2/2014 | 12/2/2014 | A | PEND |
Tony Young
|
|
|
Please call when heading to job. Thank You! Dylan Schneider Phone #: ###-#### Inspection requested via web by Dylan Schneider
|
BLD-Framing/Rough-in | 12/1/2014 | 12/1/2014 | 12/1/2014 | P | PART |
Tony Young
|
|
|
Please call when heading to job. Thank You! Dylan Schneider Phone #: ###-#### Inspection requested via web by Dylan Schneider,, correction notice posted,, need fire sprinklers passed,, point loads,, fasteners in connectors, etc
|
BLD-Framing/Rough-in | 11/29/2014 | 12/1/2014 | 12/1/2014 | A | DEFR |
Tony Young
|
|
|
Please call when heading to job. Thank You! Dylan Schneider Phone #: ###-#### Inspection requested via web by Dylan Schneider,, need trades
|
BLD-Wall Bracing | 10/6/2014 | 10/7/2014 | 10/7/2014 | A | PASS |
Tony Young
|
|
|
Dylan Phone #: ###-####,, exterior shear ok
|
BLD-Foundation | 7/18/2014 | 7/18/2014 | 7/18/2014 | P | PART |
Tony Young
|
|
|
Andy Phone #: ###-####,, pier columns ok
|
BLD-Footing | 7/15/2014 | 7/16/2014 | 7/16/2014 | A | PART |
Tony Young
|
|
|
Andy Phone #: ###-####,, pier and basement ftgs work in progress,, ok
|
BLD-Footing | 7/15/2014 | 7/16/2014 | 7/15/2014 | A | CANC |
Phil Shearer
|
|
|
|
BLD-Footing | 7/9/2014 | 7/10/2014 | 7/10/2014 | A | PART |
Tony Young
|
|
|
Andy Phone #: ###-####,, house ftgs ok
|
BLD-Foundation | 6/23/2014 | 6/24/2014 | 6/24/2014 | P | PART |
Jim Sly
|
|
|
Andy Phone #: ###-#### Bsmnt walls and footing pads for Pt. loads (Bsmnt slab) .........OK.
|
BLD-Footing | 6/16/2014 | 6/17/2014 | 6/17/2014 | A | PASS |
Tony Young
|
|
|
Andy-soil test is located at mail boxes Phone #: ###-####,, basement ftgs ok
|
BLD-Footing | 6/13/2014 | 6/16/2014 | 6/16/2014 | P | NR |
Tony Young
|
|
|
Andy-soil test is located at mail boxes Phone #: ###-####
|