BLD-Final | 10/15/2014 | 10/15/2014 | 10/15/2014 | P | PASS |
Jim Storey
|
|
|
Nate Phone #: ###-#### final ok
|
BLD-Final | 8/11/2014 | 8/12/2014 | 8/12/2014 | A | PART |
Jim Storey
|
|
|
nate Phone #: ###-####tco ok pending partitions in resaroom
|
FIRE-Final Inspection | 8/8/2014 | 8/11/2014 | 8/11/2014 | A | PASS |
Forrest France
|
|
|
C/N items finished. Fire life safety inspection completed satisfactory.
|
FIRE-Final Inspection | 8/8/2014 | 8/8/2014 | 8/8/2014 | P | PART |
Forrest France
|
|
|
Fire life safety final pending project related fire alarm permit work, repair of one EM light, post building address numbers, repair one exit sign.
|
BLD-Other | 7/30/2014 | 7/31/2014 | 7/31/2014 | A | PASS |
Jim Storey
|
|
|
Nate-Drag connection Phone #: ###-#### roof drag ok to cover.
|
BLD-Ceiling Grid Inspection | 7/24/2014 | 7/24/2014 | 7/24/2014 | P | PASS |
Jim Storey
|
|
|
Nate Phone #: ###-#### balance of ceillings ok/ drag strut hardware per drawing ok.
|
BLD-Ceiling Grid Inspection | 7/8/2014 | 7/8/2014 | 7/8/2014 | P | PASS |
Jim Storey
|
|
|
Nate Phone #: ###-#### ceillings ok allbur center rms ok to cover upon hvac/ele and fire arrpvals.
|
BLD-Framing/Rough-in | 6/24/2014 | 6/24/2014 | 6/24/2014 | P | PASS |
Jim Storey
|
|
|
Nate-fire wall Phone #: ###-#### coil strap nailling ok/ fire wall ok remove duct.
|
BLD-Framing/Rough-in | 6/12/2014 | 6/12/2014 | 6/12/2014 | P | PASS |
Jim Storey
|
|
|
Nate Phone #: ###-#### sheer ok
|
BLD-Other | 6/9/2014 | 6/9/2014 | 6/9/2014 | P | FAIL |
Jim Storey
|
|
|
1st layer sheet rock// Nate Phone #: ###-####
|
BLD-Framing/Rough-in | 5/28/2014 | 5/28/2014 | 5/28/2014 | P | PART |
Jim Storey
|
|
|
Nate Phone #: ###-#### need si for hold downs/ ok to one sde south end
|