BLD-Final | 12/11/2014 | 12/12/2014 | 12/12/2014 | A | PART |
Mike Jordan
|
|
|
Tyler Phone #: ###-####. Temp occ. Will be ok for perm occ. once zoning signs perm.
|
BLD-Final | 12/10/2014 | 12/10/2014 | 12/10/2014 | P | NR |
Mike Jordan
|
|
|
Tyler Phone #: ###-####
|
FIRE-Final Inspection | 12/9/2014 | 12/10/2014 | 12/10/2014 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 12/5/2014 | 12/5/2014 | 12/5/2014 | P | FAIL |
Troy Cobbley
|
|
|
Not ready for final yet but I did verify smoke alarms
|
BLD-Energy code compliance | 10/21/2014 | 10/22/2014 | 10/22/2014 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-####
|
BLD-Framing/Rough-in | 10/20/2014 | 10/21/2014 | 10/21/2014 | A | PASS |
Mike Jordan
|
|
|
Richard Phone #: ###-####
|
BLD-Energy code compliance | 10/16/2014 | 10/17/2014 | 10/17/2014 | P | PASS |
Mike Jordan
|
|
|
Richard Phone #: ###-####
|
BLD-Framing/Rough-in | 10/15/2014 | 10/16/2014 | 10/16/2014 | P | CANC |
Mike Jordan
|
|
|
Richard Phone #: ###-####. Wrong permit called in.
|
BLD-Wall Bracing | 9/18/2014 | 9/18/2014 | 9/18/2014 | P | PASS |
Mike Jordan
|
|
|
Ken Phone #: ###-####. Floor to floor straps, 1st floor shear walls ok.
|
BLD-Wall Bracing | 9/16/2014 | 9/17/2014 | 9/17/2014 | A | NR |
Jim Storey
|
|
|
Ken-exterior shear nailing Phone #: ###-####
|
BLD-Wall Bracing | 9/2/2014 | 9/3/2014 | 9/3/2014 | A | PASS |
Mike Jordan
|
|
|
Timm-would like at 11:00 if possible Phone #: ###-####. 2nd. floor interior and exterior shearwalls ok.
|
BLD-Framing/Rough-in | 8/28/2014 | 8/29/2014 | 8/29/2014 | A | CANC |
Phil Shearer
|
|
|
Ken Phone #: ###-####
|
BLD-Wall Bracing | 8/29/2014 | 8/29/2014 | 8/29/2014 | A | PASS |
Phil Shearer
|
|
|
Ken Phone #: ###-####. Interior shear wall
|
BLD-Other | 8/20/2014 | 8/21/2014 | 8/21/2014 | P | PASS |
Mike Jordan
|
|
|
Rebar - Ken Phone #: ###-####. INterior thickend footings.
|
BLD-Energy code compliance | 8/13/2014 | 8/13/2014 | 8/13/2014 | A | PASS |
Mike Jordan
|
|
|
###-#### Ashley. Rigid insulation at stemwall under slab on grade.
|
BLD-Energy code compliance | 8/12/2014 | 8/13/2014 | 8/13/2014 | A | FAIL |
Mike Jordan
|
|
|
ashley Phone #: ###-####. Remove all debries from building footprint. Rigid insulation to be attached in approved manner.
|
BLD-Foundation | 8/7/2014 | 8/11/2014 | 8/11/2014 | A | DONE |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|
BLD-Foundation | 8/8/2014 | 8/8/2014 | 8/8/2014 | P | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 8/6/2014 | 8/7/2014 | 8/7/2014 | P | PASS |
Mike Jordan
|
|
|
Manual Phone #: ###-####
|
BLD-Footing | 7/29/2014 | 7/30/2014 | 7/30/2014 | A | PASS |
Phil Shearer
|
|
|
Jerry Phone #: ###-####
|