BLD-Final | 4/9/2015 | 4/9/2015 | 4/9/2015 | P | PASS |
Mike Jordan
|
|
|
Tom Phone #: ###-####. Ok for perm occ.
|
BLD-Final | 3/25/2015 | 3/26/2015 | 3/26/2015 | P | PART |
Mike Jordan
|
|
|
tom Phone #: ###-####. ok for temp occ. Will be ok for perm occ. once elec. signs perm.
|
BLD-Final | 3/25/2015 | 3/25/2015 | 3/25/2015 | P | NR |
Mike Jordan
|
|
|
Tom Phone #: ###-####. Needs public works.
|
FIRE-Final Inspection | 3/25/2015 | 3/25/2015 | 3/25/2015 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Ceiling Grid Inspection | 2/23/2015 | 2/24/2015 | 2/24/2015 | A | PART |
Mike Jordan
|
|
|
Tom Phone #: ###-####. East half of grid ok, pending eelctrical and mech. rough in inspections.
|
BLD-Ceiling Grid Inspection | 2/5/2015 | 2/6/2015 | 2/6/2015 | P | PASS |
Mike Jordan
|
|
|
Tom Phone #: ###-####. West half only.
|
BLD-Framing/Rough-in | 1/29/2015 | 1/29/2015 | 1/29/2015 | P | PASS |
Mike Jordan
|
|
|
Tom Phone #: ###-####. Extrior steel soffit framing for front canopy.
|
BLD-Framing/Rough-in | 1/16/2015 | 1/16/2015 | 1/16/2015 | P | PASS |
Mike Jordan
|
|
|
barrell roof metal framing - Tom Phone #: ###-####. Barrell roof framing ok to cover.
|
BLD-Framing/Rough-in | 1/14/2015 | 1/15/2015 | 1/15/2015 | A | PART |
Mike Jordan
|
|
|
Tom Phone #: ###-####. Barrell vault framing. Contractor to provide aditional framing details from architect approving in place construction.
|
BLD-Framing/Rough-in | 1/5/2015 | 1/6/2015 | 1/6/2015 | A | PART |
Mike Jordan
|
|
|
Tom Phone #: ###-####. interior steel stud framed wall and shear walls, east half ok, pend. elec.
|
BLD-Energy code compliance | 12/9/2014 | 12/10/2014 | 12/10/2014 | A | PART |
Mike Jordan
|
|
|
Tom Phone #: ###-####. East wall at main entry, and west soffit ok to one side for barrell vault.
|
BLD-Energy code compliance | 12/3/2014 | 12/3/2014 | 12/3/2014 | P | PASS |
Mike Jordan
|
|
|
Tom Phone #: ###-####. Exterior walls from gridlines B to D.
|
BLD-Framing/Rough-in | 12/3/2014 | 12/3/2014 | 12/3/2014 | P | PASS |
Mike Jordan
|
|
|
Tom Phone #: ###-####. Interior steel stud framed walls from gridlines B to D.
|
BLD-Framing/Rough-in | 11/13/2014 | 11/18/2014 | 11/18/2014 | A | NR |
Mike Jordan
|
|
|
Dave Phone #: ###-#### (or tom ###-####). Needs electrical and plumbing rough in for interior walls, exterior walls ok.
|
FIRE-Conference | 11/7/2014 | 11/7/2014 | 11/7/2014 | P | DONE |
Troy Cobbley
|
|
|
Tom and I discussed fire dept access signage for the project.
|
BLD-Wall Bracing | 11/6/2014 | 11/7/2014 | 11/7/2014 | A | PASS |
Mike Jordan
|
|
|
Tom Phone #: ###-####. Exterior and interior shear walls ok.
|
BLD-Other | 11/3/2014 | 11/4/2014 | 11/4/2014 | A | PART |
Mike Jordan
|
|
|
welding// Tom Phone #: ###-####. Work in progress on roof deck and light guage weldin at shear wall locations.
|
BLD-Final | 10/31/2014 | 10/31/2014 | 10/31/2014 | P | CANC |
Mike Jordan
|
|
|
tom Phone #: ###-####
|
BLD-Framing/Rough-in | 10/31/2014 | 10/31/2014 | 10/31/2014 | P | PASS |
Mike Jordan
|
|
|
tom Phone #: ###-####. west half roof ok to coveer.
|
BLD-Framing/Rough-in | 10/27/2014 | 10/27/2014 | 10/27/2014 | P | PART |
Mike Jordan
|
|
|
Tom Phone #: ###-####. Exterior steel stud framed walls, west half only. Ok to cover pending special inspection on light guage steel welding.
|
BLD-Other | 10/14/2014 | 10/14/2014 | 10/14/2014 | P | PART |
Mike Jordan
|
|
|
welding, MTI will be out between 9-10am // Tom Phone #: ###-####. reviewed all special inspection reports to date.
|
BLD-Footing | 8/14/2014 | 8/15/2014 | 8/15/2014 | A | PART |
Mike Jordan
|
|
|
Footing Inspection for East portion of Building. MTI Scheduled for inspection @ 2 pm, concrete placement at 2:30 pm. Phone #: ###-#### Inspection requested via web by Rob Holtz. Work in progress on installing #10 vertical reinforcement for canopy, pending special inspection. Also reviewed all special inspection reports to date, ok.
|
BLD-Footing | 8/12/2014 | 8/13/2014 | 8/13/2014 | A | PASS |
Phil Shearer
|
|
|
Rob Phone #: ###-#### Footings north,south and west sides of the building
|