FIRE-Final Inspection | 8/21/2015 | 8/21/2015 | 8/21/2015 | A | PASS |
Jim Page
|
|
|
Life fire safety passed/complete
|
BLD-Final | 8/20/2015 | 8/21/2015 | 8/21/2015 | A | PASS |
Dave Hannah
|
|
|
Hello Jim, We are ready for final. Please call before heading to job if possible. thank you and see you tomorrow. Phone #: ###-#### Inspection requested via web by Derek Jackson
|
BLD-Final | 8/6/2015 | 8/7/2015 | 8/7/2015 | P | NR |
Jim Storey
|
|
|
Looking for final in the early afternoon 2:00ish after the Fire has passed. Thanks Jim Phone #: ###-#### Inspection requested via web by Derek Jackson
|
BLD-Final | 5/8/2015 | 5/8/2015 | 5/8/2015 | P | DONE |
Jim Storey
|
|
|
Thank you again Jim.. Phone #: ###-#### Inspection requested via web by Derek Jackson
|
BLD-Final | 5/6/2015 | 5/7/2015 | 5/8/2015 | P | PASS |
Jim Storey
|
|
|
Jim I am hoping to get my final shortly after lunch if that works for you. Kathy needs to inspect Fire Life/ Safety in the morning first. Thank you Derek Phone #: ###-#### Inspection requested via web by Derek Jackson temp ok pending all others.
|
FIRE-Final Inspection | 5/6/2015 | 5/7/2015 | 5/7/2015 | A | PART |
Katie Marron
|
|
|
Partial fire life safety pass for new portion of building. Items to fix before final: new inspection tags on 2 fire extinguishers, hang fire extinguisher located by electrical panels, complete install of emergency exit sign at side middle door, and fix back middle door that is jammed. Permit cannot be finaled until fire suppression tie in of existing building system is completed.
|
BLD-Conference | 4/2/2015 | 4/3/2015 | 4/3/2015 | A | PASS |
Jim Storey
|
|
|
Would like to meet to go over project for final. Thanks Jim... Phone #: ###-#### Inspection requested via web by Derek Jackson 10:00 appt.
|
BLD-Conference | 4/1/2015 | 4/2/2015 | 4/2/2015 | A | DEFR |
Jim Storey
|
|
|
Would like to meet to go over project for final. Thanks Jim... Phone #: ###-#### Inspection requested via web by Derek Jackson
|
BLD-Framing/Rough-in | 2/11/2015 | 2/12/2015 | 2/12/2015 | A | PASS |
Jim Storey
|
|
|
Framing inspection on riser room walls. corrections made.
Thank you Jim Phone #: ###-#### Inspection requested via web by Derek Jackson
|
BLD-Conference | 2/3/2015 | 2/4/2015 | 2/4/2015 | A | FAIL |
Jim Storey
|
|
|
framing inspection for riser room at North East corner of building. Phone #: ###-#### Inspection requested via web by Derek Jackson
|
BLD-Wall cover | 1/5/2015 | 1/5/2015 | 1/5/2015 | P | PASS |
Jim Storey
|
|
|
I am not on site but the wall in need of inspection is located on the south east corner where the overhang is. 3 hour fire wall same as the main fire wall that you have inspected.
Thanks Phone #: ###-#### Inspection requested via web by Derek Jackson
|
BLD-Framing/Rough-in | 1/5/2015 | 1/5/2015 | 1/5/2015 | P | PASS |
Jim Storey
|
|
|
I am not on site but the wall in need of inspection is located on the south east corner where the overhang is. 3 hour fire wall same as the main fire wall that you have inspected.
Thanks Phone #: ###-#### Inspection requested via web by Derek Jackson
|
BLD-Energy code compliance | 12/19/2014 | 12/19/2014 | 12/19/2014 | P | PASS |
Jim Storey
|
|
|
Insulation inspection on North wall were the roll up door was removed. This location is where the existing and the new come together.
\Thank you Derek Phone #: ###-#### Inspection requested via web by Derek Jackson
|
BLD-Wall cover | 12/19/2014 | 12/19/2014 | 12/19/2014 | P | PASS |
Jim Storey
|
|
|
drywall inspection where the existing roll up door was removed on the North wall where the new addition and existing building come together. This is a continuation of what was already inspected on the other section of wall.
Thank you! Derek Phone #: ###-#### Inspection requested via web by Derek Jackson
|
BLD-Framing/Rough-in | 12/19/2014 | 12/19/2014 | 12/19/2014 | P | PASS |
Jim Storey
|
|
|
Framing inspection where the existing roll up door was removed on the North wall where the new addition and existing building come together. This is a continuation of what was already inspected on the other section of wall.
Thank you! Derek Phone #: ###-#### Inspection requested via web by Derek Jackson
|
BLD-Wall cover | 12/12/2014 | 12/12/2014 | 12/12/2014 | P | PASS |
Jim Storey
|
|
|
Outside East exterior wall. I missed the am inspection dead line however we are ready to side now. I thought this was passed but noticed the inspection said partial. Thank you again Phone #: ###-#### Inspection requested via web by Derek Jackson
|
BLD-Energy code compliance | 12/10/2014 | 12/10/2014 | 12/10/2014 | P | PASS |
Dave Hannah
|
|
|
Second half of insulation inspection. Thank you Mike. Phone #: ###-#### Inspection requested via web by Derek Jackson
|
BLD-Energy code compliance | 12/4/2014 | 12/4/2014 | 12/4/2014 | P | PART |
Mike Jordan
|
|
|
Looking for insulation cover inspection. Phone #: ###-#### Inspection requested via web by Derek Jackson. 5 inch mineral wool insulation at 3hr. firewall, south east half only.
|
BLD-Wall cover | 11/26/2014 | 11/26/2014 | 11/27/2014 | P | PART |
Mike Jordan
|
|
|
East wall first layer of drywall inspection on 3 hour wall. Call if there is any issues and thank you. Hope you have a good Thanksgiving Phone #: ###-#### Inspection requested via web by Derek Jackson. wip.
|
BLD-Framing/Rough-in | 11/12/2014 | 11/13/2014 | 11/13/2014 | A | PASS |
Jim Storey
|
|
|
###-#### Inspection requested via web by Derek Jackson
|
BLD-Framing/Rough-in | 11/7/2014 | 11/10/2014 | 11/12/2014 | P | DEFR |
Jim Storey
|
|
|
Looking for a framing inspection for the East wall new framing. I will not be on site so if you need access to the plans there is a lock box on trailer hand rail and the combo is my last four digits of my phone number. 6692 Thank you again, Derek Jackson Phone #: ###-#### Inspection requested via web by Derek Jackson
|
BLD-Framing/Rough-in | 10/20/2014 | 10/20/2014 | 10/20/2014 | P | PASS |
Jim Storey
|
|
|
Second layer of drywall to be inspected on existing building. Phone #: ###-#### Inspection requested via web by Derek Jackson
|
BLD-Framing/Rough-in | 10/9/2014 | 10/13/2014 | 10/13/2014 | A | PART |
Jim Storey
|
|
|
This is for the drywall inspection that we talked about on Thursday. See you Monday. Thank you 503*###-#### Phone #: ###-#### Inspection requested via web by Derek Jackson 3hr 1st later ok
|
BLD-Framing/Rough-in | 10/8/2014 | 10/9/2014 | 10/9/2014 | A | PART |
Jim Storey
|
|
|
Spoke with Jim Storey about a am inspection. Please give me a 30 minute call ahead if possible. Thank you Phone #: ###-#### Inspection requested via web by Derek Jackson sfd in place ok 3 layer membrane.
|
BLD-Framing/Rough-in | 10/6/2014 | 10/7/2014 | 10/7/2014 | A | FAIL |
Jim Storey
|
|
|
Vic Phone #: ###-#### arch to address opening protrction and wall listing.
|