BLD-Final | 3/3/2015 | 3/4/2015 | 3/4/2015 | A | PASS |
Phil Shearer
|
|
|
Shop blg Phone #: ###-#### Inspection requested via web by Murph Naughtin
|
FIRE-Final Inspection | 3/2/2015 | 3/2/2015 | 3/3/2015 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Wall cover | 2/5/2015 | 2/5/2015 | 2/5/2015 | P | PASS |
Phil Shearer
|
|
|
Hard lid and wall cover @ Mezzanine in Shop- building #2 Phone #: ###-#### Inspection requested via web by Philip Allen Pending HVAC inspection
|
BLD-Framing/Rough-in | 1/28/2015 | 1/29/2015 | 1/29/2015 | A | PART |
Jim Sly
|
|
|
Shop building framing for demising wall and mezzanine. Phone #: ###-#### Inspection requested via web by Philip Allen Appears OK Note 1hr walls at stairs and riser room........walk thru ......OK to 1 side Need all trade rough-in approvals.
|
BLD-Concrete | 1/7/2015 | 1/8/2015 | 1/8/2015 | P | PASS |
Phil Shearer
|
|
|
Pre- concrete rebar for Slab on Deck for Mezzanine @ Shop Phone #: ###-#### Inspection requested via web by Philip Allen. Per MTI inspection.
|
BLD-Concrete | 12/5/2014 | 12/8/2014 | 12/8/2014 | A | PASS |
Phil Shearer
|
|
|
Pre- concrete for shop. Phone #: ###-#### Inspection requested via web by Philip Allen
|
BLD-Foundation | 10/17/2014 | 10/20/2014 | 10/20/2014 | A | PART |
Jim Storey
|
|
|
Concrete at 2:30 Phone #: ###-#### Inspection requested via web by Kevin Honeycutt wip si to verify rebar.
|
BLD-Foundation | 10/8/2014 | 10/9/2014 | 10/9/2014 | P | PASS |
Phil Shearer
|
|
|
OK per MTI's approval
|