BLD-Final | 10/21/2015 | 10/22/2015 | 10/22/2015 | A | PASS |
Dave Hannah
|
|
|
Abel Phone #: ###-####
|
BLD-Aging Inspection | 9/30/2015 | 9/30/2015 | 9/30/2015 | | PEND |
Dave Hannah
|
|
|
|
BLD-Conference | 7/29/2015 | 7/29/2015 | 7/29/2015 | A | DONE |
Bob Archibald
|
|
|
Confirmed with electrical contractor and engineer that the fire alarm system wiring has been extended to a point within the units and is available for upgrade when necessary to sustain visual notification for rooms occupied by hearing impaired tenants. ICC A117.1-2009 section 1006.2 and 1006.3.
|
FIRE-Final Inspection | 7/23/2015 | 7/24/2015 | 7/24/2015 | A | PASS |
Jim Page
|
|
|
Temporary occupancy approved for life fire safety, verbally confirmed with electrical contractor that the fire alarm system has capability to sustain visual notification for rooms occupied by hearing impaired tenants. Electrical contractor needs to provide information on heat tape used on fire sprinkler system before final sign off can occur.
*Above item confirmed - 325*
|
BLD-Final | 7/23/2015 | 7/24/2015 | 7/24/2015 | P | PEND |
Dave Hannah
|
|
|
Walk for final Phone #: ###-#### Inspection requested via web by Julian Lopez. Needs other trades ot go perm occ needs to install perm signage, type A ada units need to meet ansi 117.1 chapter 10 section 1006. ok for temp occ.
|
BLD-Ceiling Grid Inspection | 6/29/2015 | 6/29/2015 | 6/30/2015 | P | PASS |
Dave Hannah
|
|
|
corridor Phone #: ###-#### Inspection requested via web by Julian Lopez
|
BLD-Ceiling Grid Inspection | 6/24/2015 | 6/24/2015 | 6/25/2015 | P | PASS |
Dave Hannah
|
|
|
Corridor level 4 Phone #: ###-#### Inspection requested via web by Julian Lopez
|
BLD-Ceiling Grid Inspection | 6/17/2015 | 6/17/2015 | 6/18/2015 | P | PASS |
Dave Hannah
|
|
|
Ceiling grid Phone #: ###-#### Inspection requested via web by Julian Lopez
|
BLD-Other | 4/28/2015 | 4/28/2015 | 4/28/2015 | P | PASS |
Dave Hannah
|
|
|
level 4 soffits. Ready now. Phone #: ###-#### Inspection requested via web by Julian Lopez
|
BLD-Energy code compliance | 4/21/2015 | 4/21/2015 | 4/22/2015 | P | PASS |
Dave Hannah
|
|
|
Am if possible. level 2 soffits Phone #: ###-#### Inspection requested via web by Julian Lopez
|
BLD-Other | 4/13/2015 | 4/14/2015 | 4/14/2015 | A | PASS |
Dave Hannah
|
|
|
Soffit inspection level 3 Phone #: ###-#### Inspection requested via web by Julian Lopez
|
BLD-Energy code compliance | 4/8/2015 | 4/8/2015 | 4/9/2015 | P | PASS |
Dave Hannah
|
|
|
Level 4 insulation. Phone #: ###-#### Inspection requested via web by Julian Lopez
|
BLD-Framing/Rough-in | 4/3/2015 | 4/3/2015 | 4/3/2015 | P | PASS |
Dave Hannah
|
|
|
Framing inspection. If AM possible. Phone #: ###-#### Inspection requested via web by Julian Lopez
|
BLD-Energy code compliance | 3/26/2015 | 3/26/2015 | 3/27/2015 | P | PASS |
Dave Hannah
|
|
|
Area 1 level 3 Insulation Phone #: ###-#### Inspection requested via web by Julian Lopez
|
BLD-Framing/Rough-in | 3/25/2015 | 3/25/2015 | 3/25/2015 | P | NR |
Dave Hannah
|
|
|
Area 2 level 4 framing inspection. Phone #: ###-#### Inspection requested via web by Julian Lopez
|
BLD-Framing/Rough-in | 3/23/2015 | 3/23/2015 | 3/23/2015 | P | PASS |
Dave Hannah
|
|
|
Area 1 lvl 3. framing and insulation lvl 2 Phone #: ###-#### Inspection requested via web by Julian Lopez
|
BLD-Framing/Rough-in | 3/19/2015 | 3/20/2015 | 3/20/2015 | A | PART |
Dave Hannah
|
|
|
Framing inspection level 2,3, Phone #: ###-#### Inspection requested via web by Julian Lopez 2nd floor only ok to insulate
|
BLD-Framing/Rough-in | 3/13/2015 | 3/13/2015 | 3/18/2015 | P | PASS |
Dave Hannah
|
|
|
Area 2 lvl 4 shear wall and rest of showers. Phone #: ###-#### Inspection requested via web by Julian Lopez
|
BLD-Framing/Rough-in | 3/6/2015 | 3/6/2015 | 3/6/2015 | P | CANC |
Dave Hannah
|
|
|
Exterior walls lvl 4 Phone #: ###-#### Inspection requested via web by Julian Lopez
|
BLD-Framing/Rough-in | 2/25/2015 | 2/26/2015 | 2/26/2015 | A | PASS |
Dave Hannah
|
|
|
lvl 3 inside exterior walls. Phone #: ###-#### Inspection requested via web by Julian Lopez
|
BLD-Conference | 2/17/2015 | 2/18/2015 | 2/18/2015 | A | PART |
Dave Hannah
|
|
|
Framing inspection outer walls. level 2 Phone #: ###-#### Inspection requested via web by Julian Lopez ok to insulate ext walls.
|
BLD-Framing/Rough-in | 1/30/2015 | 1/30/2015 | 1/30/2015 | P | PART |
Dave Hannah
|
|
|
check corridor framing prior to drywall lvl 4 Phone #: ###-#### Inspection requested via web by Julian Lopez ok to insulate ceiling 4th floor corridor.
|
BLD-Wall cover | 1/27/2015 | 1/27/2015 | 1/27/2015 | A | CANC |
Dave Hannah
|
|
|
|
BLD-Wall Bracing | 1/27/2015 | 1/27/2015 | 1/27/2015 | A | PART |
Dave Hannah
|
|
|
ok to cover ext
|
BLD-Framing/Rough-in | 1/15/2015 | 1/16/2015 | 1/21/2015 | P | PASS |
Dave Hannah
|
|
|
Requesting a sheer nailing inspection on the exterior of the building. Thanks. Phone #: ###-#### Inspection requested via web by Tony Inserra
|
BLD-Framing/Rough-in | 1/20/2015 | 1/20/2015 | 1/21/2015 | P | PASS |
Dave Hannah
|
|
|
Requesting sheer wall nailing ; simpson strapping inspection. Phone #: ###-#### Inspection requested via web by Tony Inserra ext ok to cover
|
BLD-Framing/Rough-in | 1/12/2015 | 1/12/2015 | 1/13/2015 | P | CANC |
Dave Hannah
|
|
|
Requesting a framing inspection for corridor pree-rock 2nd floor. Phone #: ###-#### Inspection requested via web by Tony Inserra ok to rock top 2ft of corr in area two
|
BLD-Framing/Rough-in | 1/6/2015 | 1/7/2015 | 1/7/2015 | A | PASS |
Dave Hannah
|
|
|
Requesting a roof sheeting nailing inspection. Thanks. Phone #: ###-#### Inspection requested via web by Tony Inserra
|
BLD-Framing/Rough-in | 12/29/2014 | 12/29/2014 | 12/29/2014 | P | PEND |
Dave Hannah
|
|
|
Requesting a roof nailing inspection, on N.W. to N. E section of roof sheeting. Thank you. Phone #: ###-#### Inspection requested via web by Tony Inserra roof coverd in snow
|